30 subawards totaling $20.14M (31.0% of what was obligated), as Education & Training Resources LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Minact Inc | $16.68M | 1 | MS | 2022-10-01 | 2022-10-01 |
| Institute for Psychological Advancement LLC | $1.35M | 4 | MO | 2023-02-10 | 2025-10-06 |
| The Locums Co, LLC | $541.8K | 4 | NC | 2023-02-10 | 2025-10-20 |
| Performance Roofing Inc | $484.8K | 4 | OK | 2023-02-16 | 2025-03-10 |
| Summit Heating and Cooling, LLC | $201.5K | 2 | MO | 2024-06-06 | 2024-09-30 |
| Lippert Mechanical Service LLC | $167.1K | 2 | IL | 2025-01-02 | 2026-03-16 |
| Joseph A. Bellafiore, D.D.S., P.A. | $151.2K | 2 | KS | 2023-04-27 | 2024-10-08 |
| O'Dell Service Company | $139.7K | 3 | MO | 2023-03-29 | 2023-04-28 |
| Siemens Aktiengesellschaft | $100.7K | 1 | IL | 2023-04-26 | 2023-04-26 |
| Lexington Plumbing & Heating Company, Inc. | $75.5K | 1 | MO | 2026-04-17 | 2026-04-17 |
| Ameren Transmission Company, LLC | $64.0K | 2 | MO | 2025-08-01 | 2025-09-01 |
| Api Group Corp | $52.0K | 1 | TX | 2024-09-09 | 2024-09-09 |
| Design Mechanical Inc | $49.6K | 1 | KS | 2024-08-28 | 2024-08-28 |
| KH Engineering Group, P.A | $42.4K | 1 | KS | 2023-12-27 | 2023-12-27 |
| Siemens Industry Inc | $41.8K | 1 | IL | 2026-06-01 | 2026-06-01 |
| Date | To | Amount | For |
|---|---|---|---|
| 2022-10-01 | Minact, Inc | $16.68M | EXCELSIOR SPRINGS JOB CORPS CENTER - CENTER OPS AND OA 11/25/2025 ADDED: OCTOBER 2022 - SEPT 2024 EXCELSIOR SPRINGS JOB CORPS CENTER - CENTER OPS AND OA 1/13/25: CHANGE ORDER 1 INCREASING MONIES FOR PERIOD OCT 2024 -… |
| 2023-04-28 | Institute for Psychological Advancement LLC | $489.4K | BPA CONTRACT CMHC SERVICES, APRIL 1, 2023-SEPTEMBER 30, 2024 |
| 2025-10-06 | Institute for Psychological Advancement LLC | $359.7K | BPO MENTAL HEALTH SERVICES OCTOBER 1, 20025, TO SEPTEMBER 30, 2026 |
| 2024-10-15 | Institute for Psychological Advancement LLC | $342.6K | BPO FOR STUDENT MENTAL HEALTH SERVICES OPTION YEAR 1: OCTOBER 1, 2024 TO SEPTEMBER 30, 2025 |
| 2024-05-01 | Performance Roofing Inc | $294.9K | CRA 141242 MOD 25 ROOF REPLACEMENT BUILDING 06 VOCATIONAL TRADE BUILDING FIRST PAYMENT (DEPOSIT) - PRIOR TO WORK BEING STARTED - VENDOR MUST FIRST PROVIDE 100% PERFORMANCE & 100% PAYMENT BOND. FINAL PAYMENT -… |
| 2023-04-28 | The Locums Co, LLC | $181.6K | CENTER PHYSICIAN SERVICE BPA CONTRACT- APRIL 1, 2023-SEPTEMBER 30, 2024 |
| 2023-02-10 | Institute for Psychological Advancement LLC | $156.2K | BPA-EXTENSION PERIOD 180 DAYS FOR CMHC SERVICES |
| 2025-10-20 | The Locums Co, LLC | $152.2K | BPO 10/1/2025-9/30/2026 STUDENT CENTER PHYSICIAN SERVICES. 18/HR PER WEEK |
| 2024-10-08 | The Locums Co, LLC | $148.5K | BPO FOR STUDENT PHYSICIAN SERVICES BASE YEAR 1: OCTOBER 1,2024 TO SEPTEMBER 30, 2025 |
| 2024-09-30 | Summit Heating and Cooling, LLC | $138.6K | CRA 55822 MOD 30: ACADEMICS BUILDING 002 HVAC REPLACEMENT |
| 2026-03-16 | Lippert Mechanical Service LLC | $127.5K | CRA ID: 62359, DEF #: 167157, GONZALES HALL- HEAT PUMP REPLACEMENT & REPAIR. |
| 2023-04-26 | Siemens Industry Inc | $100.7K | CRA DEF 148789, CRA ID 49450, FUNDING MOD 8, FOP 9197:236 - BUILDINGS 6, 12, 14, 33, 48, & 51 ADDRESSING FIRE SAFETY NEEDS (LIFE SAFETY DEFICIENCIES 144401, 144668, 144669, 92129, 144420, 144463, 144451). |
| 2025-03-10 | Performance Roofing Inc | $100.0K | CAFETERIA ROOF OVERLAY CRA #357771 DEF #141161 MOD #35 |
| 2023-04-27 | Joseph A. Bellafiore, D.D.S., P.A. | $90.3K | CENTER DENTAL SERVICE BPA CONTRACT, APRIL 1, 2023-SEPTEMBER 30, 2024 |
| 2026-04-17 | Lexington Plumbing & Heating Company, Inc. | $75.5K | EMERGENCY DIAGNOSTIC VISIT TO LOCATE GAS LEAK ON CENTER AND ESTIMATE REPAIR COST. CO 1: CHANGED LINE ONE DESCRIPTION FROM "DIAGNOSTIC VISIT" TO "DIAGNOSTIC VISIT/LABOR/LINE MAPPING." CHANGED GROSS UNIT COST FROM… |
| 2024-06-06 | Summit Heating and Cooling, LLC | $62.9K | CRA 156240 MOD 26 - BUILDING 50 HVAC REPLACEMENT |
| 2024-10-08 | Joseph A. Bellafiore, D.D.S., P.A. | $60.9K | BPO FOR STUDENT DENTAL SERVICES OPTION YEAR 1: OCTOBER 1, 2024 TO SEPTEMBER 30, 2025 |
| 2023-02-10 | The Locums Co, LLC | $59.5K | BPA- CENTER PHYSICIAN SERVICE CONTRACT EXTENSION 6 MONTHS. OCT 2022- FEB 2023 SEPARATE POS CREATED |
| 2024-09-09 | Api Group Life Safety USA LLC | $52.0K | DEF #158063 MOD 29: REPLACEMENT FIRE SPRINKLER SYSTEM IN GONZALES CRA # 54956 |
| 2024-08-28 | Design Mechanical Inc | $49.6K | (158086) CRA ID 55745 WALK-IN FREEZER REFRIGERATION EQUIPMENT, BUILDING 56, CAFETERIA IS MALFUNCTIONING |
| 2023-04-05 | O'Dell Service Company | $48.8K | BOILER REPLACEMENT IN BUILDING 0014, ROOSEVELT HALL |
| 2023-03-29 | O'Dell Service Company | $48.8K | BUILDING 14 "ROOSEVELT HALL" BOILER REPLACEMENT. THIS CRA PROJECT IS A B1A EMERGENCY REQUEST, DEF #147206 MOD #5 FOP #183 THE EXISTING BOILER IN ROOSEVELT HALL HAD REACHED THE END OF ITS LIFESPAN. IT HAD… |
| 2023-03-15 | Performance Roofing Inc | $45.0K | CPP ASPHALT SINGLE ROOF REPLACEMENT. CRA B1A DEF # 141160 |
| 2023-02-16 | Performance Roofing Inc | $45.0K | CRA B1A DEF 141160 CCP ROOF REPLACEMENT VENDOR STATES CONSISTENT 40 DEGREE WEATHER REQUIRED BEFORE ROOF REPLACEMENT CAN BEGIN |
| 2023-12-27 | KH Engineering Group, P.A | $42.4K | CRA 153728 MOD 21 RECREATION BUILDING PHASE II |
58 actions since 2022-10-28. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-15 | P00059 | Funding only | $1.27M | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2026-08-20 | P00058 | Funding only | $46.1K | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2026-07-29 | P00057 | Funding only | $6.81M | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2026-06-29 | P00056 | Supplemental agreement (work within scope) | $21.3K | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2026-06-17 | P00055 | Funding only | -$35.8K | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2026-04-15 | P00054 | Funding only | $100.0K | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2026-04-01 | P00053 | Funding only | $3.32M | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2026-02-20 | P00052 | Funding only | -$202.4K | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2026-02-18 | P00051 | Funding only | $2.9K | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2026-02-10 | P00050 | Funding only | $127.5K | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2025-12-18 | P00049 | Funding only | $4.58M | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2025-12-03 | P00048 | Funding only | $16.5K | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2025-09-22 | P00047 | Option exercised | $3.35M | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2025-08-07 | P00046 | Supplemental agreement (work within scope) | $0 | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2025-07-11 | P00045 | Funding only | $4.00M | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2025-05-29 | P00044 | Funding only | $1.67M | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2025-05-12 | P00043 | Change order definitized | $0 | EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS |
| 2025-03-28 | P00042 | Change order definitized | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE CHANGES TO THE STATEMENT OF WORK THAT WERE ISSUED IN A CHANGE ORDER DATED FEBRUARY 27, 2025. THEREFORE, THE CONTRACT PRICE IS REDUCED AS REFLECTED IN THE ATTACHED EXCEL SPREADSHEET DUE TO THE IMPLEMEN |
| 2025-03-12 | P00041 | Administrative change | -$2.06M | THE PURPOSE OF THIS MODIFICATION IS TO REDUCE THE ESTIMATED COSTS AND DE-OBLIGATE FUNDING FOR THE PY 23 AND PY 24 UDO FUNDS DEOBLIGATION IN THE AMOUNT OF $2,060,806.63. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00041, CONTRACT: 1605JW-2 |
| 2025-02-25 | P00040 | Funding only | $40.0K | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND CRA. |
| 2025-02-12 | P00039 | Funding only | $3.57M | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE WAGE DETERMINATIONS 2015-5105 (REV. 20), DATED JULY 14, 2023, INCREASE THE ESTIMATED PRICE BY $6,012,005.89 FOR THE FOLLOWING CLINS, AND OBLIGATE $3,567,009.08 IN OPERATIONS (A, C1) FUNDING FOR CY1, |
| 2025-01-31 | P00038 | Change order | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REPLACE THE FOLLOWING CLAUSES WITH VERBIAGE BELOW FOR THIS CONTRACT. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00038, CONTRACT: 1605JW-22-C-0008. |
| 2025-01-31 | P00037 | Funding only | $8.5K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $8,500 IN CRA (B1) FUNDING FOR CY 3 AND TO DEFINITIZE CHANGES TO THE STATEMENT OF WORK THAT WERE ISSUED IN A CHANGE ORDER DATED DECEMBER 20, 2024. THEREFORE, THE CONTRACT PRICE IS REDUCED AS REFLECTED IN THE |
| 2025-01-22 | P00036 | Funding only | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REMOVE THE DEIA SECTION OF THIS CONTRACT. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00036, CONTRACT: 1605JW-22-C-0008. |
| 2024-12-04 | P00035 | Funding only | $144.5K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $144,508.96 IN CRA (B1) FUNDING FOR CY 3. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00035, CONTRACT: 1605JW-22-C-0008. REQUISITION# 1631-OJC-25-CJ5-0014. MOD WORKSPACE: ACQ-M-25-0437 |
| 2024-11-13 | P00034 | Funding only | $76.0K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $76,000 IN OPERATIONS (B4) FUNDING FOR CY 3. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00034, CONTRACT: 1605JW-22-C-0008. REQUISITION# 1631-OJC-25-OJ5-0011. MOD WORKSPACE: ACQ-M-25-0312. |
| 2024-10-18 | P00033 | Funding only | $18.5K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $18,475.33 IN CRA (B1) FUNDING FOR CY 3. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00033, CONTRACT: 1605JW-22-C-0008. REQUISITION# 1631-OJC-25-CJ5-0006. MOD WORKSPACE: ACQ-M-25-0062. |
| 2024-09-20 | P00032 | Funding only | $8.10M | THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE THE OPTION YEAR ONE (1), POP: OCT 01, 2024 THROUGH SEPTEMBER 30, 2025, UPDATE THE WAGE DETERMINATIONS FOR CONSTRUCTION AND SERVICE CONTRACTS, AND OBLIGATE $8,516,960.90 IN OPERATIONS (A, C1, C2, B2) FUN |
| 2024-08-20 | P00031 | Funding only | $40.0K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $40,000 IN CRA (B1B) FUNDING FOR CY 2. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00031, CONTRACT: 1605JW-22-C-0008. REQUISITION# 1631-OJC-24-CJ5-0089. |
| 2024-08-05 | P00030 | Funding only | $138.6K | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE ESTIMATED COST FOR THE FOLLOWING CLINS BY $300,000 EACH AND OBLIGATE $138,596 (CLIN 0006) IN CRA (B1) FUNDING FOR CY 2. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00030, CONTRACT: 1605JW-2 |
| 2024-07-22 | P00029 | Funding only | $2.76M | THE PURPOSE OF THIS MODIFICATION IS TO ADD $2,761,963.47, CONSISTING OF $2,625,036 IN OPERATIONS (A, C1, C2) AND $136,927.47 IN CRA (B1) FUNDING FOR CY 2. ADDITIONALLY, IT IS TO INCORPORATE THE CONFORMANCE APPROVAL FOR CLASSIFICATIONS AND WAGE RATES |
| 2024-05-20 | P00028 | Funding only | $12.7K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $12,696 IN EQUIPMENT (B2) FUNDING FOR CY 2. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00028, CONTRACT: 1605JW-22-C-0008. REQUISITION# 1631-OJC-24-OJ5-0070. |
| 2024-05-08 | P00027 | Funding only | $10.5K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $10,504 IN CRA (B1) FUNDING FOR CY 2. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00027, CONTRACT: 1605JW-22-C-0008. REQUISITION# 1631-OJC-24-CJ5-0057 |
| 2024-04-10 | P00026 | Funding only | $62.9K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $62,926.00 IN CRA (B1) FUNDING FOR CY 2. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00026, CONTRACT: 1605JW-22-C-0008. REQUISITION# 1631-OJC-24-CJ5-0046. |
| 2024-03-04 | P00025 | Funding only | $294.9K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $294,879.00 IN CRA (B1) FUNDING FOR CY 2. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00025, CONTRACT: 1605JW-22-C-0008. REQUISITION# 1631-OJC-24-CJ5-0036. |
| 2024-02-22 | P00024 | Funding only | $6.56M | THE PURPOSE OF THIS MODIFICATION IS TO ADD $6,562,590.40 IN IN OPERATIONS (A, C1, C2) FUNDING FOR CY 2. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00024, CONTRACT: 1605JW-22-C-0008. REQUISITION# 1631-OJC-24-OJ5-0036. |
| 2024-01-30 | P00023 | Funding only | $41.2K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $41,167.53 IN OPERATIONS (A) FUNDING FOR CY 1 AND CY 2 AND TO INCORPORATE THE MINIMUM WAGE INCREASE REQUEST FOR EQUITABLE ADJUSTMENT (REA) TO FUND THE $16.20 MINIMUM WAGE INCREASE IN ACCORDANCE WITH EXECUTIV |
| 2024-01-11 | P00022 | Funding only | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE MINIMUM WAGE RATE FROM $16.20 PER HOUR TO $17.20 PER HOUR EFFECTIVE JANUARY 1, 2024. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00022, CONTRACT: 1605JW-22-C-0008. |
| 2023-11-28 | P00021 | Funding only | $42.4K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $42,350.00 IN CRA (B1) FUNDS. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00021, CONTRACT: 1605JW-22-C-0008, REQ: 1631-OJC-24-CJ5-0015. |
| 2023-11-17 | P00020 | Funding only | $4.9K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $4,868.65 IN CRA (B1) FUNDS. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00020, CONTRACT: 1605JW-22-C-0008, REQ: 1631-OJC-24-CJ5-0014. |
| 2023-11-08 | P00019 | Funding only | $4.1K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $4,140.47 IN CRA (B1) FUNDS. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00019, CONTRACT: 1605JW-22-C-0008, REQ: 1631-OJC-24-CJ5-0009. |
| 2023-11-03 | P00018 | Funding only | $3.9K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $3,936.94 IN CRA (B1) FUNDS. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00018, CONTRACT: 1605JW-22-C-0008, REQ: 1631-OJC-24-CJ5-0006. |
| 2023-09-25 | P00017 | Funding only | $6.58M | THE PURPOSE OF THIS MODIFICATION IS TO ADD $6,582,592.14 CONSISTING OF $6,562,590.40 IN OPERATIONS (A, C1, C2) AND $20,001.74 IN CRA (B1) FUNDS. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00017, CONTRACT: 1605JW-22-C-0008, REQ: 1631-OJC-23- |
| 2023-09-11 | P00016 | Funding only | $16.0K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $16,000 IN OPERATIONS (B2-EQUIPMENT) FUNDING FOR CY 1 AND UPDATES THE WAGE DETERMINATION FOR CONSTRUCTION AND SERVICE CONTRACTS. EXCELSIOR SPRINGS JOB CORPS CENTER WITH OA/CTS, MOD P00016, CONTRACT: 1605JW-2 |
| 2023-07-21 | P00015 | Funding only | $76.0K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $76,000 IN OPERATIONS (B4) FUNDING FOR CY 1. MOD P00015, CONTRACT: 1605JW-22-C-0008, REQ: 1631-OJC-23-OJ5-0080 |
| 2023-06-28 | P00014 | Funding only | $27.6K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $27,573.41 IN EQUIPMENT FUNDING FOR CY 1. MOD P00014, CONTRACT: 1605JW-22-C-0008, REQ: 1631-OJC-23-OJ3-0117. |
| 2023-06-22 | P00013 | Funding only | -$221.4K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE $221,357 IN OPERATIONS (A) FUNDING FOR CY 1 FOR THE STAFF VACANCY TAKEBACK. MOD P00013, CONTRACT: 1605JW-22-C-0008, REQ: 1631-OJC-23-OJ5-0070. |
| 2023-06-06 | P00012 | Funding only | $4.5K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $4,459.30 IN CRA (B1) FUNDING FOR CY 1. MOD P00012, CONTRACT: 1605JW-22-C-0008, REQ: 1631-OJC-23-CJ5-0053. |
| 2023-05-23 | P00011 | Funding only | -$91.1K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE $91,086 IN OPERATIONS (C1, C2) FUNDING AND TO UPDATE SECTION B, SECTION C, AND SECTION F OF THE CONTRACT DESCOPING ALL OA/CTS SERVICES FROM THE MINGO CENTER EFFECTIVE APRIL 1, 2023 FOR THE REMAINDER |
| 2023-04-17 | P00010 | Funding only | $80.3K | THE PURPOSE OF THIS MODIFICATION IS TO ADD 80,268 IN CRA (B1, B1B) FUNDING FOR CY 1 TO THE CONTRACT. |
| 2023-03-31 | P00009 | Funding only | $11.2K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $11,245 IN CRA (B1) FUNDING FOR CY 1 TO THE CONTRACT. |
| 2023-03-21 | P00008 | Funding only | $109.5K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $109,542 IN CRA (B1) FUNDING FOR CY 1 TO THE CONTRACT. |
| 2023-01-06 | P00007 | Funding only | $64.6K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $64,624 IN CRA (B1 AND B2) FUNDING FOR CY TO THE CONTRACT. |
| 2022-12-21 | P00006 | Funding only | $1.9K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $1,894 IN CRA (B1) FUNDING FOR CY TO THE CONTRACT. |
| 2022-12-21 | P00005 | Funding only | $53.6K | THE PURPOSE OF THIS MODIFICATION IS TO ADD $53,580 IN CRA (B1) FUNDING FOR CY TO THE CONTRACT. |
| 2022-12-13 | P00004 | Funding only | $1.9K | THE PURPOSE OF THIS MODIFICATION IS FOR THE SPECIAL INITIATIVE JOB CORPS 2.0 LEADERSHIP SUMMIT. THIS INITIATIVE WILL BE FOR THE TRAVEL FOR ONE (1) STUDENT AND CENTER DIRECTOR. THE ESTIMATED COST OF THE TRAVEL IS $1,857. |
| 2022-11-30 | P00003 | Funding only | $13.30M | INCREMENTAL FUNDING |
| 2022-10-28 | P00002 | Funding only | $40.0K | INCREMENTAL FUNDING |