NEW CREEK SITE 17 - DAM REHABILITATION DESIGN
Up for re-bid: ends 2026-10-02. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2023-08-11. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-09-17 | P00006 | Supplemental agreement (work within scope) | $96.2K | NEW CREEK SITE 17 - DAM REHABILITATION DESIGN THIS PURPOSE OF THIS MODIFICATION IS TO 1) REPLACE FY20 FUNDING WITH CURRENT FUNDING (SEE CLIN 0004 AND CLIN 0009) 2) DELETE EXPIRING FUNDS ON CLIN(S) 0002, 0005, 0006, 3) ADD ADDITIONAL WORK WITHIN SC |
| 2025-05-15 | P00005 | Supplemental agreement (work within scope) | $0 | NEW CREEK SITE 17 - DAM REHABILITATION DESIGN THIS MODIFICATION IS TO LIFT SUSPENSION, ADD 76 DAYS FROM 4/30/2025 MAKING COMPLETION DATE 7/15/2025. AND 60 DAYS FROM 7/15/2025, MAKING THE ESTIMATED COMPLETION 9/15/2025. |
| 2024-10-15 | P00004 | Supplemental agreement (work within scope) | $0 | NEW CREEK SITE 17 - DAM REHABILITATION DESIGN |
| 2023-08-11 | P00003 | Supplemental agreement (work within scope) | $482.6K | NEW CREEK SITE 17 - DAM REHABILITATION DESIGN THIS MODIFICATION IS FOR DEVELOPMENT OF BORROW SITE AND RISER AND DRAIN REPLACEMENT. ONE YEAR IS BEING ADDED TO THE PERIOD OF PERFORMANCE. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗