Pullman SST, Inc. received this contract from DSC Contracting Services Division, National Park Service: $36.85M obligated so far for repair or alteration of museums and exhibition buildings. It runs to 2026-12-31.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 140P2023C0013, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_140P2023C0013_1443_-NONE-_-NONE-
Pullman SST, Inc.: all federal awards · Department of the Interior: spending · DSC Contracting Services Division: what it buys · The follow-on: recompete brief
STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK
Up for re-bid: ends 2026-12-31. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
13 actions since 2023-04-14. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-16 | P00012 | Additional work (new agreement) | $2.59M | UEI: JW12XFT7SLR7 STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MOD P00012 THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO |
| 2026-07-16 | P00011 | Supplemental agreement (work within scope) | $3.57M | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. |
| 2026-01-07 | P00010 | Supplemental agreement (work within scope) | $4.18M | UEI: JW12XFT7SLR7 STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MOD P00010 THE PURPOSE OF THIS BILATERAL MODIFICATION IS TO |
| 2025-12-12 | P00009 | Supplemental agreement (work within scope) | $55.6K | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MOD P00009 |
| 2025-09-11 | P00008 | Supplemental agreement (work within scope) | $141.9K | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MOD P00008 |
| 2025-05-06 | P00007 | Supplemental agreement (work within scope) | $0 | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MOD P00007 |
| 2025-04-18 | P00006 | Supplemental agreement (work within scope) | $152.6K | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MODIFICATION P00004 INCORPORATES ADDITIONAL WITHIN SCOPE WORK AND KEY PERSONNEL CHAN |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| 2024-09-24 | P00005 | Supplemental agreement (work within scope) | $268.5K | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MODIFICATION P00004 INCORPORATES ADDITIONAL WITHIN SCOPE WORK AND KEY PERSONNEL CHAN |
| 2024-09-17 | P00004 | Supplemental agreement (work within scope) | $43.6K | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MODIFICATION P00004 INCORPORATES ADDITIONAL WITHIN SCOPE WORK AND KEY PERSONNEL CHAN |
| 2024-06-17 | P00003 | Supplemental agreement (work within scope) | $0 | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MODIFICATION P00003 EXTENDS THE TASK ORDER'S PERIOD OF PERFORMANCE AT NO COST. |
| 2024-04-10 | P00002 | Supplemental agreement (work within scope) | $0 | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK. MODIFICATION P00002 PROVIDES KEY PERSONNEL CHANGES TO THE PROJECT AND CHANGES THE PE |
| 2023-07-10 | P00001 | Option exercised | $4.98M | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK |
| 2023-04-14 | 0 | $20.86M | STLI 312431, REHABILITATE EXTERIOR SYSTEMS OF MAIN IMMIGRATION BUILDING (GAOA PROJECT), STATUE OF LIBERTY NATIONAL MONUMENT, ELLIS ISLAND, NEW YORK COUNTY, NEW YORK |