47PD0523F0051↗

Jones Lang Lasalle Americas, Inc. received this contract from PBS R3 Philadelphia Field Office, Public Buildings Service: $174.0K obligated so far for maintenance of office buildings. Its period of performance ended 2024-04-19.

Key facts · data as of Oct 25, 2026

Recipient
Jones Lang Lasalle Americas, Inc.
Awarding agency
Public Buildings Service (General Services Administration)
Contracting office
PBS R3 Philadelphia Field Office (47PD05)
Obligated to date
$174.0K
Potential value
$174.0K
Ends
2024-04-19

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award 47PD0523F0051, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_47PD0523F0051_4740_47PD0321A0002_4740

BA54 RPA 79069 PA0278BG INSTALLATION OF CHILLED WATER BOOSTER PUMP AT THE BYRNE/GREEN COMPLEX, PHILADELPHIA, PA 19106

Bpa Call · Public Buildings Service · to Jones Lang Lasalle Americas, Inc. (UEI RJ7MF1XTJN88) · data as of 2026-10-25

Obligated to date$174.0K4 actions
Current value$174.0Kwith options exercised
Period2023-03-08 → 2024-04-19current end date

What it is

Product or service
Maintenance of Office Buildings (PSC Z1AA)
Industry
Facilities Support Services (NAICS 561210)
Contracting office
PBS R3 Philadelphia Field Office (47PD05)
Competition
Full and open competition
Pricing
Firm fixed price
How it was bought
Blanket purchase agreement (BPA) · under 47PD0321A0002
Where the work is
Philadelphia, PA · district PA-02

Obligations by fiscal year

FY2023$174.0K
FY2024$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

4 actions since 2023-03-08. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2024-03-21PS0003Supplemental agreement (work within scope)$0PA0278BG CHILLED WATER BOOSTER PUMP. MODIFICATION TO EXTEND THE COMPLETION DATE TO APRIL 19, 2024 DUE TO PART THAT IS ON ORDER FOR THIS PROJECT.
2023-10-18PA0002Administrative change$0ADMINISTRATIVE MODIFICATION TO CHANGE CONTRACTING OFFICER FROM KAREN SIMS TO JULIETTE OLIVER.
2023-10-16PS0001Supplemental agreement (work within scope)$0PA0278BG BYRNE CHILLED WATER BOOSTER MODIFICATION TO EXTEND THE COMPLETION DATE FROM 8/25/2023 TO 2/28/2023 DUE TO INSTALLATION SCHEDULE.
2023-03-080$174.0KBA54 RPA 79069 PA0278BG INSTALLATION OF CHILLED WATER BOOSTER PUMP AT THE BYRNE/GREEN COMPLEX, PHILADELPHIA, PA 19106

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗