47PE0223F0062↗

South Dade Air Conditioning & Refrigeration Inc received this contract from PBS R4 Amd Southern Branch, Public Buildings Service: $440.7K obligated so far for maint/repair/rebuild of equipment- refrigeration, air conditioning, and air circulating equipment. Its period of performance ended 2024-07-01.

Key facts · data as of Oct 26, 2026

Recipient
South Dade Air Conditioning & Refrigeration Inc
Awarding agency
Public Buildings Service (General Services Administration)
Contracting office
PBS R4 Amd Southern Branch (47PE02)
Obligated to date
$440.7K
Potential value
$440.7K
Ends
2024-07-01

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.

Cite this page: SpendQuery, Award 47PE0223F0062, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_47PE0223F0062_4740_47PE0520A0004_4740

REPLACE WCT AND INSTALL BAS LOCATED AT THE GEORGE W. ANDREWS FEDERAL BUILDING AND U.S. COURTHOUSE (AL0046ZZ) 701 AVENUE A. OPELIKA, AL 36801-4977.

Bpa Call · Public Buildings Service · to South Dade Air Conditioning & Refrigeration Inc (UEI ZJMTAL6MZLU4) · data as of 2026-10-26

Obligated to date$440.7K5 actions
Current value$440.7Kwith options exercised
Period2023-02-28 → 2024-07-01current end date

What it is

Product or service
Maint/Repair/Rebuild of Equipment- Refrigeration, Air Conditioning, and Air Circulating Equipment (PSC J041)
Industry
Facilities Support Services (NAICS 561210)
Contracting office
PBS R4 Amd Southern Branch (47PE02)
Competition
Full and open competition
Pricing
Firm fixed price
How it was bought
Blanket purchase agreement (BPA) · under 47PE0520A0004
Solicitation
47PE0520Q0008
Where the work is
Lee, AL · district AL-03

Obligations by fiscal year

FY2023$440.7K
FY2024$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

5 actions since 2023-02-23. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2024-03-14PS0004Supplemental agreement (work within scope)$0EXTEND CONTRACT COMPLETION DATE TO JULY 01, 2024 FOR THE REPLACEMENT OF WCT AND INSTALL BAS, OPELIKA, AL. 701 AVENUE A, OPELIKA, AL 36801-4977.
2023-12-06PS0003Supplemental agreement (work within scope)$0EXTEND THE CONTRACT COMPLETION DATE TO ALLOW CONTRACTOR TO SUFFICIENT TIME TO FINISH REPLACEMENT OF WCT AND INSTALL BAS PROJECT, 701 AVE, A, OPELIKA, AL 36801-4977.
2023-09-27PS0002Supplemental agreement (work within scope)$0POP EXTENSION OF 60 DAYS FOR THE REPLACEMENT OF WCT AND INSTALL BAS, LOCATED AT THE GEORGE W. ANDREWS (AL0046ZZ) FEDERAL BUILDING AND U.S. COURTHOUSE. 701 AVENUE A, OPELIKA, AL 36801-4977
2023-07-19AA0001Administrative change$0CHANGE THE OFFICER FROM WANDA GEORGE-JAMES TO VINCENT BUTLER FOR PROJECT TO REPLACE WCT AND INSTALL BAS, GEORGE W. ANDREWS FEDERAL BUILDING, 701 AVE A, OPELIKA, AL 36801-4977.
2023-02-230$440.7KREPLACE WCT AND INSTALL BAS LOCATED AT THE GEORGE W. ANDREWS FEDERAL BUILDING AND U.S. COURTHOUSE (AL0046ZZ) 701 AVENUE A. OPELIKA, AL 36801-4977.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗