DAF EVSE INSTALLATION HURLBURT AFB
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
10 actions since 2023-09-29. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-10-23 | PS0009 | Supplemental agreement (work within scope) | -$2.23M | DEOBLIGATION OF REMAINING UNUSED FUNDS |
| 2025-06-26 | PS0008 | Supplemental agreement (work within scope) | $0 | MODIFICATION EXTENDING THE SUBSTANCIAL COMPLETION DATE TO JULY 30, 2025 |
| 2025-04-29 | PS0007 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE |
| 2025-03-26 | PO0006 | Terminated for convenience | $0 | NOTICE OF TERMINATION FOR CONVENIENCE |
| 2025-03-06 | PS0005 | Supplemental agreement (work within scope) | $0 | MOD PS0005 EXTENDING THE SUBSTANCIAL COMPLETION DATE TO 23 MAY 2025. |
| 2024-11-06 | PS0004 | Supplemental agreement (work within scope) | $14.9K | THE PURPOSE OF THIS MODIFICATION IS DAF EVSE INSTALLATION INFRASTRUCTURE PROJECT- SITE 13 - CHARGER RELOCATION |
| 2024-08-14 | PS0003 | Supplemental agreement (work within scope) | $0 | MOD PS0003 TO ISSUE THE NTP FOR CONSTRUCTION. |
| 2024-08-06 | PS0002 | Supplemental agreement (work within scope) | $354.1K | MODIFICATION TO PROVIDE ADDITIONAL SERVICES FOR THE DAF EVSE INSTALLATION INFASTRUCTURE PROJECT. |
| 2024-04-10 | PS0001 | Supplemental agreement (work within scope) | -$423.2K | PS0001 DESCOPE MODIFICATION |
| 2023-09-29 | 0 | $4.88M | DAF EVSE INSTALLATION HURLBURT AFB |