12314422F0174↗
Epsilon Inc received this contract from Usda, Ocp-Pod-Acq-Mgmt-Branch-Ftc, Office of the Chief Financial Officer: $13.22M obligated so far for it and telecom - data center as a service. It runs to 2032-02-21.
Key facts · data as of Oct 25, 2026
- Recipient
- Epsilon Inc
- Awarding agency
- Office of the Chief Financial Officer (Department of Agriculture)
- Contracting office
- Usda, Ocp-Pod-Acq-Mgmt-Branch-Ftc (123144)
- Obligated to date
- $13.22M
- Potential value
- $30.40M
- Ends
- 2032-02-21
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award 12314422F0174, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_12314422F0174_1205_47QTCH18D0014_4732
Epsilon Inc: all federal awards · Department of Agriculture: spending · Usda, Ocp-Pod-Acq-Mgmt-Branch-Ftc: what it buys
GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT
What it is
- Product or service
- IT and Telecom - Data Center As a Service (PSC DC10)
- Industry
- Computer Systems Design Services (NAICS 541512)
- Contracting office
- Usda, Ocp-Pod-Acq-Mgmt-Branch-Ftc (123144)
- Competition
- Full and open after exclusion of sources · 5 offers received
- Pricing
- Firm fixed price
- How it was bought
- GWAC · under VETS 2 (47QTCH18D0014)
- Solicitation
- 12314422Q0005
- Where the work is
- Jackson, MO · district MO-05
- Topics
- cloud
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
1 subaward totaling $661.2K (5.0% of what was obligated), as Epsilon Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Ecco Select Corporation | $661.2K | 1 | MO | 2025-12-15 | 2025-12-15 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2025-12-15 | Ecco Select Corporation | $661.2K | GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT |
Every action
17 actions since 2023-02-21. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-24 | P00023 | Supplemental agreement (work within scope) | $3.2K | UNITED STATES DEPARTMENT OF AGRICULTURE (USDA)/ DIGITAL INFRASTRUCTURE SERVICES CENTER (DISC) DATA CENTER HOSTING SERVICES- GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT |
| 2026-05-13 | P00022 | Supplemental agreement (work within scope) | $6.7K | UNITED STATES DEPARTMENT OF AGRICULTURE (USDA)/ DIGITAL INFRASTRUCTURE SERVICES CENTER (DISC) DATA CENTER HOSTING SERVICES- GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT |
| 2026-04-03 | P00021 | Supplemental agreement (work within scope) | $25.6K | MOD P00021: THE PURPOSE OF THIS MODIFICATION IS TO ADD SWITCHBOARD CONNECTIONS |
| 2026-02-20 | P00020 | Option exercised | $3.72M | MOD P00020: THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 4 |
| 2025-07-18 | P00019 | Supplemental agreement (work within scope) | $5.5K | MOD P00019: THE PURPOSE OF THIS MODIFICATION IS TO ADD FUNDING TO AN EXISTING CLIN FOR VIRTUAL CONNECTIONS. |
| 2025-04-23 | P00018 | Administrative change | $0 | MOD P00018: THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE CONTRACTING OFFICER (CO) AND IPP APPROVER 2. |
| 2025-02-11 | P00017 | Option exercised | $3.58M | MOD P00017: THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 3 FOR THE PERIOD OF 02/22/2025 TO 02/21/2026. |
| 2024-09-20 | P00016 | Supplemental agreement (work within scope) | $47.0K | MOD P00016: THE PURPOSE OF THIS MODIFICATION IS TO ADD ITEMS WITHIN SCOPE - RACKS AND PDUS TO CONTRACT 47QTCH18D0014 /12314422F0174, GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT. |
| 2024-09-16 | P00015 | Supplemental agreement (work within scope) | $21.4K | MOD P00015: THE PURPOSE OF THIS MODIFICATION IS TO ADD ADDITIONAL WORK WITHIN SCOPE FOR QTS POWER SWAP, ODC FUNDING AND UPDATE CONTRACTING OFFICER TO CONTRACT 47QTCH18D0014 /12314422F0174, GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT. |
| 2024-08-01 | P00014 | Supplemental agreement (work within scope) | $123.5K | MOD P00014: IS TO ADD ADDITIONAL CLINS AND FUNDING TO OPTION PERIOD 2 FOR SWITCHBOARD VIRTUAL CONNECTION TO 47QTCH18D0014/12314422F0174, GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT. |
| 2024-06-27 | P00013 | Supplemental agreement (work within scope) | $0 | GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT - MOD P00013: 1. GOODFELLOW COLOCATION AND MIGRATION PWS REVISED MOD 2 V5 2. QUALITY CONTROL PLAN_1-18-24 3. GOODFELLOW TRANSITION IN PLAN_V5 4. GOODFELLOW QASP ALL OTHER TERMS AND CONDITIONS RE |
| 2024-04-26 | P00012 | Supplemental agreement (work within scope) | $689.0K | MOD P00012: ADDITIONAL OPTIONAL FLOOR SPACE FOR RACK EXPANSION. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-03-28 | P00011 | Supplemental agreement (work within scope) | $55.1K | MOD P00011: IS TO INCLUDE CONDUIT, INSTALLATION OF CAMERAS, AND INSTALLATION OF A QUARTER RACK WITHIN THE USDA'S STORAGE CAGE AT QTS CHICAGO, SEPARATED BY LABOR AND MATERIALS. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-02-20 | P00010 | Option exercised | $2.30M | MOD P00010: THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 2 FOR THE PERIOD OF 02/22/2024 TO 02/21/2025, IN THE AMOUNT OF $2,299,082.94 FOR THE CLINS IDENTIFIED BELOW. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2023-07-13 | P00009 | Administrative change | $0 | GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT. |
| 2023-05-11 | P00008 | Funding only | $1.07M | GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT. |
| 2023-02-21 | P00007 | Option exercised | $1.57M | GOODFELLOW COLOCATION, MIGRATION, AND SUPPORT. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗