32500280412024↗
Town of Mansfield received this grant or assistance award from Federal Aviation Administration: $377.9K obligated so far for airport improvement program, infrastructure investment and jobs act programs, and covid-19 airports programs. Its latest action was on 2025-11-12.
Key facts · data as of Nov 5, 2026
- Recipient
- Town of Mansfield
- Awarding agency
- Federal Aviation Administration (Department of Transportation)
- Obligated to date
- $377.9K
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 5, 2026.
Cite this page: SpendQuery, Award 32500280412024, data as of Nov 5, 2026, https://spendquery.com/award?id=ASST_NON_32500280412024_069
Town of Mansfield: all federal awards · Department of Transportation: spending
PURPOSE: RECONSTRUCT TAXIWAY; RECONSTRUCT RUNWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT RECONSTRUCTS 3,500 FEET OF EXISTING PAVED RUNWAY 14/32 THAT HAS REACHED THE END OF ITS USEFUL LIFE. THIS PROJECT RECONSTRUCTS 3,500 FEET OF THE EXISTING PAVED TAXIWAY A PAVEMENT THAT HAS REACHED THE END OF ITS USEFUL LIFE. THIS GRANT FUNDS THE FIRST PHASE, WHICH CONSISTS OF DESIGN. INTENDED BENEFICIARY: THIS GRANT WILL PROVIDE FEDERAL FUNDING FOR AIRPORTS ASSOCIATED WITH MANSFIELD, MASSACHUSETTS.
What it is
- Program
- Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and Covid-19 Airports Programs (Assistance Listing 20.106)
- Where the work is
- Bristol, MA · district MA-04
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
2 actions since 2024-08-26. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-11-12 | 01 | Revision | -$1.1K | PURPOSE: RECONSTRUCT TAXIWAY; RECONSTRUCT RUNWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT RECONSTRUCTS 3,500 FEET OF EXISTING PAVED RUNWAY 14/32 THAT HAS REACHED THE END OF ITS USEFUL LIFE. THIS PROJECT RECONSTRUCTS 3,500 FEET OF THE… |
| 2024-08-26 | 00 | New award | $379.0K | PURPOSE: RECONSTRUCT TAXIWAY; RECONSTRUCT RUNWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT RECONSTRUCTS 3,500 FEET OF EXISTING PAVED RUNWAY 14/32 THAT HAS REACHED THE END OF ITS USEFUL LIFE. THIS PROJECT RECONSTRUCTS 3,500 FEET OF THE… |