PROJECT TITLE: REMNANTS OF IDA1 SITE ON I-78 WB RAMP (SITE 2 PHASES 1&2), MP 43-44.8, BERKELEY HEIGHTS,UNION COUNTY, PERMANENT & ER REIMBURSEMENT CONSTRUCTION :::: PROJECT DESCRIPTION: REMNANTS OF HURRICANE IDA1 SITE ON I-78 WB RAMP (SITE 2 PHASES 1&2), MP 43-44.8, BERKELEY HEIGHTS , UNION COUNTY, PERMANENT AND EMERGENCY RELIEF REIMBURSEMENT CONSTRUCTION
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
2 actions since 2024-08-27. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-04-03 | 1 | Revision | -$1 | PROJECT TITLE: REMNANTS OF IDA1 SITE ON I-78 WB RAMP (SITE 2 PHASES 1&2), MP 43-44.8, BERKELEY HEIGHTS,UNION COUNTY, PERMANENT & ER REIMBURSEMENT CONSTRUCTION :::: PROJECT DESCRIPTION: REMNANTS OF HURRICANE IDA1 SITE ON I-78 WB RAMP (SITE 2 PHASES 1&2), MP… |
| 2024-08-27 | 0 | New award | $4.97M | PROJECT TITLE: REMNANTS OF IDA1 SITE ON I-78 WB RAMP (SITE 2 PHASES 1&2), MP 43-44.8, BERKELEY HEIGHTS,UNION COUNTY, PERMANENT & ER REIMBURSEMENT CONSTRUCTION :::: PROJECT DESCRIPTION: REMNANTS OF HURRICANE IDA1 SITE ON I-78 WB RAMP (SITE 2 PHASES 1&2), MP… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗