33900210402026↗

Cuyahoga County received this grant or assistance award from Federal Aviation Administration: $5.39M obligated so far for airport improvement program. Its latest action was on 2026-08-03.

Key facts · data as of Nov 5, 2026

Recipient
Cuyahoga County
Awarding agency
Federal Aviation Administration (Department of Transportation)
Obligated to date
$5.39M

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 5, 2026.

Cite this page: SpendQuery, Award 33900210402026, data as of Nov 5, 2026, https://spendquery.com/award?id=ASST_NON_33900210402026_069

PURPOSE: SHIFT TAXIWAY; RECONSTRUCT TAXIWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT RECONSTRUCTS 263 FEET OF EXISTING PAVED TAXIWAYS B2, B3, AND B4 PAVEMENT THAT HAVE REACHED THE END OF THEIR USEFUL LIVES. THIS PROJECT SHIFTS EXISTING PAVED TAXIWAY A BY 25 FEET TO BRING THE AIRPORT INTO CONFORMITY WITH CURRENT STANDARDS. THIS GRANT FUNDS PHASE 5, WHICH CONSISTS OF THE CONSTRUCTION OF 3,350 FEET OF PAVEMENT AND LIGHTING. THIS GRANT FUNDS THE FINAL PHASE, WHICH CONSISTS OF THE RECONSTRUCTION OF PAVEMENT AND LIGHTING. INTENDED BENEFICIARY: THIS GRANT WILL PROVIDE FEDERAL FUNDING FOR AIRPORTS ASSOCIATED WITH CLEVELAND, OHIO.

Project Grant (B) · Federal Aviation Administration · to Cuyahoga County (UEI GWKMA1HNL1Y1) · data as of 2026-11-05

Obligated to date$5.39M1 action
Period2026-08-03 → 2026-08-03first to last action

What it is

Program
Airport Improvement Program (Assistance Listing 20.116)
Where the work is
Cuyahoga, OH · district OH-11

Obligations by fiscal year

FY2026$5.39M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subrecipients: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

1 action since 2026-08-03. Each is a modification or amendment with the money it added or took back.

DateAmendmentKindAmountWhat the agency wrote
2026-08-0300New award$5.39MPURPOSE: SHIFT TAXIWAY; RECONSTRUCT TAXIWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT RECONSTRUCTS 263 FEET OF EXISTING PAVED TAXIWAYS B2, B3, AND B4 PAVEMENT THAT HAVE REACHED THE END OF THEIR USEFUL LIVES. THIS PROJECT SHIFTS EXISTING…