GAOA SAVENAC WATER - WASTE WATER REPLACEMENT ON THE LOLO NATIONAL FOREST
Up for re-bid: ends 2026-08-01. Recompete brief → · USDA Forest Service, Coeur d'Alene Nursery Storage Building Replacement ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
6 actions since 2024-02-07. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-10 | P00005 | Supplemental agreement (work within scope) | $85.1K | MOD 0005 TO GAOA SAVENAC WATER - WASTE WATER REPLACEMENT - MODIFICATION ADDS FINAL LANDSCAPE PRESERVATION & ROAD WORK TO NEWLY DISTURBED, UNFORESEEN AREA AND IT ADDS AN ADDITIONAL 550 FEET OF 3" WATER MAIN PIPE. THIS WORK IS NECESSARY TO CO |
| 2026-06-01 | P00004 | Supplemental agreement (work within scope) | $0 | MOD 0004 TO GAOA SAVENAC WATER - WASTE WATER REPLACEMENT - IS A TIME EXTENSION MODIFICATION THAT SHOULD HAVE BEEN EXTENDED IN JANUARY WITH MOD 0003 WHEN WORK WAS REMOVED AND ADDED BACK IN. NEW POP ENDING DATE SHOULD BE 07/01/2026. THIS IS A ZERO-DO |
| 2026-02-02 | P00003 | Supplemental agreement (work within scope) | $0 | MOD 0003 TO GAOA SAVENAC WATER - WASTE WATER REPLACEMENT - DELETES 4" AND 6" SEWER LINE ITEMS AND OTHER MISC. ITEMS AS OLD SYSTEM COULD NOT CONNECT WITH CURRENT MATERIALS AVAILABLE. A NEW DEEP BURY SEPTIC SYSTEM WILL BE INSTALLED IN ITS PL |
| 2025-09-29 | P00002 | Supplemental agreement (work within scope) | $0 | MOD 0002 TO GAOA SAVENAC WATER - WASTE WATER REPLACEMENT ON THE LOLO NATIONAL FOREST CORRECTS MODIFICATION 0001 WHEN A 30-DAY TIME EXTENSION SHOULD HAVE BEEN GRANTED FOR THE ADDITIONAL WORK. NEW PERFORMANCE ENDING DATE SHALL BE 5/31/2026 DUE TO FREEZ |
| 2025-07-31 | P00001 | Supplemental agreement (work within scope) | $73.6K | MOD 0001 TO GAOA SAVENAC WATER - WASTE WATER REPLACEMENT ON THE LOLO NATIONAL FOREST REMOVES WELL DRILLING FUNDS TO BE ADDED BACK FOR ADDITIONAL 3" WATERLINE, NECESSARY BECAUSE THE DRILLING PRODUCED NO NEW WATER SOURCE. TAPPING INTO EXITING SYS |
| 2024-02-07 | 0 | $982.1K | GAOA SAVENAC WATER - WASTE WATER REPLACEMENT ON THE LOLO NATIONAL FOREST |