140R4024F0099↗

Hydra Engineering & Construction, LLC received this contract from Upper Colorado Regional Office, Bureau of Reclamation: $300.3K obligated so far for construction of office buildings. Its period of performance ended 2025-11-01.

Key facts · data as of Oct 23, 2026

Recipient
Hydra Engineering & Construction, LLC
Awarding agency
Bureau of Reclamation (Department of the Interior)
Contracting office
Upper Colorado Regional Office (140R40)
Obligated to date
$300.3K
Potential value
$300.3K
Ends
2025-11-01

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award 140R4024F0099, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_140R4024F0099_1425_140F0822D0055_1448

BIG SANDY BOAT RAMP

Delivery Order · Bureau of Reclamation · to Hydra Engineering & Construction, LLC (UEI HVA8QVX8YST1) · data as of 2026-10-23

Obligated to date$300.3K5 actions
Current value$300.3Kwith options exercised
Period2024-09-20 → 2025-11-01current end date

What it is

Product or service
Construction of Office Buildings (PSC Y1AA)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
Upper Colorado Regional Office (140R40)
Competition
Full and open after exclusion of sources · 1 offer received
Set-aside
Small business
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 140F0822D0055
Solicitation
140R4024R0023
Where the work is
Sublette, WY · district WY-00

Obligations by fiscal year

FY2024$267.1K
FY2025$33.1K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

5 actions since 2024-09-20. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2025-09-09P00004Supplemental agreement (work within scope)$33.1KBIG SANDY BOAT LAUNCH - THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE BOAT RAMP.
2025-07-15P00003Administrative change$0BIG SANDY BOAT LAUNCH - THE PURPOSE OF THIS MODIFICATION IS TO CHANGE CONTRACTING OFFICER (CO).
2025-06-13P00002Supplemental agreement (work within scope)$0BIG SANDY BOAT LAUNCH - THE PURPOSE OF THIS MODIFICATION IS TO EXTEND POP END DATE TO 11/01/2025.
2025-04-15P00001Administrative change$0CHANGE THE CONTRACTING OFFICER REPRESENTATIVE (COR) FROM JUAN ALMODOVAR-ORTIZ TO ASHLEE HILTON EFFECTIVE 15 APRIL 2025.
2024-09-200$267.1KBIG SANDY BOAT RAMP

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗