47PD5326F0208↗

Dae Sung LLC received this contract from PBS Project Delivery West - Branch C, Public Buildings Service: $22.5K obligated so far for support- management: other. Its period of performance ended 2026-10-27; options could extend it to 2026-12-26.

Key facts · data as of Oct 26, 2026

Recipient
Dae Sung LLC
Awarding agency
Public Buildings Service (General Services Administration)
Contracting office
PBS Project Delivery West - Branch C (47PD53)
Obligated to date
$22.5K
Potential value
$22.5K
Ends
2026-10-27

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.

Cite this page: SpendQuery, Award 47PD5326F0208, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_47PD5326F0208_4740_47PJ0023A0001_4740

THIS PROJECT IS TO REMOVE 3 EXISTING STEEL INSULATED DOORS AND EXISTING DOOR FRAMES, TO INCLUDE THE THRESHOLDS AND REPLACE THEM WITH 3 NEW STEEL INSULATED DOORS, FRAMES AND THRESHOLDS LOCATED AT 200 4TH STREET SW, HURON, SD 57350.

Bpa Call · Public Buildings Service · to Dae Sung LLC (UEI X6E8D5J5BZF7) · data as of 2026-10-26

Obligated to date$22.5K2 actions
Current value$22.5Kwith options exercised
Period2026-07-14 → 2026-10-27up to 2026-12-26 with options

What it is

Product or service
Support- Management: Other (PSC R799)
Industry
Facilities Support Services (NAICS 561210)
Contracting office
PBS Project Delivery West - Branch C (47PD53)
Competition
Full and open competition
Pricing
Firm fixed price
How it was bought
Blanket purchase agreement (BPA) · under 47PJ0023A0001
Solicitation
EQPMBA-26-0174
Where the work is
Beadle, SD · district SD-00

Obligations by fiscal year

FY2026$22.5K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

2 actions since 2026-07-14. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-10PS0001Supplemental agreement (work within scope)$0THE PURPOSE OF THIS NO COST MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE 45 DAYS DUE TO MATERIAL DELAY LOCATED AT 200 4TH ST HURON, SOUTH DAKOTA 57350.
2026-07-140$22.5KTHIS PROJECT IS TO REMOVE 3 EXISTING STEEL INSULATED DOORS AND EXISTING DOOR FRAMES, TO INCLUDE THE THRESHOLDS AND REPLACE THEM WITH 3 NEW STEEL INSULATED DOORS, FRAMES AND THRESHOLDS LOCATED AT 200 4TH STREET SW, HURON, SD 57350.