36C24725F0025↗

Johnson Controls, Inc received this contract from 247-Network Contract Office 7 (36C247), Department of Veterans Affairs: $1.82M obligated so far for maint/repair/rebuild of equipment- refrigeration, air conditioning, and air circulating equipment. Its period of performance ended 2026-09-30; options could extend it to 2029-09-30.

Key facts · data as of Oct 23, 2026

Recipient
Johnson Controls, Inc
Awarding agency
Department of Veterans Affairs
Contracting office
247-Network Contract Office 7 (36C247) (36C247)
Obligated to date
$1.82M
Potential value
$4.25M
Ends
2026-09-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award 36C24725F0025, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_36C24725F0025_3600_GS07F190CA_4732

PREVENTATIVE MAINTENANCE AND UPGRADES TO METASYS BUILDING MANAGEMENT SOFTWARE AND HARDWARE

Delivery Order · Department of Veterans Affairs · to Johnson Controls, Inc (UEI CE8MGXAS9KJ6) · data as of 2026-10-23

Obligated to date$1.82M4 actions
Current value$4.25Mwith options exercised
Period2024-10-01 → 2026-09-30up to 2029-09-30 with options

Up for re-bid: ends 2026-09-30. Recompete brief → · J041-- CHILLER TUBE CLEANING ↗

What it is

Product or service
Maint/Repair/Rebuild of Equipment- Refrigeration, Air Conditioning, and Air Circulating Equipment (PSC J041)
Industry
Other Communications Equipment Manufacturing (NAICS 334290)
Contracting office
247-Network Contract Office 7 (36C247) (36C247)
Competition
Full and open competition · 1 offer received
Pricing
Firm fixed price
How it was bought
GSA Schedule · under GS07F190CA
Where the work is
Richmond, GA · district GA-12

Obligations by fiscal year

FY2025$614.5K
FY2026$1.20M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

4 actions since 2024-10-01. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-07P00003Administrative change$635.3KPREVENTATIVE MAINTENANCE AND UPGRADES TO METASYS BUILDING MANAGEMENT SOFTWARE AND HARDWARE
2025-10-01P00002Option exercised$567.9KPREVENTATIVE MAINTENANCE AND UPGRADES TO METASYS BUILDING MANAGEMENT SOFTWARE AND HARDWARE
2025-04-11P00001Administrative change$0PREVENTATIVE MAINTENANCE AND UPGRADES TO METASYS BUILDING MANAGEMENT SOFTWARE AND HARDWARE
2024-10-010$614.5KPREVENTATIVE MAINTENANCE AND UPGRADES TO METASYS BUILDING MANAGEMENT SOFTWARE AND HARDWARE