34200820562026↗
Allegheny County Airport Authority received this grant or assistance award from Federal Aviation Administration: $7.29M obligated so far for airport improvement program. Its latest action was on 2026-09-16.
Key facts · data as of Nov 14, 2026
- Recipient
- Allegheny County Airport Authority
- Awarding agency
- Federal Aviation Administration (Department of Transportation)
- Obligated to date
- $7.29M
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 14, 2026.
Cite this page: SpendQuery, Award 34200820562026, data as of Nov 14, 2026, https://spendquery.com/award?id=ASST_NON_34200820562026_069
Allegheny County Airport Authority: all federal awards · Department of Transportation: spending
PURPOSE: CONSTRUCT/EXTEND SAFETY AREA. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT EXTENDS THE RUNWAY 10-28 SAFETY AREA AT BOTH RUNWAY ENDS TO ENHANCE SAFETY. THIS GRANT FUNDS PHASE 8, WHICH CONSISTS OF THE PLACEMENT OF 122,900 CUBIC YARDS OF FILL. NON-14 CFR PART 139 CERTIFICATED AIRPORTS WERE NOT SUBJECT TO THE RUNWAY SAFETY AREA DEADLINE OF DECEMBER 31, 2015, AND SOME AIRPORTS, INCLUDING THIS ONE, CONTINUE TO PURSUE FURTHER IMPROVEMENTS AS THEY BECOME FEASIBLE. INTENDED BENEFICIARY: THIS GRANT WILL PROVIDE FEDERAL FUNDING FOR AIRPORTS ASSOCIATED WITH WEST MIFFLIN, PENNSYLVANIA.
What it is
- Program
- Airport Improvement Program (Assistance Listing 20.116)
- Where the work is
- Allegheny, PA · district PA-17
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
1 action since 2026-09-16. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-16 | 00 | New award | $7.29M | PURPOSE: CONSTRUCT/EXTEND SAFETY AREA. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT EXTENDS THE RUNWAY 10-28 SAFETY AREA AT BOTH RUNWAY ENDS TO ENHANCE SAFETY. THIS GRANT FUNDS PHASE 8, WHICH CONSISTS OF THE PLACEMENT OF 122,900 CUBIC YARDS OF… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-14). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗