Garco Construction, Inc. received this contract from Pacific NW Region PN 6615, Bureau of Reclamation: $61.21M obligated so far for construction of other non-building facilities. It runs to 2027-06-01.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 140R1023C0008, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_140R1023C0008_1425_-NONE-_-NONE-
Garco Construction, Inc.: all federal awards · Department of the Interior: spending · Pacific NW Region PN 6615: what it buys · The follow-on: recompete brief
CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON
Up for re-bid: ends 2027-06-01. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
56 actions since 2023-09-13. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-16 | P00056 | Funding only | $3.01M | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: FULLY FUND INCREMENTALLY FUNDED CONTRACT |
| 2026-09-16 | P00055 | Change order definitized | $336.7K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZE P00013 MCC UNIT SUBSTATION CHANGES |
| 2026-09-02 | P00054 | Change order | $15.0K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 228, GRAVITY DRAINAGE SYSTEM FLOOR DRAIN TRAPS UNILATERAL CHANGE ORDER |
| 2026-09-01 | P00053 | Change order definitized | $1.66M | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZATION OF P00032 FLOW & DIVERSION CHANGES |
| 2026-08-04 | P00052 | Supplemental agreement (work within scope) | $369.7K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZE P00033 UNWATERING PLAN CHANGES AND DEMO REMOVAL OF TEMPORARY OUTFALL |
| 2026-06-12 | P00051 | Change order | $19.0K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI-229 LOUVERS |
| 2026-05-18 | P00050 | Supplemental agreement (work within scope) | $0 | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: CONCRETE PEDESTAL REBAR CHANGES |
| 2026-03-27 | P00049 | Change order definitized | $434.2K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZATION OF P00009, P00010, P00015, AND P00028 TEMPORARY CONTAINMENT STRUCTURE |
| 2026-03-19 | P00048 | Change order | $10.0K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RIVERBED CHANGES |
| 2026-02-13 | P00047 | Change order | $16.7K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 186 EQUIPMENT BOLLARDS |
| 2026-02-13 | P00046 | Change order | $0 | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 218 HI 9.8 PUMP SPEC CHANGE |
| 2025-12-31 | P00045 | Change order | $2.7K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 206 FALSE WEIR DRAIN VALVE STEM GUIDE |
| 2025-12-30 | P00044 | Change order | $3.6K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 198 FISH LOCK WALL REVISIONS |
| 2025-12-30 | P00043 | Change order | $12.0K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: PIT TAG BLOCK OUTS |
| 2025-12-29 | P00042 | Change order | $31.0K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: STILLING BASIN CLEANING FOR REPAIR IDENTIFICATION |
| 2025-12-15 | P00041 | Change order definitized | $667 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZE P00018 DAVIT ARM SYSTEMS |
| 2025-12-08 | P00040 | Change order definitized | $16.0K | CLE ELUM DAM FISH PASSAGE ADULT COLLECTION FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: DEFINITIZE P00005 ADDITIONAL DEWATERING AND OBSERVATION WELLS |
| 2025-09-18 | P00039 | Funding only | $9.80M | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: FY 25 SWEPT INCREMENTAL FUNDING |
| 2025-09-12 | P00038 | Change order | $11.1K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 163 FLIPPER GATE AIR CYLINDER |
| 2025-09-11 | P00037 | Supplemental agreement (work within scope) | $110.2K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFP 0001 PIT TAG CONDUIT AND JUNCTION BOXES |
| 2025-08-18 | P00036 | Change order | $23.1K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 147 INTAKE SCREENS SLIDE GATES CONTROLS |
| 2025-08-13 | P00035 | Supplemental agreement (work within scope) | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: LIFT PARTIAL SUSPENSION OF WORK AND INCORPORATES REVISED ENVIRONMENTAL PERMITS FOR THE CLE ELUM DAM FISH PASSAGE |
| 2025-07-17 | P00034 | Supplemental agreement (work within scope) | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 158 TRENCH DRAIN CORRECTIONS |
| 2025-06-10 | P00033 | Change order | $336.7K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: UNWATERING PLAN CHANGES AND DEMO/REMOVAL OF TEMPORARY OUTFALL CHANGE ORDER. |
| 2025-06-07 | P00032 | Change order | $610.0K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 165 & 166 DIVERSION AND CARE OF FLOWS DURING CONSTRUCTION AND TEMPORARY OUTLET WORKS DIVERSION |
| 2025-05-19 | P00031 | Change order | $3.6K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 159 SECURITY CAMERAS |
| 2025-05-09 | P00030 | Change order | $18.2K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: CLSM PIPE TRENCH CHANGE ORDER |
| 2025-05-07 | P00029 | Supplemental agreement (work within scope) | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFIS 130 AND 131 SPLITTER WALL CHANGES |
| 2025-05-02 | P00028 | Change order | $3.93M | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: ADDITIONAL FUNDING FOR TEMPORARY CONTAINMENT STRUCTURE |
| 2025-05-02 | P00027 | Change order | $6.9K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 66 PHONE AND BOOSTER |
| 2025-04-25 | P00026 | Change order | $7.9K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 111 OIL WATER SEPARATOR SLAB |
| 2025-04-25 | P00025 | Supplemental agreement (work within scope) | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: PERIOD OF PERFORMANCE EXTENSION |
| 2025-04-11 | P00024 | Supplemental agreement (work within scope) | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFIS 64 EPOXY REBAR ANCHORS |
| 2025-03-13 | P00023 | Change order | $68.4K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFIS 96 FISH SCREENS GUARDRAIL CLASH |
| 2025-03-13 | P00022 | Supplemental agreement (work within scope) | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 148 CJP WELD DELETE |
| 2025-03-05 | P00021 | Change order | $21.0K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFIS 72, 76, 110, 112, 114, 127, AND 146, MISC. MECHANICAL PUMPS, UNILATERAL CHANGE ORDER |
| 2025-03-05 | P00020 | Change order | $21.6K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 35 SIGNAGE AND PANEL DRAWINGS UNILATERAL CHANGE ORDER |
| 2025-03-05 | P00019 | Change order | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 115 HVAC FANS, NO COST UNILATERAL CHANGE ORDER |
| 2025-03-05 | P00018 | Change order | $2.9K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 98 DAVIT ARMS SYSTEMS UNILATERAL CHANGE ORDER |
| 2025-02-11 | P00017 | Change order | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 100 UNIT SKYLIGHTS NO COST UNILATERAL CHANGE ORDER |
| 2025-02-05 | P00016 | Supplemental agreement (work within scope) | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: P00016 COMMUNICATION CABLING, TELEPHONE, SECURITY, AND SURVEILLANCE SYSTEM |
| 2024-12-03 | P00015 | Change order | $5.14M | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: P00010 SUPPLEMENTAL FUNDING CHANGE ORDER |
| 2024-09-20 | P00013 | Change order | $45.0K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: MOTOR CONTROL CENTER (MCC) UNILATERAL CHANGE ORDER |
| 2024-09-18 | P00012 | Funding only | $4.26M | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: INCREMENTAL FUNDING END OF YEAR FY2024 |
| 2024-09-12 | P00011 | Change order | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: CHANGE ORDER, VERTICAL ATTRACTION PUMPS, TRENCH SUMP VERTICAL PUMPING UNITS |
| 2024-09-10 | P00010 | Change order | $2.94M | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: TEMPORARY CONTAINMENT STRUCTURE WORK PLAN #2 |
| 2024-08-27 | P00009 | Change order | $5.00M | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: TEMPORARY CONTAINMENT STRUCTURE WORK PLAN |
| 2024-08-27 | P00008 | Change order | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: WEIR BLAD MATERIAL CHANGE NO-COST BILATERAL CHANGE ORDER |
| 2024-06-27 | P00007 | Change order | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: LAND USE AND SAFETY QUALIFICATIONS BILATERAL CHANGE ORDER |
| 2024-04-19 | P00006 | Change order | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: STOREFRONT WINDOWS BILATERAL CHANGE ORDER |
| 2024-03-14 | P00005 | Change order | $879.8K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: ADDITIONAL DEWATERING WELLS CHANGE ORDER |
| 2024-03-07 | P00004 | Change order | $932.4K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: RFI 2 AND 3 SLIDE GATE AND SCREEN ACTUATORS CHANGE ORDER. |
| 2023-10-26 | P00003 | Supplemental agreement (work within scope) | $4.8K | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: PARTNERING SESSION MOD |
| 2023-10-17 | P00002 | Supplemental agreement (work within scope) | $0 | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: PERIOD OF PERFORMANCE AND TABLE OF CONTENTS REVISION |
| 2023-09-19 | P00001 | Funding only | $2.50M | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON: INCREMENTAL FUNDING ONLY |
| 2023-09-13 | 0 | $18.60M | CLE ELUM DAM FISH PASSAGE FACILITY ADULT FACILITY, YAKIMA RIVER BASIN WATER ENHANCEMENT PROJECT, WASHINGTON |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗