47PC5526F0396↗

Action Facilities Management Inc received this contract from PBS Project Delivery East - Branch E, Public Buildings Service: $219.0K obligated so far for maintenance of office buildings. Its period of performance ended 2026-09-30.

Key facts · data as of Oct 23, 2026

Recipient
Action Facilities Management Inc
Awarding agency
Public Buildings Service (General Services Administration)
Contracting office
PBS Project Delivery East - Branch E (47PC55)
Obligated to date
$219.0K
Potential value
$219.0K
Ends
2026-09-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award 47PC5526F0396, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_47PC5526F0396_4740_47PC0625A0002_4740

NY0282ZZ - HOWARD STREET GARAGE DRY SPRINKLER SYSTEM 1ST FLOOR INSTALLATION

Bpa Call · Public Buildings Service · to Action Facilities Management Inc (UEI HB9HZZ9R8AX4) · data as of 2026-10-23

Obligated to date$219.0K3 actions
Current value$219.0Kwith options exercised
Period2026-06-04 → 2026-09-30current end date

What it is

Product or service
Maintenance of Office Buildings (PSC Z1AA)
Industry
Facilities Support Services (NAICS 561210)
Contracting office
PBS Project Delivery East - Branch E (47PC55)
Competition
Full and open competition
Pricing
Firm fixed price
How it was bought
Blanket purchase agreement (BPA) · under 47PC0625A0002
Solicitation
EQPMAG-26-0329
Where the work is
New York, NY · district NY-10

Obligations by fiscal year

FY2026$219.0K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

3 actions since 2026-06-04. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-08-12PS0002Supplemental agreement (work within scope)$2.7K47PC5526F0396, MOD PS0002 - NY0282ZZ - HOWARD STREET GARAGE DRY SPRINKLER SYSTEM 1ST FLOOR INSTALLATION AND WORTH STREET CURB VALVE REPLACEMENT
2026-06-11PS0001Supplemental agreement (work within scope)$67.7K47PC5526F0396, MOD PS0001 - NY0282ZZ - HOWARD STREET GARAGE DRY SPRINKLER SYSTEM 1ST FLOOR INSTALLATION AND WORTH STREET CURB VALVE REPLACEMENT
2026-06-040$148.6KNY0282ZZ - HOWARD STREET GARAGE DRY SPRINKLER SYSTEM 1ST FLOOR INSTALLATION

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗