47PC0325F0009↗
Benchmark Construction Services Inc received this contract from PBS R2 Capital Construction Branch, Public Buildings Service: $7.75M obligated so far for repair or alteration of office buildings. Its period of performance ended 2026-09-02; options could extend it to 2026-11-05.
Key facts · data as of Oct 25, 2026
- Recipient
- Benchmark Construction Services Inc
- Awarding agency
- Public Buildings Service (General Services Administration)
- Contracting office
- PBS R2 Capital Construction Branch (47PC03)
- Obligated to date
- $7.75M
- Potential value
- $7.75M
- Ends
- 2026-09-02
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award 47PC0325F0009, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_47PC0325F0009_4740_47PC0220D0005_4740
Benchmark Construction Services Inc: all federal awards · General Services Administration: spending · PBS R2 Capital Construction Branch: what it buys · The follow-on: recompete brief
GENERAL CONSTRUCTION SERVICES FOR SECURITY BARRIER REPLACEMENT AT 225 CADMAN PLAZA, BROOKLYN NY
Up for re-bid: ends 2026-09-02. Recompete brief →
What it is
- Product or service
- Repair or Alteration of Office Buildings (PSC Z2AA)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Funded by
- Department of Justice
- Contracting office
- PBS R2 Capital Construction Branch (47PC03)
- Competition
- Full and open after exclusion of sources · 3 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under 47PC0220D0005
- Solicitation
- 47PC0324R0014
- Where the work is
- Nassau, NY · district NY-03
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
8 actions since 2025-05-02. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-21 | PS0007 | Change order | $4.4K | RFP 14 GUARD BOOTH CORES AND PADLOCKS |
| 2026-08-18 | PS0006 | Change order | $10.9K | PS0006 - RFP 8V2 & RFP 9 |
| 2026-05-08 | PS0005 | Change order | $3.9K | INCORPORATE CLIN 07: RFP 05 PRICED AT $3,878.62 & REMOVING THE FUNDING OFF CLIN 02: OPTION 1 - GUARD BOOTHS FROM THE CONTRACT DUE RWA FUNDING CONSTRAINTS & THE SUBSTANTIAL CONTRACT COMPLETION DATE IS EXTENDED BY 6 CALENDAR DAYS 09/02/2026. |
| 2026-04-28 | PS0004 | Change order | $21.4K | PS0004 - RFP 4- HYSECURITY INSPECTIONS |
| 2026-03-04 | PS0003 | Supplemental agreement (work within scope) | $10.6K | MODIFICATION NO. PS0003 IS ISSUED FOR ADDITIONAL CONSTRUCTION SERVICES FOR THE USMS SECURITY BARRIERS PROJECT AT 225 CADMAN PLAZA, BROOKLYN, NY |
| 2025-09-17 | PS0002 | Supplemental agreement (work within scope) | $567.5K | MOD FOR ADDITIONAL GC SERVICES FOR THE BARRIER PROJECT IN BROOKLYN NY |
| 2025-07-24 | PS0001 | Supplemental agreement (work within scope) | $551.4K | ADDITIONAL GC SERVICES FOR THE SECURITY BARRIERS PROJECT IN BROOKLYN, NY. |
| 2025-05-02 | 0 | $6.58M | GENERAL CONSTRUCTION SERVICES FOR SECURITY BARRIER REPLACEMENT AT 225 CADMAN PLAZA, BROOKLYN NY |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗