34500650732025↗
County of Horry received this grant or assistance award from Federal Aviation Administration: $44.01M obligated so far for airport improvement program, infrastructure investment and jobs act programs, and covid-19 airports programs. Its latest action was on 2026-03-10.
Key facts · data as of Nov 14, 2026
- Recipient
- County of Horry
- Awarding agency
- Federal Aviation Administration (Department of Transportation)
- Obligated to date
- $44.01M
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 14, 2026.
Cite this page: SpendQuery, Award 34500650732025, data as of Nov 14, 2026, https://spendquery.com/award?id=ASST_NON_34500650732025_069
County of Horry: all federal awards · Department of Transportation: spending
PURPOSE: SHIFT TAXIWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS GRANT INCLUDES FUTURE YEAR FUNDING PLANNED FOR THIS PROJECT, SUBJECT TO APPROPRIATIONS. THIS PROJECT SHIFTS EXISTING PAVED TAXIWAY B BY 390 FEET TO BRING THE AIRPORT INTO CONFORMITY WITH CURRENT STANDARDS. THIS GRANT FUNDS PHASE 2, WHICH CONSISTS OF 7,469 FEET. INTENDED BENEFICIARY: THIS GRANT WILL PROVIDE FEDERAL FUNDING FOR AIRPORTS ASSOCIATED WITH MYRTLE BEACH, SOUTH CAROLINA.
What it is
- Program
- Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and Covid-19 Airports Programs (Assistance Listing 20.106)
- Where the work is
- Horry, SC · district SC-07
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
2 actions since 2025-09-24. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-10 | 01 | Continuation | $1.98M | PURPOSE: SHIFT TAXIWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS GRANT INCLUDES FUTURE YEAR FUNDING PLANNED FOR THIS PROJECT, SUBJECT TO APPROPRIATIONS. THIS PROJECT SHIFTS EXISTING PAVED TAXIWAY B BY 390 FEET TO BRING THE AIRPORT INTO CONFORMITY… |
| 2025-09-24 | 00 | New award | $42.04M | PURPOSE: SHIFT TAXIWAY. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS GRANT INCLUDES FUTURE YEAR FUNDING PLANNED FOR THIS PROJECT, SUBJECT TO APPROPRIATIONS. THIS PROJECT SHIFTS EXISTING PAVED TAXIWAY B BY 390 FEET TO BRING THE AIRPORT INTO CONFORMITY… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-14). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗