DEGD0000038↗

Oregon Department of Energy received this grant or assistance award from Department of Energy: $30.90M obligated so far for grid infrastructure deployment and resilience. Its latest action was on 2026-02-11.

Key facts · data as of Nov 21, 2026

Recipient
Oregon Department of Energy
Awarding agency
Department of Energy
Obligated to date
$30.90M

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 21, 2026.

Cite this page: SpendQuery, Award DEGD0000038, data as of Nov 21, 2026, https://spendquery.com/award?id=ASST_NON_DEGD0000038_089

BIPARTISAN INFRASTRUCTURE LAW (BIL) – PREVENTING OUTAGES AND ENHANCING THE RESILIENCE OF THE ELECTRIC GRID FORMULA GRANTS TO STATES AND INDIAN TRIBES. THE OBJECTIVE OF THIS PROJECT IS TO IMPROVE THE RESILIENCE OF THE ELECTRIC GRID AGAINST DISRUPTIVE EVENTS.

Formula Grant (A) · Department of Energy · to Oregon Department of Energy (UEI WT3KTTM9TU19) · data as of 2026-11-21

Obligated to date$30.90M5 actions
Period2023-06-30 → 2026-02-11first to last action
Passed on$10.79Mto 9 subrecipients

What it is

Program
Grid Infrastructure Deployment and Resilience (Assistance Listing 81.254)
Where the work is
Marion, OR · district OR-06
Funding law
Infrastructure law (IIJA)

Obligations by fiscal year

FY2023$19.91M
FY2024$10.99M
FY2025$0
FY2026$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subrecipients: where the money went next

9 subawards totaling $10.79M (34.9% of what was obligated), as Oregon Department of Energy reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.

SubrecipientAmountSubawardsWhereFirstLast
Pacificorp$4.10M1OR2025-12-152025-12-15
Umatilla Electric Cooperative$1.48M1OR2025-11-072025-11-07
Columbia Power Cooperative Association$1.33M1OR2025-01-152025-01-15
Coos-Curry Electric Cooperative, Inc.$1.13M1OR2025-02-012025-02-01
Midstate Electric Cooperative, Inc.$836.4K1OR2026-04-082026-04-08
Columbia Basin Electric Cooperative, Inc.$700.1K1OR2025-02-122025-02-12
Forest Grove, City of$438.2K1OR2025-04-112025-04-11
Oregon Trail Electric Consumers Cooperative Inc$392.4K1OR2025-05-082025-05-08
Columbia River Peoples Utility District$377.4K1OR2025-04-232025-04-23
The largest single subawards
DateToAmountFor
2025-12-15Pacificorp$4.10MTHIS PROJECT WILL ENHANCE WILDFIRE RESILIENCE IN JOSEPHINE COUNTY, OREGON, BY RECONDUCTORING 12.54 MILES OF DISTRIBUTION LINES WITH COVERED CONDUCTOR AND REPLACING 311 EXISTING WOOD POLES WITH FIRE-RESISTANT COMPOSITE…
2025-11-07Umatilla Electric Cooperative$1.48MUNDERGROUND 4.55 MILES OF DISTRIBUTION LINE IN THREE RURAL AREAS.
2025-01-15Columbia Power Cooperative Association$1.33MTHE PROJECT INCLUDES THE FOLLOWING ACTIVITIES TO REDUCE THE LIKELIHOOD AND CONSEQUENCES OF DISRUPTIVE EVENTS: A. PURCHASE EQUIPMENT AND CONVERT AN EXISTING SERVICE TRUCK TO A FLATBED TRUCK WITH FIREFIGHTING CAPABILITY,…
2025-02-01Coos-Curry Electric Cooperative, Inc.$1.13MCONVERSION TO UNDERGROUND OF APPROXIMATELY 2.16 MILES OF OVERHEAD DISTRIBUTION LINE IN COOS COUNTY ALONG HIGHWAY 42 IN EXISTING RIGHTS-OF-WAY.
2026-04-08Midstate Electric Cooperative, Inc.$836.4KTHE PROJECT INVOLVES THE REMOVAL OF 72 POLES AND APPROXIMATELY 3.95 MILES OF OVERHEAD ELECTRICAL CONDUCTOR. TRENCHING WILL TAKE PLACE ALONG THE SAME 3.95 MILES OF RIGHT-OF-WAY TO INSTALL IN-CONDUIT UNDERGROUND CABLE…
2025-02-12Columbia Basin Electric Cooperative, Inc.$700.1KCONVERSION TO UNDERGROUND OF APPROXIMATELY 10 MILES OF RURAL OVERHEAD ELECTRICAL DISTRIBUTION LINES IN THREE SEPARATE SECTIONS NEAR THE CITY OF CONDON.
2025-04-11Forest Grove, City of$438.2KRELOCATION OF EXISTING OVERHEAD PRIMARY VOLTAGE DISTRIBUTION LINES TO UNDERGROUND ALONG DAVID HILL ROAD IN FOREST GROVE, OR 97116, TOTALING APPROXIMATELY 3500 FT OF PRIMARY DISTRIBUTION LINE IN PVC CONDUIT.
2025-05-08Oregon Trail Electric Consumers Cooperative Inc$392.4KINSTALLATION OF SCADA ENABLED, UPGRADED FIELD RECLOSERS, FUSE BANKS AND RELATED EQUIPMENT THAT OPERATE AS THE CONTROLLING DEVICES ON 23 POLE LOCATIONS IN RECIPIENT'S SERVICE AREA FOR AREAS SUBJECT TO PUBLIC SAFETY…
2025-04-23Columbia River Peoples Utility District$377.4KCONVERSION TO UNDERGROUND OF APPROXIMATELY 1,508 FEET OF OVERHEAD POWER LINES BETWEEN THE CITIES OF ST. HELENS AND COLUMBIA CITY, THE MAIN FEEDER SERVING THE CITY OF ST. HELENS' WATER FILTRATION FACILITY.

Every action

5 actions since 2023-06-30. Each is a modification or amendment with the money it added or took back.

DateAmendmentKindAmountWhat the agency wrote
2026-02-110004Revision$0INFRASTRUCTURE INVESTMENT AND JOBS ACT (IIJA) – PREVENTING OUTAGES AND ENHANCING THE RESILIENCE OF THE ELECTRIC GRID FORMULA GRANTS TO STATES AND INDIAN TRIBES. THE OBJECTIVE OF THIS PROJECT IS TO IMPROVE THE RESILIENCE OF THE ELECTRIC GRID AGAINST…
2025-06-100003Revision$0BIPARTISAN INFRASTRUCTURE LAW (BIL) – PREVENTING OUTAGES AND ENHANCING THE RESILIENCE OF THE ELECTRIC GRID FORMULA GRANTS TO STATES AND INDIAN TRIBES. THE OBJECTIVE OF THIS PROJECT IS TO IMPROVE THE RESILIENCE OF THE ELECTRIC GRID AGAINST DISRUPTIVE EVENTS.
2025-01-070002Revision$0BIPARTISAN INFRASTRUCTURE LAW (BIL) – PREVENTING OUTAGES AND ENHANCING THE RESILIENCE OF THE ELECTRIC GRID FORMULA GRANTS TO STATES AND INDIAN TRIBES. THE OBJECTIVE OF THIS PROJECT IS TO IMPROVE THE RESILIENCE OF THE ELECTRIC GRID AGAINST DISRUPTIVE EVENTS.
2024-07-220001Revision$10.99MBIPARTISAN INFRASTRUCTURE LAW (BIL) – PREVENTING OUTAGES AND ENHANCING THE RESILIENCE OF THE ELECTRIC GRID FORMULA GRANTS TO STATES AND INDIAN TRIBES. THE OBJECTIVE OF THIS PROJECT IS TO IMPROVE THE RESILIENCE OF THE ELECTRIC GRID AGAINST DISRUPTIVE EVENTS.
2023-06-30New award$19.91MBIPARTISAN INFRASTRUCTURE LAW (BIL) – PREVENTING OUTAGES AND ENHANCING THE RESILIENCE OF THE ELECTRIC GRID FORMULA GRANTS TO STATES AND INDIAN TRIBES. THE OBJECTIVE OF THIS PROJECT IS TO IMPROVE THE RESILIENCE OF THE ELECTRIC GRID AGAINST DISRUPTIVE EVENTS.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-21). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗