CONTRACT#47PB0024C0021 IS AWARDED TO ALEXANDRA CONSTRUCTION FOR THE SCOPE OF WORK RELATED TO THE RENOVATION OF THE PASSPORT OFFICE AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA. THE COMPLETION DATE IS 07/18/25. AWARD IN THE AMOUNT OF 9,418,560.00.
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
9 subawards totaling $8.05M (81.9% of what was obligated), as Alexandra Construction Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| B L Mechanical Inc | $2.93M | 2 | MA | 2024-06-19 | 2024-06-19 |
| Murphy Electric & Industrial Control, LLC | $2.83M | 2 | MA | 2024-04-29 | 2024-04-29 |
| Clifford and Galvin Contracting, LLC | $1.69M | 2 | MA | 2024-05-13 | 2024-05-13 |
| Allegheny Contract Flooring Inc | $352.5K | 2 | MA | 2024-04-23 | 2024-04-23 |
| Delta Mechanical Contractors LLC | $244.9K | 1 | RI | 2024-06-07 | 2024-06-07 |
| Date | To | Amount | For |
|---|---|---|---|
| 2024-06-19 | B L Mechanical Inc | $1.47M | PLUMBING & HVAC SCOPES OF WORK. |
| 2024-04-29 | Murphy Electric & Industrial Control, LLC | $1.47M | ELECTRIC AND TEL/DATA SCOPES OF WORK |
| 2024-06-19 | B L Mechanical Inc | $1.46M | PLUMBING AND HVAC SCOPE OF WORK. |
| 2024-04-29 | Murphy Electric & Industrial Control, LLC | $1.36M | ELECTRIC AND TELEPHONE/DATA SCOPE OF WORK |
| 2024-05-13 | Clifford and Galvin Contracting, LLC | $952.2K | TEMPORARY WALLS, FRAMING AND SEALANT SCOPES OF WORK. |
| 2024-05-13 | Clifford and Galvin Contracting, LLC | $739.2K | FURNISH & INSTALL METAL FRAMING, ACOUSTICAL SEALANT, SOUND INSULATION, GYPSUM WALL BOARD, SECURITY MESH AT PARTITIONS, BALLISTIC RESISTANT BOARD, WOOD BLOCKING AND INSTALL HOLLOW METAL DOOR FRAMES, WOOD DOORS AND DOOR… |
| 2024-06-07 | Delta Mechanical Contractors LLC | $244.9K | THE FIRE PROTECTION SCOPE OF WORK |
| 2024-04-23 | Allegheny Contract Flooring Inc | $197.5K | FLOORING SCOPE OF WORK. |
| 2024-04-23 | Allegheny Contract Flooring Inc | $155.0K | FURNISH AND INSTALL CARPET, LVT, SDT TILE AND RUBBER COVE BASE. |
17 actions since 2024-04-04. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-11-20 | PS0016 | Supplemental agreement (work within scope) | -$4.7K | PS0016 FOR THE DOS 2ND FLOOR PASSPORT RENOVATIONS IN BOSTON, MA IS MODIFIED AS FOLLOWS: THE TOTAL CONTRACT PRICE IS REDUCED BY $4,746.41 TO TOTAL $9,828,438.00 FOR THE CREDIT ASSOCIATED WITH THE TEMPORARY OFFICE SPACE AND VISUAL DISPLAY UNITS. |
| 2025-09-17 | PS0014 | Supplemental agreement (work within scope) | $0 | PS00014 EXTENDS THE ULTIMATE COMPLETION DATE AT NO-COST TO 10/10/2025 TO ALLOW TIME FOR THE PROJECT AS BUILDS TO BE COMPLETED. THE PROJECT TAKES PLACE AT THE O'NEILL FB IN BOSTON, MA. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2025-09-17 | PA0015 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE FUNDING FIXED ASSET INFORMATION FROM CIPIMP TO IMPROVMNT IN THE ACCOUNTING LINES. THIS IS AN ADMINISTRATIVE CHANGE TO THE ACCOUNTING ONLY, ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2025-09-09 | PS0013 | Supplemental agreement (work within scope) | $4.6K | PS0013 ADDS $4,556.00 TO THE CONTRACT FOR FLOOR TITLE REPLACEMENTS FOR THE DEPARTMENT OF STATE PASSPORT PROJECT. THE PROJECT TAKES PLACE AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2025-08-06 | PS0012 | Supplemental agreement (work within scope) | $30.4K | PS0012 ADDS $30,354.00 TO INCORPORATE RFP 12 AND RFP 13 INTO THE CONTRACT. THE CONTRACT TAKES PLACE AT THE DOS OFFICE SPACE AT THE O'NEILL FEDERAL BUILDING, IN BOSTON, MA. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2025-05-20 | PS0011 | Supplemental agreement (work within scope) | $30.7K | PS0011 INCREASES THE CONTRACT VALUE BY $30,653.80 FOR WORK ASSOCIATED WITH RFP 11 AT THE DOS PROJECT AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2025-05-07 | PS0010 | Supplemental agreement (work within scope) | $14.0K | PS0010 ADDS $14,015.00 ON THE CONTRACT FOR THE SCOPE OF WORK ASSOCIATED WITH THE RFP. THE WORK WILL BE COMPLETED AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2025-05-05 | PS0009 | Supplemental agreement (work within scope) | $0 | PS0009 INCORPORATES THE DRONE CLAUSE INTO THE DOS CONTRACT AT THE O'NEILL FEDERAL BUILDING IN BOSTON,MA. CONTRACT PRICING AND COMPLETION DATE REMAINS UNCHANGED. |
| 2025-02-25 | PS0008 | Supplemental agreement (work within scope) | $822 | MODIFICATION PS0008 MODIFIES THE ONEILL DOS PASSPORT 2ND FLOOR RENOVATION IN BOSTON, MA TO INSATLL APPROX. 40 HUBBLE DATA PORT RAISED FACE PLATES IN CUBICLE FURNITURE. |
| 2025-01-03 | PS0007 | Supplemental agreement (work within scope) | $5.1K | PS0007, FOR THE DOS 2ND FLOOR PASSPORT RENOVATIONS IN BOSTON, MA INCORPORATE RFP #7 INTO THE CONTRACT. THE CONTRACT CONTRACT VALUE INCREASED BY $5,121 TO TOTAL 9,752,783.61. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-11-18 | PS0006 | Supplemental agreement (work within scope) | $34.3K | DOS 2ND FLOOR PASSPORT RENOVATIONS AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA IS MODIFIED TO INCLUDE A CHANGE ORDER FOR RFP #6. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-11-12 | PS0005 | Supplemental agreement (work within scope) | $8.1K | DOS 2ND FLOOR PASSPORT RENOVATIONS AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA IS MODIFIED TO INCLUDE A CHANGE ORDER FOR RFP #5. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-10-18 | PS0004 | Supplemental agreement (work within scope) | $43.3K | DOS 2ND FLOOR PASSPORT RENOVATIONS AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA IS MODIFIED TO INCLUDE A CHANGE ORDER FOR RFP #4. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-09-27 | PS0003 | Supplemental agreement (work within scope) | $48.2K | OS 2ND FLOOR PASSPORT RENOVATIONS AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA IS MODIFIED TO INCLUDE A CHANGE ORDER FOR RFP #3. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-08-16 | PS0002 | Supplemental agreement (work within scope) | $68.1K | DOS 2ND FLOOR PASSPORT RENOVATIONS AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA IS MODIFIED TO INCLUDE A CHANGE ORDER FOR THE WALL REMOVAL AND FLOOR LEVELING. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-08-09 | PS0001 | Supplemental agreement (work within scope) | $127.1K | DOS 2ND FLOOR PASSPORT RENOVATIONS AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA IS MODIFIED TO INCLUDE A CHANGE ORDER FOR THE WALL DOOR. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-04-04 | 0 | $9.42M | CONTRACT#47PB0024C0021 IS AWARDED TO ALEXANDRA CONSTRUCTION FOR THE SCOPE OF WORK RELATED TO THE RENOVATION OF THE PASSPORT OFFICE AT THE O'NEILL FEDERAL BUILDING IN BOSTON, MA. THE COMPLETION DATE IS 07/18/25. AWARD IN THE AMOUNT OF 9,418,560.00. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗