47PB5326C0001↗
Clark Construction Group LLC received this contract from PBS Project Delivery Capital Construction - Branch Central, Public Buildings Service: $32.30M obligated so far for salvage- demolition of buildings. Its period of performance ended 2026-03-23.
Key facts · data as of Oct 23, 2026
- Recipient
- Clark Construction Group LLC
- Awarding agency
- Public Buildings Service (General Services Administration)
- Contracting office
- PBS Project Delivery Capital Construction - Branch Central (47PB53)
- Obligated to date
- $32.30M
- Potential value
- $32.30M
- Ends
- 2026-03-23
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 47PB5326C0001, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_47PB5326C0001_4740_-NONE-_-NONE-
Clark Construction Group LLC: all federal awards · General Services Administration: spending · PBS Project Delivery Capital Construction - Branch Central: what it buys
EMERGENCY DESIGN-BUILD DEMOLITION OF 17 STRUCTURALLY AND SECURITY-COMPROMISED BUILDINGS AT THE ST. ELIZABETHS WEST CAMPUS DHS HEADQUARTERS TO MITIGATE LIFE-SAFETY AND NATIONAL SECURITY RISKS.
What it is
- Product or service
- Salvage- Demolition of Buildings (PSC P400)
- Industry
- Site Preparation Contractors (NAICS 238910)
- Funded by
- Department of Homeland Security
- Contracting office
- PBS Project Delivery Capital Construction - Branch Central (47PB53)
- Competition
- Not competed · 1 offer received
- Pricing
- Firm fixed price
- How it was bought
- Standalone contract
- Solicitation
- EQPXCB-26-0001
- Where the work is
- District of Columbia, DC · district DC-98
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
2 actions since 2026-01-02. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-28 | PA0002 | Funding only | -$1.36M | THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE REMAINING FUNDS FOR CONTRACT CLOSEOUT. 47PB5326C0001, MOD PA0002 HEREBY DECREASES THE TOTAL OBLIGATED AMOUNT FROM $33,655,499.00 BY $1,358,575.00 TO $32,296,924.00. THE POP REMAINS THE SAME. |
| 2026-01-02 | 0 | $33.66M | EMERGENCY DESIGN-BUILD DEMOLITION OF 17 STRUCTURALLY AND SECURITY-COMPROMISED BUILDINGS AT THE ST. ELIZABETHS WEST CAMPUS DHS HEADQUARTERS TO MITIGATE LIFE-SAFETY AND NATIONAL SECURITY RISKS. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗