35500520722026↗
Marathon County received this grant or assistance award from Federal Aviation Administration: $2.86M obligated so far for airport improvement program. Its latest action was on 2026-08-24.
Key facts · data as of Nov 5, 2026
- Recipient
- Marathon County
- Awarding agency
- Federal Aviation Administration (Department of Transportation)
- Obligated to date
- $2.86M
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 5, 2026.
Cite this page: SpendQuery, Award 35500520722026, data as of Nov 5, 2026, https://spendquery.com/award?id=ASST_NON_35500520722026_069
Marathon County: all federal awards · Department of Transportation: spending
PURPOSE: RECONSTRUCT TAXILANE; REHABILITATE APRON; RECONSTRUCT APRON. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT RECONSTRUCTS 239 FEET OF EXISTING TAXILANE 3 PAVEMENT THAT HAS REACHED THE END OF ITS USEFUL LIFE. THIS PROJECT RECONSTRUCTS 7,900 SQUARE YARDS OF THE CENTER SECTION OF EXISTING GENERAL AVIATION APRON PAVEMENT THAT HAS REACHED THE END OF ITS USEFUL LIFE. THIS PROJECT REHABILITATES 8,079 SQUARE YARDS OF THE EASTERN SECTION OF EXISTING GENERAL AVIATION APRON PAVEMENT TO MAINTAIN THE STRUCTURAL INTEGRITY OF THE PAVEMENT AND TO MINIMIZE FOREIGN OBJECT DEBRIS. INTENDED BENEFICIARY: THIS GRANT WILL PROVIDE FEDERAL FUNDING FOR AIRPORTS ASSOCIATED WITH MOSINEE, WISCONSIN.
What it is
- Program
- Airport Improvement Program (Assistance Listing 20.116)
- Where the work is
- Marathon, WI · district WI-07
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
1 action since 2026-08-24. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-24 | 00 | New award | $2.86M | PURPOSE: RECONSTRUCT TAXILANE; REHABILITATE APRON; RECONSTRUCT APRON. ACTIVITIES TO BE PERFORMED/EXPECTED OUTCOMES: THIS PROJECT RECONSTRUCTS 239 FEET OF EXISTING TAXILANE 3 PAVEMENT THAT HAS REACHED THE END OF ITS USEFUL LIFE. THIS PROJECT RECONSTRUCTS… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-05). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗