1232SA25F0460↗
Mill Creek Firelake JV LLC received this contract from Usda Ars Afm Apd, Agricultural Research Service: $291.8K obligated so far for maintenance of office buildings. Its period of performance ended 2026-05-29.
Key facts · data as of Oct 23, 2026
- Recipient
- Mill Creek Firelake JV LLC
- Awarding agency
- Agricultural Research Service (Department of Agriculture)
- Contracting office
- Usda Ars Afm Apd (1232SA)
- Obligated to date
- $291.8K
- Potential value
- $291.8K
- Ends
- 2026-05-29
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 1232SA25F0460, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_1232SA25F0460_12H2_12805B24D0003_12H2
Mill Creek Firelake JV LLC: all federal awards · Department of Agriculture: spending · Usda Ars Afm Apd: what it buys
UPGRADE VARIABLE FREQUENCY DRIVES
What it is
- Product or service
- Maintenance of Office Buildings (PSC Z1AA)
- Industry
- Plumbing, Heating, and Air-Conditioning Contractors (NAICS 238220)
- Contracting office
- Usda Ars Afm Apd (1232SA)
- Competition
- Full and open after exclusion of sources · 2 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 12805B24D0003
- Solicitation
- 1232SA25R0072
- Where the work is
- Riley, KS · district KS-01
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
2 subawards totaling $199.0K (68.2% of what was obligated), as Mill Creek Firelake JV LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| P1 Construction LLC | $167.5K | 1 | KS | 2025-10-07 | 2025-10-07 |
| Johnson Controls International Public Limited Company | $31.5K | 1 | PA | 2025-11-20 | 2025-11-20 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2025-10-07 | P1 Construction LLC | $167.5K | PROVIDE AND INSTALL NEW ABB 580 VARIABLE FREQUENCY DRIVES (VFDS) AND ENCLOSURES. |
| 2025-11-20 | Johnson Controls, Inc. | $31.5K | VFD INSTALLATION AND TESTING |
Every action
3 actions since 2025-09-23. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-27 | P00002 | Supplemental agreement (work within scope) | $0 | TIME EXTENSION MODIFICATION FOR UPGRADE OF VARIABLE FREQUENCY DRIVES |
| 2026-02-05 | P00001 | Supplemental agreement (work within scope) | $0 | TIME EXTENSION MODIFICATION FOR UPGRADE OF VARIABLE FREQUENCY DRIVES |
| 2025-09-23 | 0 | $291.8K | UPGRADE VARIABLE FREQUENCY DRIVES |