34100070362024↗
City of Bend received this grant or assistance award from Federal Aviation Administration: $181.6K obligated so far for airport improvement program, infrastructure investment and jobs act programs, and covid-19 airports programs. Its latest action was on 2026-07-30.
Key facts · data as of Nov 14, 2026
- Recipient
- City of Bend
- Awarding agency
- Federal Aviation Administration (Department of Transportation)
- Obligated to date
- $181.6K
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 14, 2026.
Cite this page: SpendQuery, Award 34100070362024, data as of Nov 14, 2026, https://spendquery.com/award?id=ASST_NON_34100070362024_069
City of Bend: all federal awards · Department of Transportation: spending
PURPOSE: REHABILITATE TAXIWAY; INSTALL AIRFIELD GUIDANCE SIGNAGE; INSTALL TAXIWAY LIGHTING; REHABILITATE RUNWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT INSTALLS A NEW TAXIWAY A & B LIGHTING SYSTEM TO ENHANCE SAFE AIRFIELD OPERATIONS DURING LOW VISIBILITY CONDITIONS. . THIS PROJECT INSTALLS NEW AIRFIELD SIGNAGES TO BRING THE AIRPORT INTO CONFORMITY WITH CURRENT STANDARDS. THIS PROJECT REHABILITATES 120 FEET OF RUNWAY 16/34 PAVEMENT MARKING TO ENHANCE SAFE AIRFIELD OPERATIONS. THIS PROJECT REHABILITATES 13,000 FEET OF THE EXISTING TAXIWAY A & B PAVEMENT TO EXTEND ITS USEFUL LIFE. THIS GRANT FUNDS A PORTION OF PHASE 1, WHICH CONSISTS OF DESIGN. THIS GRANT FUNDS A PORTION OF PHASE 1, WHICH CONSISTS OF DESIGN. . THIS GRANT FUNDS A PORTION PHASE 1, WHICH CONSISTS OF DESIGN. . THIS PROJECT IS ASSOCIATED WITH A BIPARTISAN INFRASTRUCTURE LAW AIRPORT INFRASTRUCTURE GRANT THAT FUNDS THE REMAINING ELIGIBLE PORTION OF THE PROJECT. INTENDED BENEFICIARY: THIS GRANT WILL PROVIDE FEDERAL FUNDING FOR AIRPORTS ASSOCIATED WITH BEND, OREGON.
What it is
- Program
- Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and Covid-19 Airports Programs (Assistance Listing 20.106)
- Where the work is
- Crook, OR · district OR-02
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
2 actions since 2024-07-08. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-30 | 01 | Revision | -$1.2K | PURPOSE: RECONSTRUCT RUNWAY SIGNAGE; REHABILITATE TAXIWAY; INSTALL AIRFIELD GUIDANCE SIGNAGE; INSTALL TAXIWAY LIGHTING. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT INSTALLS NEW AIRFIELD SIGNAGES TO BRING THE AIRPORT INTO CONFORMITY WITH… |
| 2024-07-08 | 00 | New award | $182.8K | PURPOSE: REHABILITATE TAXIWAY; INSTALL AIRFIELD GUIDANCE SIGNAGE; INSTALL TAXIWAY LIGHTING; REHABILITATE RUNWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT INSTALLS A NEW TAXIWAY A & B LIGHTING SYSTEM TO ENHANCE SAFE AIRFIELD OPERATIONS… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-14). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗