Putting the award page together from the records…
Putting the award page together from the records…
EHRM INTERFACES
Up for re-bid: ends 2027-09-29. Recompete brief → · DA01--VA-27-00015330 - Mission-Oriented Services for Application Integration and Capabilities (MOSAIC) ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
9 subawards totaling $10.40M (4.6% of what was obligated), as Oracle Health Government Services, Inc. reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Novetta Solutions, LLC | $6.89M | 3 | VA | 2023-01-04 | 2023-02-23 |
| Document Storage Systems, Inc. | $1.59M | 1 | FL | 2023-03-20 | 2023-03-20 |
| Favor Techconsulting, LLC | $1.24M | 3 | VA | 2022-12-09 | 2023-03-15 |
| Microhealth LLC | $473.8K | 1 | VA | 2022-11-29 | 2022-11-29 |
| Atg Innovations LLC | $200.7K | 1 | VA | 2022-10-21 | 2022-10-21 |
| Date | To | Amount | For |
|---|---|---|---|
| 2023-02-23 | Accenture Federal Services LLC | $4.70M | SUBCONTRACTOR WILL PROVIDE PROJECT MANAGEMENT OVERSIGHT AND FACILITATION FOR THE FOLLOWING WAVES/SITES WHOSE DEPLOYMENT ACTIVITIES CURRENTLY FALL WITHIN THE PERIOD OF PERFORMANCE WAVE C, E, D, F, G, H, J |
| 2023-03-20 | Document Storage Systems, Inc. | $1.59M | THE SUBCONTRACTOR SHALL COMPLETE CHANGES ON THE VA-SIDE SYSTEM THAT ARE REQUIRED TO LOCALIZE THE INTEGRATION FOR CARIBOU |
| 2023-01-13 | Accenture Federal Services LLC | $1.19M | SUBCONTRACTOR TO PROVIDE RHAPSODY SUPPORT |
| 2023-01-04 | Accenture Federal Services LLC | $1.01M | PROVIDE EXPERT CONSULTING SERVICES ON RHAPSODY PRODUCT USAGE, CONFIGURATION, AND FUNCTIONALITY |
| 2022-12-09 | Favor Techconsulting, LLC | $630.4K | "THE SUBCONTRACTOR SHALL PROVIDE UP TO THREE (3) RESOURCES TO PROVIDE SUPPORT FOR TASKS OUTLINED IN PWS 5.3.14.2 OR SOME SUBSET THEREOF. SPECIFICALLY, AUGMENTATION OF THE CERNER FIREWALL TEAM IS REQUIRED IN ORDER TO… |
| 2022-11-29 | Microhealth LLC | $473.8K | SUPPORT AND DEVELOP TESTING ARTIFACTS SUCH AS TEST SCENARIOS, TEST CASES, TEST DATA AND TEST RESULTS TO EXECUTE AND REPORT ON ALL TESTING ACTIVITIES AS DIRECTED BY THE T&QA LEAD. THE SUBCONTRACTOR TEST REPORT OF… |
| 2023-03-15 | Favor Techconsulting, LLC | $415.9K | SUBCONTRACTOR SHALL PROVIDE INTERFACE DEVELOPMENT FOR BHL INTERFACE ICR 466 |
| 2022-10-21 | Atg Innovations LLC | $200.7K | "THE SUBCONTRACTOR SHALL PROVIDE KNOWLEDGEABLE RESOURCES (€œPERSONNEL€Ͽ½) TO AUGMENT CERNER€„¢S EXISTING INTERFACE ARCHITECTS TO COMPLETE ALL NECESSARY INTERFACE DESIGN FOR INTEGRATIONS TO SATISFY… |
| 2023-01-13 | Favor Techconsulting, LLC | $193.5K | SUBCONTRACTOR SHALL PROVIDE CERTIFIED SCRUM MASTER |
19 actions since 2022-10-22. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-10 | P00019 | Supplemental agreement (work within scope) | $15.38M | VISN 15 B-SIDE LOCALIZATIONS (VA-26-00072563) |
| 2026-08-07 | P00018 | Supplemental agreement (work within scope) | $346.9K | ELIGIBILITY OPTIMIZATION PROJECT - OPTIONAL TASK 5.1 |
| 2026-05-27 | P00017 | Supplemental agreement (work within scope) | $11.39M | EXERCISE OPTION PERIOD 4 OPTIONAL TASK 3 - VA-SIDE (B-SIDE) LOCALIZATIONS FOR VISN 20 INTERFACES |
| 2026-05-15 | P00016 | Supplemental agreement (work within scope) | $22.24M | ADD WITHIN SCOPE WORK AND EXERCISE OPTION PERIOD 4 OPTIONAL TASK 3 - VA-SIDE (B-SIDE) LOCALIZATIONS FOR VISN 23 INTERFACES |
| 2026-04-10 | P00015 | Option exercised | $26.59M | EXERCISE OPTION YEAR 4 AND OP4 OPTIONAL TASKS & VA SIDE INTERFACE SUSTAINMENT (POP: 5/17/2026 - 5/16/2027) |
| 2026-03-16 | P00014 | Administrative change | $0 | DESCOPING BED MANAGEMENT SYSTEM (BMS) AT ANCHORAGE AND CLEVELAND |
| 2025-11-13 | P00013 | Option exercised | $0 | EXERCISE OPTIONAL TASKS 8.3 AND PART B OF 8.4 |
| 2025-09-23 | P00012 | Supplemental agreement (work within scope) | $5.27M | EXERCISE OPTIONAL TASK 9 (SUSTAINMENT SUPPORT) AND NET NEW INTERFACES FOR ALASKA & CLEVELAND DEPLOYMENT |
| 2025-05-30 | P00011 | Option exercised | $25.69M | EXERCISE OPTION PERIOD 3 (POP EXTENDED TO 5/16/2026) AND FOUR OPTIONAL TASKS |
| 2024-11-07 | P00010 | Supplemental agreement (work within scope) | $0 | ADDITIONAL INTERFACE WORK FOR SPOKANE CBOC LOCALIZATION |
| 2024-10-24 | P00009 | Administrative change | $0 | ADDITIONAL INTERFACE WORK |
| 2024-09-16 | P00008 | Supplemental agreement (work within scope) | $0 | ADDITIONAL INTERFACE WORK |
| 2024-05-20 | P00007 | Supplemental agreement (work within scope) | $27.46M | ADDITIONAL INTERFACE WORK |
| 2024-01-12 | P00006 | Supplemental agreement (work within scope) | $0 | ADDITIONAL INTERFACE WORK |
| 2023-08-11 | P00005 | Supplemental agreement (work within scope) | $1.14M | ADDITIONAL INTERFACE WORK |
| 2023-05-18 | P00004 | Option exercised | $32.04M | EXERCISE OPTIONAL TASKS AND OPTION PERIOD 1 |
| 2023-03-14 | P00003 | Option exercised | $1.77M | EXERCISE OPTIONAL TASKS FOR ADDITIONAL INTERFACES AND SUSTAINMENT SUPPORT |
| 2023-02-28 | P00002 | Option exercised | $56.11M | EXERCISE OPTIONAL TASKS FOR ADDITIONAL INTERFACES AND SUSTAINMENT SUPPORT |
| 2022-10-22 | P00001 | Administrative change | $0 | ADD GFE |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-20). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗