140R1020C0012↗
Hartman-Walsh Painting Company received this contract from Pacific NW Region PN 6615, Bureau of Reclamation: $28.21M obligated so far for maintenance of epg facilities - hydro. It runs to 2027-02-16.
Key facts · data as of Oct 25, 2026
- Recipient
- Hartman-Walsh Painting Company
- Awarding agency
- Bureau of Reclamation (Department of the Interior)
- Contracting office
- Pacific NW Region PN 6615 (140R10)
- Obligated to date
- $28.21M
- Potential value
- $37.87M
- Ends
- 2027-02-16
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award 140R1020C0012, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_140R1020C0012_1425_-NONE-_-NONE-
Hartman-Walsh Painting Company: all federal awards · Department of the Interior: spending · Pacific NW Region PN 6615: what it buys · The follow-on: recompete brief
JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION
Up for re-bid: ends 2027-02-16. Recompete brief →
What it is
- Product or service
- Maintenance of Epg Facilities - Hydro (PSC Z1MD)
- Industry
- Water and Sewer Line and Related Structures Construction (NAICS 237110)
- Contracting office
- Pacific NW Region PN 6615 (140R10)
- Competition
- Full and open competition · 2 offers received
- Pricing
- Firm fixed price
- How it was bought
- Standalone contract
- Solicitation
- 140R1020R0003
- Where the work is
- Grant, WA · district WA-04
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
38 actions since 2022-10-25. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-24 | P00051 | Change order | $2.88M | MOD P051 P5 & P6 ABATEMENT & RECOAT. |
| 2026-08-13 | P00050 | Supplemental agreement (work within scope) | $0 | MOD P050 NO COST TIME EXTENSION. |
| 2026-08-10 | P00049 | Supplemental agreement (work within scope) | $70.5K | MOD P049 REA COATING MATERIAL INCREASE PG7. |
| 2026-06-02 | P00048 | Supplemental agreement (work within scope) | $208.7K | THE PURPOSE OF THIS MODIFICATION IS REA VEQ CAVITATION OVERRUN PG7. |
| 2026-04-30 | P00047 | Supplemental agreement (work within scope) | $460.5K | THE PURPOSE OF THIS MODIFICATION IS REA VEQ CAVITATION OVERRUN PG9. |
| 2026-02-17 | P00046 | Supplemental agreement (work within scope) | $135.1K | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE P00037 TAR ABATEMENT. REA COATING MATERIAL PG8 & PG9. |
| 2026-01-21 | P00045 | Supplemental agreement (work within scope) | $256.0K | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE P00037 TAR ABATEMENT. PG8 VEQ CAVITATION OVERRUN |
| 2025-07-28 | P00044 | Change order definitized | -$145.6K | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE P00037 TAR ABATEMENT. |
| 2025-06-10 | P00043 | Funding only | $7.68M | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: INCREMENTAL FUNDING MODIFICATION FOR UNITS PG7, PG8, AND PG9. |
| 2025-04-17 | P00042 | Administrative change | $0 | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: ADMINISTRATIVE CO CHANGE |
| 2025-03-13 | P00041 | Supplemental agreement (work within scope) | $109.0K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: REA COATING MATERIAL PG11 & 12. |
| 2025-03-07 | P00040 | Supplemental agreement (work within scope) | $2.1K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: P12 ADDITIONAL VEQ CAVITATION OVERRUN. |
| 2025-02-24 | P00039 | Supplemental agreement (work within scope) | -$105.9K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: P11 QTY DECREASE & DE-OB. |
| 2025-02-11 | P00038 | Supplemental agreement (work within scope) | $538.7K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: P12 VEQ CAVITATION OVERRUN |
| 2024-12-12 | P00037 | Change order | $417.0K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: CHANGE ORDER P5 P6 CRACK AND LEAK REPAIRS |
| 2024-11-18 | P00036 | Change order definitized | -$28.7K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: DEFINITIZE CHANGE ORDER P00033. |
| 2024-09-17 | P00035 | Supplemental agreement (work within scope) | $556.1K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: INCREMENTAL FUNDING MODIFICATION. |
| 2024-05-31 | P00034 | Funding only | $828.7K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: INCREMENTAL FUNDING MODIFICATION. |
| 2024-05-21 | P00033 | Change order | $85.0K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: PGP P6 PAINT & TAR REMOVAL |
| 2024-05-08 | P00032 | Supplemental agreement (work within scope) | $0 | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: 01 14 30 OUTAGES CHANGES |
| 2024-04-16 | P00031 | Change order definitized | -$2.4K | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: DEFINITIZE MOD P28 SUCTION TUBE WELD REPAIRS |
| 2024-03-11 | P00030 | Funding only | $5.90M | 140R1020C0012 JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: INCREMENTAL FUNDING MODIFICATION PG11 & PG12 |
| 2024-01-22 | P00029 | Supplemental agreement (work within scope) | $53.2K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: P5 PAINT TAR ABATEMENT |
| 2024-01-12 | P00028 | Change order | $10.0K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: P5 SUCTION TUBE WELD REPAIRS |
| 2024-01-12 | P00027 | Supplemental agreement (work within scope) | $30.8K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: P6 CAVITATION VEQ |
| 2023-12-01 | P00026 | Supplemental agreement (work within scope) | $7.8K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: REA P5 GROOVE WELD REPAIRS |
| 2023-10-17 | P00025 | Supplemental agreement (work within scope) | $12.0K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: VEQ OVERRUN P5 CAVITATION REPAIRS |
| 2023-08-31 | P00024 | Funding only | $4.34M | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: BILATERAL MODIFICATION FOR WORK WITHIN SCOPE, PG10, P5, P6 REA |
| 2023-08-26 | P00023 | Supplemental agreement (work within scope) | $147.2K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: BILATERAL MODIFICATION FOR WORK WITHIN SCOPE, PG10, P5, P6 REA |
| 2023-07-25 | P00022 | Supplemental agreement (work within scope) | $499.6K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: VEQ MODIFICATION FOR PG10 CAVITATION REPAIRS. |
| 2023-05-17 | P00021 | Supplemental agreement (work within scope) | $1.6K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: BILATERAL MODIFICATION FOR WORK WITHIN SCOPE |
| 2023-04-07 | P00020 | Funding only | $2.93M | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: INCREMENTAL FUNDING MODIFICATION |
| 2023-03-01 | P00019 | Supplemental agreement (work within scope) | $25.4K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: P2 CLIN 10 VEQ ADJUSTMENT |
| 2023-01-23 | P00018 | Supplemental agreement (work within scope) | $0 | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: PERIOD OF PERFORMANCE CORRECTION |
| 2023-01-03 | P00017 | Supplemental agreement (work within scope) | $90.0K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: P1 P2 EPOXY REA |
| 2022-12-09 | P00016 | Supplemental agreement (work within scope) | $222.1K | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: P1 CLIN 0010 VEQ OVERRUN ADJUSTEMENT |
| 2022-10-31 | P00015 | Change order definitized | $0 | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: DEFINITIZE P014 SAFETY MOD CHANGE ORDER |
| 2022-10-25 | P00014 | Supplemental agreement (work within scope) | $0 | JOHN W. KEYS III PUMP-GENERATING PLANT DISCHARGE TUBE COATING-LINING REHABILITATION: FY22 INCREMENTAL FUNDING MODIFICATION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗