140F1B24F0002↗
J. I. Garcia Construction, Inc. received this contract from FWS Construction & A/E - Bil/Disaster, U.S. Fish and Wildlife Service: $1.76M obligated so far for construction of office buildings. Its period of performance ended 2025-12-31.
Key facts · data as of Oct 28, 2026
- Recipient
- J. I. Garcia Construction, Inc.
- Awarding agency
- U.S. Fish and Wildlife Service (Department of the Interior)
- Contracting office
- FWS Construction & A/E - Bil/Disaster (140F1B)
- Obligated to date
- $1.76M
- Potential value
- $2.02M
- Ends
- 2025-12-31
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 28, 2026.
Cite this page: SpendQuery, Award 140F1B24F0002, data as of Oct 28, 2026, https://spendquery.com/award?id=CONT_AWD_140F1B24F0002_1448_140FGA23D0100_1448
J. I. Garcia Construction, Inc.: all federal awards · Department of the Interior: spending · FWS Construction & A/E - Bil/Disaster: what it buys
DESIGN-BUILD SERVICES FOR MULTIPLE OBSERVATION PLATFORMS AND FISHING PIERS AT SAN LUIS NATIONAL WILDLIFE REFUGE COMPLEX
What it is
- Product or service
- Construction of Office Buildings (PSC Y1AA)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- FWS Construction & A/E - Bil/Disaster (140F1B)
- Competition
- Full and open after exclusion of sources · 2 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 140FGA23D0100
- Where the work is
- Merced, CA · district CA-13
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
3 actions since 2024-02-23. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-12-08 | P00002 | Change order | $0 | MOD P00002: THIS MODIFICATION EXTENDS THE PERIOD OF PERFORMANCE TO DECEMBER 31, 2025 TO ALLOW FOR THE COMPLETION OF WORK AND DEMOBILIZATION. UPDATED FAR CLAUSES ARE RELEASED IN THIS CHANGE ORDER. |
| 2024-05-10 | P00001 | Option exercised | $192.7K | 1. THIS MODIFICATION IS TO EXERCISE OPTIONS K, L, AND M ON THE CONTRACT. 2. CLIN LINE 250, TULE ELK TOWER OBSERVATION PLATFORM GUARDRAILS AND POSTS ALONG PATH LEADING TO RAMP, $77,361.00 [OPTION K] 3. CLIN LINE 260, EAST MARSH OBSERVATION PLATFORM |
| 2024-02-23 | 0 | $1.57M | DESIGN-BUILD SERVICES FOR MULTIPLE OBSERVATION PLATFORMS AND FISHING PIERS AT SAN LUIS NATIONAL WILDLIFE REFUGE COMPLEX |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-28). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗