47PD5326F0171↗
Dae Sung LLC received this contract from PBS Project Delivery West - Branch C, Public Buildings Service: $21.5K obligated so far for support- management: other. Its period of performance ended 2026-09-06; options could extend it to 2026-11-05.
Key facts · data as of Oct 26, 2026
- Recipient
- Dae Sung LLC
- Awarding agency
- Public Buildings Service (General Services Administration)
- Contracting office
- PBS Project Delivery West - Branch C (47PD53)
- Obligated to date
- $21.5K
- Potential value
- $21.5K
- Ends
- 2026-09-06
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.
Cite this page: SpendQuery, Award 47PD5326F0171, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_47PD5326F0171_4740_47PJ0023A0001_4740
Dae Sung LLC: all federal awards · General Services Administration: spending · PBS Project Delivery West - Branch C: what it buys
THIS PROJECT IS TO REPLACE A FAILED 8 INCH CHECK VALVE, CONVERT THE WET SYSTEM IN ROOM 003 TO THE DRY SYSTEM, & UPDATE THE ANTIQUATED JOCKEY PUMP CONTROLLER ON THE FIRE SUPPRESSION SYSTEM LOCATED AT 115 4TH AVENUE SE ABERDEEN, SD 57401.
What it is
- Product or service
- Support- Management: Other (PSC R799)
- Industry
- Facilities Support Services (NAICS 561210)
- Contracting office
- PBS Project Delivery West - Branch C (47PD53)
- Competition
- Full and open competition
- Pricing
- Firm fixed price
- How it was bought
- Blanket purchase agreement (BPA) · under 47PJ0023A0001
- Solicitation
- EQPMBA-26-0195
- Where the work is
- Brown, SD · district SD-00
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
2 actions since 2026-05-19. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-20 | PS0001 | Supplemental agreement (work within scope) | $0 | ISSUE NOTICE TO PROCEED AND EXTEND THE PERIOD OF PERFORMANCE 67 DAYS DUE TO MATERIAL LEAD TIME AT FEDERAL BUILDING, ABERDEEN 115 4TH AVENUE SE ABERDEEN, SD 57401. |
| 2026-05-19 | 0 | $21.5K | THIS PROJECT IS TO REPLACE A FAILED 8 INCH CHECK VALVE, CONVERT THE WET SYSTEM IN ROOM 003 TO THE DRY SYSTEM, & UPDATE THE ANTIQUATED JOCKEY PUMP CONTROLLER ON THE FIRE SUPPRESSION SYSTEM LOCATED AT 115 4TH AVENUE SE ABERDEEN, SD 57401. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗