Brasfield & Gorrie LLC received this contract from PBS R4 Amd Capital/Ae Branch, Public Buildings Service: $217.83M obligated so far for construction of office buildings. It runs to 2026-11-28, or to 2027-01-28 if every option is exercised.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 47PE0323C0004, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_47PE0323C0004_4740_-NONE-_-NONE-
Brasfield & Gorrie LLC: all federal awards · General Services Administration: spending · PBS R4 Amd Capital/Ae Branch: what it buys · The follow-on: recompete brief
DESIGN-BUILD CONSTRUCTION SERVICES FOR A NEW U. S. FEDERAL BUILDING LOCATED AT FORT LAUDERDALE, FL 33316-
Up for re-bid: ends 2026-11-28. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
18 subawards totaling $67.64M (31.1% of what was obligated), as Brasfield & Gorrie LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Tutor Perini Corp | $21.27M | 1 | FL | 2023-02-22 | 2023-02-22 |
| Hypower, LLC | $18.58M | 1 | FL | 2023-02-14 | 2023-02-14 |
| David Allen Company, Inc. | $9.48M | 1 | NC | 2023-03-01 | 2023-03-01 |
| Central Civil Construction Co | $3.36M | 1 | FL | 2023-03-27 | 2023-03-27 |
| Central Broward Construction, Inc | $3.36M | 1 | FL | 2024-05-21 | 2024-05-21 |
| Lotspeich Co of Florida, Inc | $2.75M | 1 | FL | 2024-10-29 | 2024-10-29 |
| West Tampa Glass Company | $2.27M | 1 | FL | 2023-02-23 | 2023-02-23 |
| Alabama Roof Pro LLC | $1.33M | 1 | AL | 2023-02-27 | 2023-02-27 |
| Summers Fire Sprinklers, Inc. | $1.19M | 1 | FL | 2023-02-17 | 2023-02-17 |
| Promex Contractors Inc | $1.15M | 1 | FL | 2024-03-11 | 2024-03-11 |
| Percopo Coatings | $848.7K | 1 | FL | 2023-02-24 | 2023-02-24 |
| Topbuild Corp. | $529.7K | 1 | FL | 2023-05-09 | 2023-05-09 |
| Above All Caulking & Waterproofing, Inc | $454.5K | 1 | FL | 2024-02-12 | 2024-02-12 |
| Apex Building Co LLC | $350.4K | 1 | TN | 2023-03-28 | 2023-03-28 |
| Florida Concrete Unlimited, Inc | $310.4K | 1 | FL | 2024-02-12 | 2024-02-12 |
| Irvine Access Floors, Inc. | $290.9K | 1 | MD | 2023-02-27 | 2023-02-27 |
| Hire Quest Payroll Services, LLC | $75.0K | 1 | SC | 2023-05-24 | 2023-05-24 |
| Lorad LLC | $33.5K | 1 | OH | 2023-03-13 | 2023-03-13 |
| Date | To | Amount | For |
|---|---|---|---|
| 2023-02-22 | Nagelbush Mechanical, Inc | $21.27M | PLUMBING & HVAC SYSTEM |
| 2023-02-14 | Hypower, LLC | $18.58M | ELECTRICAL AND FIRE ALARM |
| 2023-03-01 | David Allen Company, Inc. | $9.48M | STEEL FABRICATIONS & ERECTION |
| 2023-03-27 | Central Civil Construction Co | $3.36M | CIVIL SITEWORK, EARTHWORK AND UTILITIES |
| 2024-05-21 | Central Broward Construction, Inc | $3.36M | MASONRY |
| 2024-10-29 | Lotspeich Co of Florida, Inc | $2.75M | DOORS, FRAMES, & HARDWARE |
| 2023-02-23 | West Tampa Glass Company | $2.27M | EXTERIOR CURTAINWALL |
| 2023-02-27 | Alabama Roof Pro LLC | $1.33M | ROOFING & CORRUGATED METAL PANELS |
| 2023-02-17 | Summers Fire Sprinklers, Inc. | $1.19M | FIRE PROTECTION SYSTEM |
| 2024-03-11 | Promex Contractors Inc | $1.15M | REINFORCING STEEL & WIRE MESH INSTALLATION |
| 2023-02-24 | Percopo Coatings Company LLC | $848.7K | PAINTING AND COATING |
| 2023-05-09 | Builder Services Group, Inc. | $529.7K | SPRAY FIREPROOFING |
| 2024-02-12 | Above All Caulking & Waterproofing, Inc | $454.5K | WATERPROOFING |
| 2023-03-28 | Apex Building Co LLC | $350.4K | SPRAY FOAM INSULATION |
| 2024-02-12 | Florida Concrete Unlimited, Inc | $310.4K | CONCRETE PUMP, PLACE AND FINISH |
| 2023-02-27 | Irvine Access Floors, Inc. | $290.9K | RAISED ACCESS FLOORING |
| 2023-05-24 | Hire Quest, L.L.C | $75.0K | TEMPORARY LABOR |
| 2023-03-13 | Lorad LLC | $33.5K | FACILITY FALL PROTECTION |
25 actions since 2023-01-31. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-28 | PS0025 | Supplemental agreement (work within scope) | $5.24M | 47PE0323C0004, MOD PS0025 - FT LAUDERDALE NEW COURTHOUSE - MOD PS0025, PCOS 062, 069, 076, 077, 080 |
| 2026-07-07 | PS0024 | Supplemental agreement (work within scope) | $0 | 47PE0323C0004, MOD PS0024 - INCORPORATING DEI CLAUSE UNDER EO 14398 |
| 2026-06-01 | PS0023 | Supplemental agreement (work within scope) | $0 | 47PE0323C0004, MOD PS0023 - FT LAUDERDALE NEW COURTHOUSE - MOD PS0023, TO OBLIGATE BA54 FUNDS AND TO DEOBLIGATE BA80 FUNDS |
| 2026-04-21 | PS0022 | Supplemental agreement (work within scope) | $1.03M | 47PE0323C0004, MOD PS0022 - FT LAUDERDALE NEW COURTHOUSE - MOD PS0022, PCOS 061B_COURTS STRUCTURED CABLING, 067_USMS TELECOMMUNICATIONS & A/V STRUCTURED CABLING |
| 2026-03-04 | PS0021 | Supplemental agreement (work within scope) | $725.0K | THE PURPOSE OF THIS MODIFICATION FOR 47PE0323C0004, MOD PS0021 - FT LAUDERDALE NEW COURTHOUSE IS TO INCORPORATE MOD PS0021, PCO 061_US STRUCTURED CABLING INSTALLATION. |
| 2026-02-09 | PS0020 | Supplemental agreement (work within scope) | $331.6K | DESIGN BUILD SERVICES FOR NEW US FEDERAL COURTHOUSE LOCATED IN FORT LAUDERDALE FLORIDA. MODIFICATION TO PROVIDE FUNDING FOR SERVICES IN ACCORDANCE WITH PCOS 059, 071, 072 AND 073. |
| 2026-01-13 | PS0019 | Supplemental agreement (work within scope) | $0 | FT LAUDERDALE NEW COURTHOUSE - LEGAL LIMITS OF DISTURBANCE {LOD} MODIFICATION |
| 2025-12-19 | PS0018 | Supplemental agreement (work within scope) | $143.8K | MODIFICATION PS0018 IS FOR PURPOSE OF ADDING PCOS 55, 66, 68 AND 70 FOR DESIGN BUILD SERVICES FOR THE NEW FORT LAUDERDALE U.S. COURTHOUSE, FORT LAUDERDALE, FL. MODIFICATION TO ADD PCOS 55, 66, 68 AND 70. |
| 2025-11-03 | PS0017 | Supplemental agreement (work within scope) | $2.03M | DESIGN-BUILD NEW COURTHOUSE, FORT LAUDERDALE FL MODIFICATION TO ADD PCOS 32, 51, 52, 54, 56, 57, 58, 64, 65 |
| 2025-09-05 | PS0016 | Supplemental agreement (work within scope) | $1.15M | THE PURPOSE OF THIS MODIFICATION WILL BE TO ADD PCOS 43, 45, 49, 50. TOTAL PS0016 MOD 1$1,151,871. |
| 2025-07-10 | PS0015 | Supplemental agreement (work within scope) | $499.6K | MODIFICATION TO ADD CLINS 36, 37 & 38 TO INCORPORATE PCOS 30, 42 & 47 TO THE CONTRACT AS SUPPLEMENTAL CHANGES WITHIN THE SCOPE OF THE CONTRACT. |
| 2025-05-15 | PS0014 | Supplemental agreement (work within scope) | $445.4K | SUPPLEMENTAL AGREEMENT TO ADD WORK WITHIN SCOPE FOR ELECTRICAL AND SURVEY. LOCATION: NEW FORT LAUDERDALE CH GSA BLDG #: FL0514ZZ |
| 2025-04-07 | PS0013 | Supplemental agreement (work within scope) | $0 | ADD CD AND DRONE CLAUSES |
| 2025-02-18 | PA0012 | Administrative change | $0 | FLL COURTHOUSE PROJECT: ADMINISTRATIVE MODIFICATION TO CHANGE THE CO RESPONSIBILITIES ON FROM KAREN DRAKE TO RIC SOCHOR. |
| 2025-02-12 | PS0011 | Supplemental agreement (work within scope) | $5.5K | MOD PS0011 TO ADD WORK ACTIVITIES TO THE DB CONTRACT FOR THE NEW FORT LAUDERDALE COURTHOUSE PROJECT. THE WORK INVOLVES HAVING A BOUNDARY SURVEY CONDUCTED FOR USE BY FPL. THIS WILL ALLOW FPL TO BRING PERMANENT ELECTRICITY TO THE NEW BUILDING. |
| 2024-11-14 | PS0010 | Supplemental agreement (work within scope) | $1.68M | MODIFICATION PS0010 TO CONTRACT 47PE0323C0004 FOR NINE CHANGES TO THE NEW FORT LAUDERDALE CTHS PROJECT. THESE CHANGES VARY IN WHO REQUIRED THEM. SOME CHANGES WERE INITIATED BY GSA, SOME THE COURTS, AND ALSO INCLUDED ARE DIFFERING SITE CONDITIONS. |
| 2024-09-23 | PS0009 | Supplemental agreement (work within scope) | $1.26M | 47PE0323C0004, B&G CONTRACT FOR THE NEW FORT LAUDERDALE FL U. S. FEDERAL COURTHOUSE. BILATERAL MOD PS0009 SUPPLEMENTAL AGREEMENT IS ISSUED TO ADD VALUE TO THE CONTRACT FOR THE FOLLOWING CHANGES: PCOS 014, 018, 019, 020, 024, 026, AND 028 |
| 2024-06-06 | PS0008 | Supplemental agreement (work within scope) | $905.9K | FORT LAUDERDALE FL NEW DB U. S. FEDERAL COURTHOUSE PROJECT. MODIFICATION PS0008 PROVIDES AN EA FOR AN EXCUSABLE TIME IMPACT, BOTH DAYS AND TIME. ALSO, A SUPPLEMENTAL AGREEMENT FOR PCOS 011R AND 021. |
| 2024-02-12 | PS0007 | Supplemental agreement (work within scope) | $264.5K | 47PE0323C0004 - FORT LAUDERDALE NEW COURTHOUSE PROJECT. THIS SUPPLEMENTAL AGREEMENT PS0007 IS TO INCORPORATE PCO-017 FOR SITE RESTORATION |
| 2024-01-22 | PS0006 | Supplemental agreement (work within scope) | $771.2K | FORT LAUDERDALE NEW DB COURTHOUSE PROJECT. CONTRACT MODIFICATION PS0006 TO ADD CLINS 0011 AN 0012 TO ADD VALUE FOR PCOS 15 AND 16, AND TO DEDUCT VALUE FROM CLIN 0001 FOR PCO 04. |
| 2023-09-21 | PS0005 | Supplemental agreement (work within scope) | $282.1K | FORT LAUDERDALE FL - NEW DB COURTHOUSE PROJECT - PS0005, SUPPLEMENTAL AGREEMENT FOR PCO 06, ADDITIONAL COURTROOM SIGHT-LINE MOCK-UPS. |
| 2023-08-23 | PS0004 | Supplemental agreement (work within scope) | $4.62M | 47PE0323C0004, U. S. FEDERAL COURTHOUSE, FORT LAUDERDALE COURTHOUSE. PS0004 SUPPLEMENTAL AGREEMENT IS EXECUTED TO SETTLE PCOS 02, 07, 08, 09, AND 12 AND TO EXTEND THE SCD DATE BY 16 DAYS. |
| 2023-07-11 | PS0003 | Supplemental agreement (work within scope) | -$113.6K | FORT LAUDERDALE NEW FED CTHS PROJECT. PS003 IS A SUPPLEMENTAL AGREEMENT FOR A SERIES OF ADDS AND DEDUCTS TO THE AWARD INCLUDING BASE RECONCILIATION, PCO 01, BAS, PCO-03, DUCT BANK, AND PCO-05, FACADE STUDY. |
| 2023-05-26 | PS0001 | Supplemental agreement (work within scope) | $246.0K | MODIFICATION FOR EQUITABLE ADJUSTMENT DUE TO DOL DB WAGE CHANGE AT TIME OF AWARD. DB U. S. FEDERAL COURTHOUSE, FORT LAUDERDALE FL |
| 2023-01-31 | 0 | $196.31M | DESIGN-BUILD CONSTRUCTION SERVICES FOR A NEW U. S. FEDERAL BUILDING LOCATED AT FORT LAUDERDALE, FL 33316- |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗