DEGD0001048↗
Puerto Rico Electric Power Authority received this grant or assistance award from Department of Energy: $365.00M obligated so far for grid infrastructure deployment and resilience. Its latest action was on 2026-09-15.
Key facts · data as of Nov 21, 2026
- Recipient
- Puerto Rico Electric Power Authority
- Awarding agency
- Department of Energy
- Obligated to date
- $365.00M
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 21, 2026.
Cite this page: SpendQuery, Award DEGD0001048, data as of Nov 21, 2026, https://spendquery.com/award?id=ASST_NON_DEGD0001048_089
Puerto Rico Electric Power Authority: all federal awards · Department of Energy: spending
PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) ELECTRIC GRID RESILIENCE & STABILIZATION THE OBJECTIVE OF THE RESULTING AWARD TO PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) IS TO IMPROVE THE RESILIENCE AND STABILIZATION OF THE PUERTO RICAN ELECTRIC GRID. THE AWARD FOCUSES ON KEY EMERGENCY ACTIVITIES DESIGNED TO ADDRESS CRITICAL VULNERABILITIES ACROSS GENERATION, TRANSMISSION, AND DISTRIBUTION SYSTEMS.
What it is
- Program
- Grid Infrastructure Deployment and Resilience (Assistance Listing 81.254)
- Funding law
- Other emergency or disaster supplementals
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
5 actions since 2025-09-30. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-15 | 0004 | EX | $0 | PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) ELECTRIC GRID RESILIENCE & STABILIZATION THE OBJECTIVE OF THE RESULTING AWARD TO PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) IS TO IMPROVE THE RESILIENCE AND STABILIZATION OF THE PUERTO RICAN ELECTRIC GRID. THE… |
| 2026-04-29 | 0003 | Revision | $0 | PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) ELECTRIC GRID RESILIENCE & STABILIZATION THE OBJECTIVE OF THE RESULTING AWARD TO PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) IS TO IMPROVE THE RESILIENCE AND STABILIZATION OF THE PUERTO RICAN ELECTRIC GRID. THE… |
| 2026-02-19 | 0002 | Revision | $0 | PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) ELECTRIC GRID RESILIENCE & STABILIZATION THE OBJECTIVE OF THE RESULTING AWARD TO PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) IS TO IMPROVE THE RESILIENCE AND STABILIZATION OF THE PUERTO RICAN ELECTRIC GRID. THE… |
| 2025-11-03 | 0001 | Revision | $0 | PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) ELECTRIC GRID RESILIENCE & STABILIZATION THE OBJECTIVE OF THE RESULTING AWARD TO PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) IS TO IMPROVE THE RESILIENCE AND STABILIZATION OF THE PUERTO RICAN ELECTRIC GRID. THE… |
| 2025-09-30 | New award | $365.00M | PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) ELECTRIC GRID RESILIENCE & STABILIZATION THE OBJECTIVE OF THE RESULTING AWARD TO PUERTO RICO ELECTRIC POWER AUTHORITY (PREPA) IS TO IMPROVE THE RESILIENCE AND STABILIZATION OF THE PUERTO RICAN ELECTRIC GRID. THE… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-21). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗