47PC0221F0058↗

S. J. Thomas Co., Inc. received this contract from PBS R2 Repair and Alterations Branch, Public Buildings Service: $64.2K obligated so far for repair or alteration of office buildings. Its period of performance ended 2024-10-31.

Key facts · data as of Oct 25, 2026

Recipient
S. J. Thomas Co., Inc.
Awarding agency
Public Buildings Service (General Services Administration)
Contracting office
PBS R2 Repair and Alterations Branch (47PC02)
Obligated to date
$64.2K
Potential value
$1.92M
Ends
2024-10-31

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award 47PC0221F0058, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_47PC0221F0058_4740_47PC0220D0003_4740

THE AWARD IS TO REPLACE THE TWO EXISTING ROOF-MOUNTED AIR-COOLED CHILLERS LOCATED ON THE ROOF OF THE JAMES T. FOLEY BUILDING LOCATED IN ALBANY, NY FOR THE AMOUNT OF $1,713,267.48. THE PERFORMANCE IS 150 DAYS FROM THE NOTICE TO PROCEED ISSUANCE.

Delivery Order · Public Buildings Service · to S. J. Thomas Co., Inc. (UEI FUL9FAAW2QA7) · data as of 2026-10-25

Obligated to date$64.2K5 actions
Current value$1.92Mwith options exercised
Period2021-06-07 → 2024-10-31up to 2025-06-20 with options

What it is

Product or service
Repair or Alteration of Office Buildings (PSC Z2AA)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
PBS R2 Repair and Alterations Branch (47PC02)
Competition
Full and open after exclusion of sources · 4 offers received
Set-aside
Small business
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 47PC0220D0003
Solicitation
47PC0221R0027
Where the work is
Albany, NY · district NY-20

Obligations by fiscal year

FY2023$11.4K
FY2024$21.4K
FY2025$31.4K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

5 actions since 2022-10-13. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2024-10-09PS0009Additional work (new agreement)$31.4KTHIS MOD IS TO INCORPORATE CLIN 0007 IN RESPONSE TO THE CONTRACTOR'S REQUEST FOR EQUITABLE ADJUSTMENT IN THE AMOUNT OF $31,438.72, AND EXTENDS THE SUBSTANTIAL COMPLETION DATE TO 10/31/24 FOR THE CHILLER REPLACEMENT PROJECT AT FOLEY BUILDING IN NY.
2024-08-26PS0007Additional work (new agreement)$21.4KTHIS MOD IS TO INCORPORATE CLIN 0006 IN RESPONSE TO THE CONTRACTOR'S REQUEST FOR EQUITABLE ADJUSTMENT IN THE AMOUNT OF $21,389.93. THIS INCREASES THE AWARD TOTAL FROM $1,862,250.67 TO $1,883,640.60, EXTENDS THE COMPLETION DATE FROM 4/30/24 TO 8/31/24
2023-05-25PS0006Additional work (new agreement)$5.5KTHIS MOD IS TO INCORPORATE CLIN 0005 FOR THE ATTACHED SOW IN THE AMOUNT OF $5,499.60. THIS MOD CHANGES THE SUBSTANTIAL COMPLETION DATE TO 4/30/24 AND THE COMPLETION DATE TO 6/20/25. FOLEY CHILLER REPLACEMENT- CONSTRUCTION
2023-02-21PS0005Additional work (new agreement)$5.9KTHE PURPOSE OF THIS CONTRACT MODIFICATION IS TO INCORPORATE THE SCOPE OF WORK DATED 2/07/2023. THE MODIFICATION INCREASES THE AWARD TOTAL FROM $1,850,866.07 TO $1,856,751.07. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
2022-10-13PS0004Additional work (new agreement)$0THE PURPOSE OF THIS NO COST TIME EXTENSION IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM 10/11/22 TO 5/31/24. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.