APPLICATION PURPOSE: THE PURPOSE IS TO CONSTRUCT THE SECOND AVENUE SUBWAY PHASE 2 PROJECT.; ACTIVITIES PERFORMED: THE PROJECT INCLUDES THE CONSTRUCTION OF THREE NEW STATIONS TRACTION POWER SUBSTATIONS SIGNAL TRACK COMMUNICATION SYSTEMS AND STATION ARCHITECTURAL ELEMENTS AND FACILITIES.; EXPECTED OUTCOMES: THE SECOND AVENUE SUBWAY (SAS) PHASE 2 PROJECT (PROJECT) IS A PLANNED TWO-TRACK 1.76-MILE HEAVY RAIL SUBWAY EXTENSION ALONG THE EAST SIDE OF MANHATTAN. IT WILL CONNECT THE NORTHERN END OF PHASE 1 AT 105TH STREET TO THE 125TH STREET STATION OF THE LEXINGTON AVENUE LINE AND TERMINATE WEST OF THE INTERSECTION OF MALCOLM X BOULEVARD AND 125TH STREET.; INTENDED BENEFICIARIES: COMMUTERS ALONG MANHATTANS EAST SIDE AND USERS OF THE MTA SUBWAY SYSTEM.; SUBRECIPIENT ACTIVITIES: THERE ARE NO SUB-RECIPIENT ACTIVITIES WITH THIS AWARD.
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2023-11-04. Each is a modification or amendment with the money it added or took back.
| Date | Amendment | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-16 | 3 | Revision | $307.30M | APPLICATION PURPOSE: THE PURPOSE IS TO CONSTRUCT THE SECOND AVENUE SUBWAY PHASE 2 PROJECT.; ACTIVITIES PERFORMED: THE PROJECT INCLUDES THE CONSTRUCTION OF THREE NEW STATIONS TRACTION POWER SUBSTATIONS SIGNAL TRACK COMMUNICATION SYSTEMS AND STATION… |
| 2026-05-12 | 2 | Revision | $307.26M | APPLICATION PURPOSE: THE PURPOSE IS TO CONSTRUCT THE SECOND AVENUE SUBWAY PHASE 2 PROJECT.; ACTIVITIES PERFORMED: THE PROJECT INCLUDES THE CONSTRUCTION OF THREE NEW STATIONS TRACTION POWER SUBSTATIONS SIGNAL TRACK COMMUNICATION SYSTEMS AND STATION… |
| 2024-09-09 | 1 | Revision | $496.78M | APPLICATION PURPOSE: THE PURPOSE IS TO CONSTRUCT THE SECOND AVENUE SUBWAY PHASE 2 PROJECT.; ACTIVITIES PERFORMED: THE PROJECT INCLUDES THE CONSTRUCTION OF THREE NEW STATIONS TRACTION POWER SUBSTATIONS SIGNAL TRACK COMMUNICATION SYSTEMS AND STATION… |
| 2023-11-04 | 0 | New award | $450.00M | APPLICATION PURPOSE: THE PURPOSE IS TO CONSTRUCT THE SECOND AVENUE SUBWAY PHASE 2 PROJECT.; ACTIVITIES PERFORMED: THE PROJECT INCLUDES THE CONSTRUCTION OF THREE NEW STATIONS TRACTION POWER SUBSTATIONS SIGNAL TRACK COMMUNICATION SYSTEMS AND STATION… |