1240LS24F0013↗

Applied Intellect LLC received this contract from Usda-Fs, Csa Intermountain 7, Forest Service: $315.4K obligated so far for environmental systems protection- environmental remediation. It runs to 2029-04-14.

Key facts · data as of Nov 20, 2026

Recipient
Applied Intellect LLC
Awarding agency
Forest Service (Department of Agriculture)
Contracting office
Usda-Fs, Csa Intermountain 7 (1240LS)
Obligated to date
$315.4K
Potential value
$377.2K
Ends
2029-04-14

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 20, 2026.

Cite this page: SpendQuery, Award 1240LS24F0013, data as of Nov 20, 2026, https://spendquery.com/award?id=CONT_AWD_1240LS24F0013_12C2_GS10F026BA_4732

ZACA MINE/COLORADO HILL MONITORING AND MAINTENANCE PROJECT. PER ATTACHED SCHEDULE OF ITEMS AND PRICING.

Delivery Order · Forest Service · to Applied Intellect LLC (UEI SKDNFVJ9K8U3) · data as of 2026-11-20

Obligated to date$315.4K6 actions
Current value$315.4Kwith options exercised
Potential value$377.2Kif every option is used
Period2024-04-15 → 2029-04-14current end date

What it is

Product or service
Environmental Systems Protection- Environmental Remediation (PSC F108)
Industry
Administrative Management and General Management Consulting Services (NAICS 541611)
Contracting office
Usda-Fs, Csa Intermountain 7 (1240LS)
Competition
Full and open competition · 1 offer received
Pricing
Firm fixed price
How it was bought
GSA Schedule · under GS10F026BA
Solicitation
RFQ1685789
Where the work is
Weber, UT · district UT-01

Obligations by fiscal year

FY2024$84.0K
FY2025$56.4K
FY2026$175.0K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

6 actions since 2024-04-15. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-22P00005Option exercised$52.0KZACA MINE/COLORADO HILL MONITORING AND MAINTENANCE PROJECT. MOD 5: THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO EXERCISE OPTION 3. THIS WILL WILL ALIGN MORE WITH THE REQUIRED MAINTENANCE THAT IS NEEDED AND THE ADDITIONAL WATER MONITORING WIL
2026-07-06P00004Supplemental agreement (work within scope)$64.8KZACA MINE/COLORADO HILL MONITORING AND MAINTENANCE PROJECT. MOD 4: THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO REMOVE THE CURRENT INFILTRATION GALLERY MAINTENANCE, ADD PROPOSED SYSTEM MODIFICATIONS AND SURFACE WATER ANALYTICAL-AS OUTLINED IN
2026-02-11P00003Option exercised$58.1KZACA MINE/COLORADO HILL MONITORING AND MAINTENANCE PROJECT. MOD 3: THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO EXERCISE OPTION 2, PER ATTACHED SCHEDULE OF ITEMS, PERIOD OF PERFORMANCE 4/15/2026-4/14/2027 NO OTHER CHANGES ARE BEING MADE A
2025-05-21P00002Option exercised$56.4KZACA MINE/COLORADO HILL MONITORING AND MAINTENANCE PROJECT. MOD 2: THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO EXERCISE OPTION 1. PER ATTACHED SCHEDULE OF ITEMS. PERIOD OF PERFORMANCE 4/15/2025-4/14/2026. NO OTHER CHANGES ARE BEING MADE A
2025-05-05P00001Administrative change$0ZACA MINE/COLORADO HILL MONITORING AND MAINTENANCE PROJECT. MOD 1: THE PURPOSE OF THIS MODIFICATION IS TO DO A NO COST PERIOD OF PERFORMANCE EXTENSION TO 4/14/2026. FUNDING FOR OPTION YEAR 1 WILL BE ADDED AT A LATER DATE. NO OTHER CHANGES ARE
2024-04-150$84.0KZACA MINE/COLORADO HILL MONITORING AND MAINTENANCE PROJECT. PER ATTACHED SCHEDULE OF ITEMS AND PRICING.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-20). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗