47PC0223F0047↗
Synthesis Inc received this contract from PBS R2 Repair and Alterations Branch, Public Buildings Service: $1.66M obligated so far for repair or alteration of office buildings. Its period of performance ended 2025-10-08.
Key facts · data as of Nov 25, 2026
- Recipient
- Synthesis Inc
- Awarding agency
- Public Buildings Service (General Services Administration)
- Contracting office
- PBS R2 Repair and Alterations Branch (47PC02)
- Obligated to date
- $1.66M
- Potential value
- $1.66M
- Ends
- 2025-10-08
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 25, 2026.
Cite this page: SpendQuery, Award 47PC0223F0047, data as of Nov 25, 2026, https://spendquery.com/award?id=CONT_AWD_47PC0223F0047_4740_47PC0220D0010_4740
Synthesis Inc: all federal awards · General Services Administration: spending · PBS R2 Repair and Alterations Branch: what it buys
TO PROVIDE CONSTRUCTION SERVICES FOR THE ABATEMENT OF ASBESTOS AND REPLACEMENT OF DOMESTIC WATER PIPING IN THE EMANUEL CELLER FEDERAL BUILDING LOCATED AT 225 CADMAN PLAZA EAST. BROOKLYN, NY 11201.
What it is
- Product or service
- Repair or Alteration of Office Buildings (PSC Z2AA)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- PBS R2 Repair and Alterations Branch (47PC02)
- Competition
- Full and open after exclusion of sources · 5 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 47PC0220D0010
- Solicitation
- 47PC0223R0026
- Where the work is
- Kings, NY · district NY-07
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
11 actions since 2023-05-26. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-07-31 | PS0010 | Supplemental agreement (work within scope) | $89.5K | THIS MODIFICATION PS0010 IS BEING ISSUED TO PROVIDE ADDITIONAL INSTALLATION AND COMMISSIONING SERVICES FOR THE ITEMS AS DESCRIBED IN RPF 12 SOW DATED 6/18/2025. |
| 2025-05-16 | PS0009 | Supplemental agreement (work within scope) | $161.1K | THIS MODIFICATION PS0009 IS BEING ISSUED TO PROVIDE SELECTIVE DEMOLITION SERVICES. |
| 2025-04-07 | PS0008 | Supplemental agreement (work within scope) | $18.9K | THIS MODIFICATION IS BEING EXECUTED FOR 846 SF OF ADDITIONAL FIREPROOFING TO THE BEAMS NOT SHOWN IN THE ORIGINAL CONTRACT DOCUMENTS AS DEFINED IN RFP 10 DATED 3/24/2025. |
| 2024-12-20 | PS0007 | Supplemental agreement (work within scope) | $115.2K | ADDITIONAL ABATEMENT AND FIRE PROOFING AT THE CELLER U.S. COURTHOUSE IN BROOKLYN |
| 2024-10-29 | PS0006 | Supplemental agreement (work within scope) | $21.7K | THIS MODIFICATION PS0006 IS BEING ISSUED FOR ADDITIONAL CSO COVERAGE DURING ASBESTOS ABATEMENT AS DEFINED IN RFP 8 DATED 10/10/2024. |
| 2024-08-28 | PS0005 | Supplemental agreement (work within scope) | $0 | THIS MODIFICATION IS BEING ISSUED TO EXTEND THE COMPLETION DATE DUE TO DELAYS IN PERMITTING AND A DELAYED CONSTRUCTION START DATE, AT NO ADDITIONAL COST TO THE GOVERNMENT. |
| 2024-06-10 | PS0004 | Supplemental agreement (work within scope) | $60.2K | PS0004 IS FOR THE INSTALLATION OF THE MECHANICAL ACCESS DOOR AND CSO COVERAGE DURING ASBESTOS ABATEMENT. |
| 2024-02-12 | PS0003 | Supplemental agreement (work within scope) | $0 | THIS MODIFICATION IS BEING ISSUED TO EXTEND THE COMPLETION DATE DUE TO PROJECT DELAYS AND CHANGES IN THE SOW AT NO ADDITIONAL COST TO THE GOVERNMENT. |
| 2024-01-02 | PS0002 | Supplemental agreement (work within scope) | $255.0K | THIS MODIFICATION PS0002 IS BEING ISSUED FOR ADDITIONAL ABATEMENT AND FIREPROOFING SERVICES IN ADDITIONAL BASEMENT AREAS AND CORRESPONDING FIREPROOFING REPLACEMENT PER REVISED SOW DATED 12/05/2023. |
| 2023-11-16 | PS0001 | Supplemental agreement (work within scope) | $123.1K | THIS MOD IS BEING ISSUED FOR FIREPROOFING REPLACEMENT SERVICES, LIGHTING AND CEILING REPLACEMENT SERVICES PER SOW DATED 7/27/2023, AND DESCOPING OF BASEMENT FLOOR TILE ABATEMENT SERVICES PER SOW DATED 8/16/2023. |
| 2023-05-26 | 0 | $813.0K | TO PROVIDE CONSTRUCTION SERVICES FOR THE ABATEMENT OF ASBESTOS AND REPLACEMENT OF DOMESTIC WATER PIPING IN THE EMANUEL CELLER FEDERAL BUILDING LOCATED AT 225 CADMAN PLAZA EAST. BROOKLYN, NY 11201. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗