34600440552026↗

City of Pierre received this grant or assistance award from Federal Aviation Administration: $2.34M obligated so far for airport improvement program. Its latest action was on 2026-09-09.

Key facts · data as of Nov 19, 2026

Recipient
City of Pierre
Awarding agency
Federal Aviation Administration (Department of Transportation)
Obligated to date
$2.34M

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 19, 2026.

Cite this page: SpendQuery, Award 34600440552026, data as of Nov 19, 2026, https://spendquery.com/award?id=ASST_NON_34600440552026_069

PURPOSE: RESEAL/RESURFACE TAXIWAY; CONSTRUCT TAXIWAY; INSTALL TAXIWAY LIGHTING. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT CONSTRUCTS NEW 7,300 FOOT TAXIWAY C TO BRING THE AIRPORT INTO CONFORMITY WITH CURRENT STANDARDS. THIS PROJECT INSTALLS NEW LIGHTING ON TAXIWAY C TO BRING THE AIRPORT INTO CONFORMITY WITH CURRENT STANDARDS. THIS PROJECT RESEALS 2,200 FEET OF EXISTING TAXIWAY C PAVEMENT AT A NONPRIMARY AIRPORT TO EXTEND ITS USEFUL LIFE. THIS GRANT FUNDS PHASE 2, WHICH CONSISTS OF CONSTRUCTION OF 4,400 FEET OF LIGHTING. THIS GRANT FUNDS PHASE 3, WHICH CONSISTS OF CONSTRUCTION OF SITE STORM WATER DRAINAGE AND CONSTRUCTION ENGINEERING. INTENDED BENEFICIARY: THIS GRANT WILL PROVIDE FEDERAL FUNDING FOR AIRPORTS ASSOCIATED WITH PIERRE, SOUTH DAKOTA.

Formula Grant (A) · Federal Aviation Administration · to City of Pierre (UEI GADTHSKWGJS8) · data as of 2026-11-19

Obligated to date$2.34M1 action
Period2026-09-09 → 2026-09-09first to last action

What it is

Program
Airport Improvement Program (Assistance Listing 20.116)
Where the work is
Hughes, SD · district SD-00

Obligations by fiscal year

FY2026$2.34M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subrecipients: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

1 action since 2026-09-09. Each is a modification or amendment with the money it added or took back.

DateAmendmentKindAmountWhat the agency wrote
2026-09-0900New award$2.34MPURPOSE: RESEAL/RESURFACE TAXIWAY; CONSTRUCT TAXIWAY; INSTALL TAXIWAY LIGHTING. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT CONSTRUCTS NEW 7,300 FOOT TAXIWAY C TO BRING THE AIRPORT INTO CONFORMITY WITH CURRENT STANDARDS. THIS PROJECT INSTALLS…

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-19). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗