15F06721F0000957↗
Brasfield & Gorrie LLC received this contract from Fbi-Jeh, Federal Bureau of Investigation: $59.1K obligated so far for construction of other utilities. Its period of performance ended 2023-10-16.
Key facts · data as of Oct 23, 2026
- Recipient
- Brasfield & Gorrie LLC
- Awarding agency
- Federal Bureau of Investigation (Department of Justice)
- Contracting office
- Fbi-Jeh (15F067)
- Obligated to date
- $59.1K
- Potential value
- $14.46M
- Ends
- 2023-10-16
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 15F06721F0000957, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_15F06721F0000957_1549_15F06719D0003691_1549
Brasfield & Gorrie LLC: all federal awards · Department of Justice: spending · Fbi-Jeh: what it buys
TO 21-0038 CONSTRUCTION SERVICES FOR SUBSTATION #24 EMERGENCY GENERATORS AT REDSTONE ARSENAL
What it is
- Product or service
- Construction of Other Utilities (PSC Y1NZ)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Fbi-Jeh (15F067)
- Competition
- Full and open competition · 4 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 15F06719D0003691
- Where the work is
- Madison, AL · district AL-05
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
3 actions since 2023-03-23. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2024-01-19 | P00009 | Close-out | $0 | NORTH CAMPUS BACKUP GENERATOR PROJECT. CONTRACT CLOSEOUT. |
| 2023-12-18 | P00008 | Supplemental agreement (work within scope) | $34.7K | THIS MODIFICATION IS ISSUE TO INCORPORATE FUNDS FOR THE GENERATOR BLACK START TEST CONDUCTED OCTOBER 7, 2023. |
| 2023-03-23 | P00007 | Supplemental agreement (work within scope) | $24.4K | NORTH CAMPUS BACKUP GENERATOR PROJECT. P00007: INCORPORATE INCREASE FOR GOVERNMENT-INITIATED REMOBILIZATION FOR BLACK START TESTING. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗