140F0422F0059↗

Hydra Engineering & Construction, LLC received this contract from FWS, Construction A/E Team 1, U.S. Fish and Wildlife Service: $9.4K obligated so far for construction of office buildings. Its period of performance ended 2024-04-08.

Key facts · data as of Oct 23, 2026

Recipient
Hydra Engineering & Construction, LLC
Awarding agency
U.S. Fish and Wildlife Service (Department of the Interior)
Contracting office
FWS, Construction A/E Team 1 (140FC1)
Obligated to date
$9.4K
Potential value
$508.9K
Ends
2024-04-08

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award 140F0422F0059, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_140F0422F0059_1448_140F0822D0055_1448

DESIGN BUILD OPEN-AIR BARN (ALLIGATOR RIVER NWR)

Delivery Order · U.S. Fish and Wildlife Service · to Hydra Engineering & Construction, LLC (UEI HVA8QVX8YST1) · data as of 2026-10-23

Obligated to date$9.4K2 actions
Current value$508.9Kwith options exercised
Period2022-08-30 → 2024-04-08current end date

What it is

Product or service
Construction of Office Buildings (PSC Y1AA)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
FWS, Construction A/E Team 1 (140FC1)
Competition
Full and open after exclusion of sources · 6 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 140F0822D0055
Solicitation
140F0422R0029
Where the work is
Dare, NC · district NC-03

Obligations by fiscal year

FY2023$0
FY2024$9.4K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

2 actions since 2023-08-11. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2024-03-01P00002Change order$9.4KMODIFICATION EXTEND PERIOD OF PERFORMANCE DESIGN BUILD OPEN-AIR BARN (ALLIGATOR RIVER NWR)
2023-08-11P00001Option exercised$0MODIFICATION EXTEND PERIOD OF PERFORMANCE DESIGN BUILD OPEN-AIR BARN (ALLIGATOR RIVER NWR)

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗