BACKLOG ITEMS NEEDED TO CONTINUE OPERATIONS AND REPAIR OF THE NBAF CAMPUS
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
2 actions since 2023-07-27. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2024-01-16 | P00001 | Close-out | -$15.3K | BACKLOG ITEMS NEEDED TO CONTINUE OPERATIONS AND REPAIR OF THE NBAF CAMPUS |
| 2023-07-27 | 0 | $78.2K | BACKLOG ITEMS NEEDED TO CONTINUE OPERATIONS AND REPAIR OF THE NBAF CAMPUS |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗