DENE0009042↗
Constellation Energy Generation, LLC received this grant or assistance award from Department of Energy: $59.04M obligated so far for nuclear energy research, development and demonstration. Its latest action was on 2026-06-16.
Key facts · data as of Nov 14, 2026
- Recipient
- Constellation Energy Generation, LLC
- Awarding agency
- Department of Energy
- Obligated to date
- $59.04M
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 14, 2026.
Cite this page: SpendQuery, Award DENE0009042, data as of Nov 14, 2026, https://spendquery.com/award?id=ASST_NON_DENE0009042_089
Constellation Energy Generation, LLC: all federal awards · Department of Energy: spending
THIS NUCLEAR INDUSTRY SAFETY SYSTEM DIGITAL UPGRADE PROJECT ADDRESSES THE NEED TO ACHIEVE PROGRESS IN MODERNIZING CURRENT PLANTS TO ENSURE THEIR LONG-TERM ECONOMIC VIABILITY THROUGH SUCCESSFUL DEMONSTRATION OF A MAJOR SAFETY INSTRUMENTATION AND CONTROL (I&C) SYSTEM UPGRADE. THIS PROJECT WILL DESIGN AND PROCURE A SAFETY I&C SYSTEM UPGRADE, INTEGRATING ALL REQUIRED DESIGN BASIS FUNCTIONS WITH NEW LABOR-REDUCTION FEATURES THAT SUBSTANTIALLY REDUCE OPERATING AND MAINTENANCE COSTS; DEVELOP A LICENSING STRATEGY AND DEMONSTRATE USE OF THE NUCLEAR REGULATORY COMMISSION’S (NRC) NEWLY REVISED DIGITAL I&C INTERIM STAFF GUIDANCE #06 (ISG-06), REVISION 2 FOR SAFETY I&C SYSTEMS; AND INSTALL AND COMMISSION THE SAFETY I&C SYSTEM IN AN OPERATING NUCLEAR PLANT.
What it is
- Program
- Nuclear Energy Research, Development and Demonstration (Assistance Listing 81.121)
- Where the work is
- Montgomery, PA · district PA-04
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subrecipients: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
10 actions since 2022-10-05. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-16 | 0011 | Revision | $6.81M | THE PURPOSE OF THIS AMENDMENT IS TO ADD INCREMENTAL FUNDING AND CHANGE THE ASSIGNED CONTRACT SPECIALIST FROM ALDEN ALLEN TO DAVID HAWKES. A NEW POINT OF CONTACT SHEET IS ATTACHED. (SEE A-016 POINT OF CONTACT SHEET DE-NE0009042 - 011) ALL OTHER TERMS AND… |
| 2025-12-08 | 0010 | Continuation | $0 | THIS MODIFICATION IS TO AUTHORIZE BUDGET PERIOD 6 FOR THIS AWARD. PER THE CONTINUATION APPLICATION SUBMITTED BY THE AWARDEE, NO BUDGETARY CHANGES ARE REQUESTED FOR THE UPCOMING BUDGETARY YEAR. THIS MODIFICATION: 1. AUTHORIZES BUDGET PERIOD 6 OF THE AWARD… |
| 2025-09-17 | 0009 | Revision | $17.00M | THIS MODIFICATION IS TO ADD THE REMAINING FUNDS FOR BUDGET PERIOD 5 IN THE AMOUNT OR $11,128,000 AND TO INCREMENTALLY FUND BUDGET PERIOD 6 (DEPENDENT ON APPROVAL OF THE CONTINUATION AWARD) IN THE AMOUNT OF $5,872,000. IT ALSO CHANGES THE HQ PROGRAM MANAGER… |
| 2025-01-13 | 0008 | Continuation | $0 | THIS MODIFICATION IS TO AUTHORIZE BUDGET PERIOD 5 FOR THIS AWARD. PER THE CONTINUATION APPLICATION SUBMITTED BY THE AWARDEE, NO BUDGETARY CHANGES ARE REQUESTED FOR THE UPCOMING BUDGETARY YEAR. THIS MODIFICATION: 1. AUTHORIZES BUDGET PERIOD 5 OF THE AWARD… |
| 2024-09-30 | 0007 | Revision | $10.00M | THIS MODIFICATION OBLIGATES $10,000,000 IN INCREMENTAL FUNDING TOWARDS BUDGET PERIOD 5 FOR THE AWARD. ADDITIONALLY, THE SPECIAL TERMS AND CONDITIONS HAS BEEN UPDATED TO INCLUDE THE CLAUSE ''FUNDING OF BUDGET PERIODS'' TO ALLOW OBLIGATION FOR BUDGET PERIOD 5.… |
| 2024-08-27 | 0006 | Continuation | $10.00M | THIS MODIFICATION IS A CONTINUATION ACTION FOR BUDGET PERIOD 4. THIS MODIFICATION RESETS BUDGET PERIOD 3 TO THE ACTUAL COSTS INCURRED AND ADJUSTS THE UPCOMING COSTS FOR BUDGET PERIOD 4. ADDITIONALLY, DUE TO INCREASES IN FINAL DESIGN COSTS FROM WESTINGHOUSE… |
| 2023-08-24 | 0005 | Revision | $4.20M | THIS MODIFICATION IS TO ADD INCREMENTAL FUNDING FOR BUDGET PERIOD 3 IN THE AMOUNT OF $4,200,000. THIS MODIFICATION: 1. OBLIGATES $4,200,000 TO THE AWARD. 2. THE TOTAL AMOUNT OBLIGATED TO BUDGET PERIOD 3 IS INCREASED BY $4,200,000 FROM $5,800,00 TO… |
| 2023-02-06 | 0004 | Revision | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE PROGRAM OFFICIAL WITHIN DOE INTERNAL SYSTEMS. THE PROGRAM OFFICIAL HAS BEEN CHANGED FROM ALISON HAHN TO DAVID HERRIN. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. UNILATERAL MODIFICATION, NO SIGNATURE… |
| 2023-01-30 | 0003 | Continuation | $11.04M | THIS MODIFICATION IS TO APPROVE THE CONTINUATION APPLICATION FOR BUDGET PERIOD 3. THIS MODIFICATION: 1. OBLIGATED FUNDS FOR BUDGET PERIOD 2 ARE INCREASED BY $5,235,000 FROM $4,510,300 TO $9,745,000. 2. OBLIGATED FUNDS FOR BUDGET PERIOD 3 ARE INCREASED BY… |
| 2022-10-05 | 0002 | Revision | $0 | THIS MODIFICATION IS TO CHANGE THE NAME OF THE RECIPIENT FROM EXELON GENERATION COMPANY, LLC TO CONSTELLATION ENERGY GENERATION, LLC. THIS IS NOT A CHANGE TO ANOTHER RECIPIENT AND REQUIRES NO NOVATION. NO CHANGES OF ASSIGNMENT OF PAYMENT, NOR ANY TRANSFER OF… |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-14). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗