30800190722026↗
City of Durango received this grant or assistance award from Federal Aviation Administration: $2.22M obligated so far for airport infrastructure grants. Its latest action was on 2026-02-10.
Key facts · data as of Nov 25, 2026
- Recipient
- City of Durango
- Awarding agency
- Federal Aviation Administration (Department of Transportation)
- Obligated to date
- $2.22M
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 25, 2026.
Cite this page: SpendQuery, Award 30800190722026, data as of Nov 25, 2026, https://spendquery.com/award?id=ASST_NON_30800190722026_069
City of Durango: all federal awards · Department of Transportation: spending
PURPOSE: EXPAND TERMINAL; RECONSTRUCT TERMINAL. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT EXPANDS THE EXISTING TERMINAL BY 19,728 SQUARE FEET, INCLUDING NEW GATES, PASSENGER HOLD ROOMS, TSA PASSENGER SCREENING AND BAGGAGE CLAIM AREAS. THIS EXPANSION WILL FACILITATE THE MOVEMENT OF PASSENGERS AND BAGGAGE TO BRING THE AIRPORT INTO CONFORMITY WITH CURRENT STANDARDS. THIS PROJECT RECONSTRUCTS 21,476 SQUARE FEET OF THE EXISTING TERMINAL, INCLUDING GATE AREAS, HOLD ROOMS, AND RESTROOMS THAT HAVE REACHED THE END OF THEIR USEFUL LIVES. THIS GRANT FUNDS PHASE 3, WHICH CONSISTS OF 2,300 SQUARE FEET OF EXPANSION. THIS GRANT FUNDS PHASE 3, WHICH CONSISTS OF 2,450 SQUARE FEET OF RECONSTRUCTION. INTENDED BENEFICIARY: THIS GRANT WILL PROVIDE FEDERAL FUNDING FOR AIRPORTS ASSOCIATED WITH DURANGO, COLORADO.
What it is
- Program
- Airport Infrastructure Grants (Assistance Listing 20.117)
- Where the work is
- Los Angeles Plata, CO · district CO-03
- Funding law
- Infrastructure law (IIJA)
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
1 action since 2026-02-10. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-02-10 | 00 | New award | $2.22M | PURPOSE: EXPAND TERMINAL; RECONSTRUCT TERMINAL. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT EXPANDS THE EXISTING TERMINAL BY 19,728 SQUARE FEET, INCLUDING NEW GATES, PASSENGER HOLD ROOMS, TSA PASSENGER SCREENING AND BAGGAGE CLAIM AREAS. THIS… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗