Deloitte & Touche LLP received this contract from Pension Benefit Guaranty Corp, Pension Benefit Guaranty Corporation: $13.80M obligated so far for special studies/analysis- accounting/financial management. It runs to 2027-09-28.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 16PBGC22M0009, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_16PBGC22M0009_1665_16PBGC22A0005_1665
Deloitte & Touche LLP: all federal awards · Pension Benefit Guaranty Corporation: spending · Pension Benefit Guaranty Corp: what it buys · The follow-on: recompete brief
PDR SUPPORT SERVICES
Up for re-bid: ends 2027-09-28. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
1 subaward totaling $98.8K (0.7% of what was obligated), as Deloitte & Touche LLP reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Ark Solutions, Inc. | $98.8K | 1 | VA | 2023-07-13 | 2023-07-13 |
| Date | To | Amount | For |
|---|---|---|---|
| 2023-07-13 | Ark Solutions, Inc. | $98.8K | PARTICIPANT DATA REVIEW SUPPORT SERVICES |
18 actions since 2023-07-13. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-30 | P00018 | Administrative change | $0 | THE PURPOSE OF THIS UNILATERAL MODIFICATION IS TO CORRECT AN ADMINISTRATIVE ERROR IN THE ACQUISITION MANAGEMENT SYSTEM. |
| 2026-09-18 | P00017 | Option exercised | $4.01M | EXERCISE OPTION PERIOD FOUR CLINS 4001 - 4006 |
| 2026-08-05 | P00016 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ALIGN THE CLINS IN PBGC'S ACQUISITION MANAGEMENT SYSTEM (AMS) WITH THE CONTRACT PRICE SCHEDULE. ALL OTHER TERMS AND CONDITIONS OF THE CONTRACT REMAIN THE SAME. |
| 2026-06-24 | P00015 | Administrative change | $0 | REALLOCATION OF LABOR HOURS IN OPTION PERIOD THREE AND TO REVISE GSA LABOR RATES IN OPTION PERIODS THREE AND FOUR |
| 2026-01-20 | P00014 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 3 WITH FAR 52.217-9 OPTION TO EXTEND THE TERMS OF THE CONTRACT (MAR 2000), FOR THE PERIOD OF PERFORMANCE OF SEPTEMBER 29, 2025 THROUGH SEPTEMBER 28, 2026. |
| 2025-09-24 | P00013 | Option exercised | $3.91M | THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 3 WITH FAR 52.217-9 OPTION TO EXTEND THE TERMS OF THE CONTRACT (MAR 2000), FOR THE PERIOD OF PERFORMANCE OF SEPTEMBER 29, 2025 THROUGH SEPTEMBER 28, 2026. |
| 2025-09-10 | P00012 | Supplemental agreement (work within scope) | -$5 | THE PURPOSE OF THIS MODIFICATION IS TO RE-ALLOCATE LEVEL OF EFFORT (LOE) IN OPTION PERIOD 2 (OPTIONAL CLIN 2005). |
| 2025-09-04 | P00011 | Funding only | $5.0K | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDING IN THE AMOUNT OF $5,000 TO OPTIONAL CLIN 2006 FOR TRAVEL. |
| 2025-07-21 | P00010 | Supplemental agreement (work within scope) | -$9 | THE PURPOSE OF THIS MODIFICATION IS TO RE-ALLOCATE LEVEL OF EFFORT (LOE) IN OPTION PERIOD 2 (OPTIONAL CLIN 2005). |
| 2025-05-27 | P00009 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE LOCAL CLAUSE PBGC CLAUSE 52.237-7000, KEY PERSONNEL (APRIL 2018) AS FOLLOWS: 1. AUDIT MANAGER REMOVE: TIMOTHY BROZEK ADD: MADISON TRICKER 2. SENIOR AUDITOR REMOVE: NICOLE JUDY ADD: SARA |
| 2025-03-27 | P00008 | Supplemental agreement (work within scope) | -$232 | THE PURPOSE OF THIS MODIFICATION IS TO RE-ALLOCATE THE HOURS IN OPTION PERIOD 1 AND OPTION PERIOD 2. |
| 2024-11-13 | P00007 | Administrative change | $0 | COR CHANGE. |
| 2024-09-25 | P00006 | Funding only | $900.0K | THE PURPOSE OF THE MODIFICATION IS TO OBLIGATE FUNDING TO OPTIONAL CLIN 2005 OF THE CONFORMED TASK ORDER. |
| 2024-09-19 | P00005 | Option exercised | $1.70M | THE PURPOSE OF THIS MODIFICATION IS TO FULLY FUND OPTION PERIOD 2 OPTIONAL CLIN 2003 AND 2004. IN ADDITION, PARTIALLY FUND OPTIONAL CLIN 2005. |
| 2024-09-12 | P00004 | Option exercised | $523.0K | THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE AND FULLY FUND OPTION PERIOD 2 FROM SEPTEMBER 29, 2024, TO SEPTEMBER 28, 2025, IN THE TOTAL AMOUNT OF $522,994.37. |
| 2023-09-22 | P00003 | Option exercised | $1.18M | EXERCISE OPTIONAL CLIN 1005. THE PERIOD OF PERFORMANCE IS SEPTEMBER 29, 2023 TO SEPTEMBER 28, 2024. THIS MODIFICATION ALSO REDUCES OPTIONAL CLIN 1005 CEILING AND THE OVERALL CEILING PRICE OF BY $941,043.70. |
| 2023-08-03 | P00002 | Funding only | $84.3K | PDR SUPPORT SERVICE |
| 2023-07-13 | P00001 | Option exercised | $1.49M | PARTICIPANT DATA REVIEW (PDR) SUPPORT SERVICES |