32000890382026↗
Wichita Airport Authority received this grant or assistance award from Federal Aviation Administration: $1.13M obligated so far for airport improvement program. Its latest action was on 2026-08-28.
Key facts · data as of Nov 14, 2026
- Recipient
- Wichita Airport Authority
- Awarding agency
- Federal Aviation Administration (Department of Transportation)
- Obligated to date
- $1.13M
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 14, 2026.
Cite this page: SpendQuery, Award 32000890382026, data as of Nov 14, 2026, https://spendquery.com/award?id=ASST_NON_32000890382026_069
Wichita Airport Authority: all federal awards · Department of Transportation: spending
PURPOSE: RECONSTRUCT TAXIWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS GRANT INCLUDES FUTURE YEAR FUNDING PLANNED FOR THIS PROJECT, SUBJECT TO APPROPRIATIONS. THIS PROJECT RECONSTRUCTS 550 FEET OF EXISTING PAVED TAXIWAY A-2 PAVEMENT THAT HAS REACHED THE END OF ITS USEFUL LIFE. THIS GRANT FUNDS A PORTION OF THE TOTAL PROJECT. THIS GRANT IS ASSOCIATED WITH INFRASTRUCTURE INVESTMENT AND JOBS ACT GRANT THAT FUNDS THE REMAINING ELIGIBLE PORTION OF THIS PROJECT. INTENDED BENEFICIARY: THIS GRANT WILL PROVIDE FEDERAL FUNDING FOR AIRPORTS ASSOCIATED WITH WICHITA, KANSAS.
What it is
- Program
- Airport Improvement Program (Assistance Listing 20.116)
- Where the work is
- Sedgwick, KS · district KS-04
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
1 action since 2026-08-28. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-28 | 00 | New award | $1.13M | PURPOSE: RECONSTRUCT TAXIWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS GRANT INCLUDES FUTURE YEAR FUNDING PLANNED FOR THIS PROJECT, SUBJECT TO APPROPRIATIONS. THIS PROJECT RECONSTRUCTS 550 FEET OF EXISTING PAVED TAXIWAY A-2 PAVEMENT THAT HAS… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-14). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗