12970224F0018↗

J. I. Garcia Construction, Inc. received this contract from Usda-Fs, Csa Southwest 6, Forest Service: $14.48M obligated so far for construction of other administrative facilities and service buildings. It runs to 2026-11-24.

Key facts · data as of Oct 23, 2026

Recipient
J. I. Garcia Construction, Inc.
Awarding agency
Forest Service (Department of Agriculture)
Contracting office
Usda-Fs, Csa Southwest 6 (127EAW)
Obligated to date
$14.48M
Potential value
$14.48M
Ends
2026-11-24

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award 12970224F0018, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_12970224F0018_12C2_140FGA23D0100_1448

CREEK (15) - CON - FACILITIES, NORTH FORK CCC CAMP - BARRACKS, ENGINE BAY

Delivery Order · Forest Service · to J. I. Garcia Construction, Inc. (UEI GRGVD98552T5) · data as of 2026-10-23

Obligated to date$14.48M4 actions
Current value$14.48Mwith options exercised
Period2024-09-30 → 2026-11-24current end date

Up for re-bid: ends 2026-11-24. Recompete brief → · GAOA Red Rock Lookout Renovation, Plumas National Forest ↗

What it is

Product or service
Construction of Other Administrative Facilities and Service Buildings (PSC Y1AZ)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
Usda-Fs, Csa Southwest 6 (127EAW)
Competition
Full and open after exclusion of sources · 3 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 140FGA23D0100
Where the work is
Madera, CA · district CA-05
Funding law
Other emergency or disaster supplementals

Obligations by fiscal year

FY2024$13.92M
FY2025$0
FY2026$562.8K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

4 actions since 2024-09-19. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-08-26P00003Supplemental agreement (work within scope)$101.6K12970224F0018 - NORTH FORK CCC CAMP DESIGN BUILD - P00003 - DATA_COMM
2026-04-07P00002Supplemental agreement (work within scope)$461.2K12970224F0018 - NORTH FORK CCC CAMP DESIGN BUILD - P00002 - DRYWALL
2025-03-18P00001Administrative change$0CREEK (15) - CON - FACILITIES, NORTH FORK CCC CAMP - BARRACKS, ENGINE BAY
2024-09-190$13.92MCREEK (15) - CON - FACILITIES, NORTH FORK CCC CAMP - BARRACKS, ENGINE BAY

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗