DESIGN SERVICES FOR THE USDC COURTS AT THE LEXINGTON KY CTH TO RENOVATE/ALTER THE USDC JUDGE'S CHAMBER, COURTROOM, AND JURY SUITE.
Up for re-bid: ends 2026-10-31. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
10 actions since 2022-11-02. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-02-21 | PS0009 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO PROVIDE AT NO COST TO THE GOVERNMENT A PERIOD OF PERFORMANCE EXTENSION OF 270 CALENDAR DAYS FOR THE LEXINGTON, KY UNITED STATES DISTRICT COURTHOUSE LOCATED AT 101 BARR STREET IN LEXINGTON, KY 40507 |
| 2026-01-14 | PA0008 | Administrative change | $0 | ADMIN MODIFICATION TO UPDATE VENDOR INFORMATION AND CHANGE CONTRACTING OFFICER FOR U.S. DISTRICT COURTHOUSE DESIGN OF COURTROOM, JUDGES CHAMBER, AND JURY SUITE. IN THE LEXINGTON KY U.S. COURTHOUSE LOCATED AT 101 BARR STREET LEXINGTON, KY. |
| 2025-02-24 | PA0007 | Administrative change | $0 | LEXINGTON USDC COURTROOM/CHAMBERS & JURY SUITE PROJECT. THIS TASK ORDER IS FOR DESIGN & CMA SERVICES. THIS ADMIN MODIFICATION, PA0007, IS TO CHANGE THE GSA CONTRACTING OFFICER RESPONSIBILITY FROM KAREN DRAKE TO MR. CHEVETTE SUTTLE. |
| 2024-08-31 | PS0006 | Supplemental agreement (work within scope) | $0 | TASK ORDER 47PE0323F0001 TO GRIFFITH (TLC ENGINEERING) IS MODIFIED TO CORRECT/MATCH THE END DATE FOR PERIOD OF PERFORMANCE OF THE CMA SERVICES TO THE ESTIMATED DATE THE CONSTRUCTION WILL BE COMPLETED. |
| 2024-06-30 | PS0005 | Supplemental agreement (work within scope) | $0 | LEXINGTON KY USDC DESIGN PROJECT. MODIFICATION PS0005 IS ISSUED TO EXTEND THE PERIOD OF PERFORMANCE TO PROVIDE TIME TO NEGOTIATE CMA REDUCTION OF SCOPE AND SETTLE EQUITABLE ADJUSTMENT. |
| 2024-04-30 | PA0004 | Administrative change | $0 | TASK ORDER 47PE0323F0001, LEXINGTON USDC PROJECT. 100% DESIGN DOCUMENTS WERE RECEIVED ON 4/26/2024. THIS CONTRACT ACTION, MODIFICATION PA0004, IS TO EXTEND THE TIME FOR FINAL SETTLEMENT AND CLOSEOUT DUTIES. REA PENDING. |
| 2024-02-27 | PS0003 | Supplemental agreement (work within scope) | $0 | LEXINGTON KY - DESIGN FOR NEW USDC COURTROOM, CHAMBERS, AND JURY SUITE. BOTH PARTIES AGREE TO A ZERO COST EXTENSION TO THE DATE REQUIRED FOR 100% SUBMISSION. |
| 2023-10-26 | PS0002 | Supplemental agreement (work within scope) | $0 | LEXINGTON KY - DESIGN SERVICES FOR UDSC COURTROOM/CHAMBERS/JURY SUITE. MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE DUE TO TENANT REQUESTS FOR ADDITIONAL DESIGN OPTIONS. |
| 2023-08-07 | PS0001 | Supplemental agreement (work within scope) | $0 | LEXINGTON KY - USDC DESIGN FOR NEW USDC CHAMBERS, COURTROOM, AND JURY SUITE. MOD PS0001 IS ISSUED TO EXTEND THE DATE FOR 100% DESIGN SUBMITTAL. THIS EXTENSION IS DUE TO MULTIPLE DESIGN OPTIONS REQUESTED BY THE TENANT, USDC. |
| 2022-11-02 | 0 | $531.6K | DESIGN SERVICES FOR THE USDC COURTS AT THE LEXINGTON KY CTH TO RENOVATE/ALTER THE USDC JUDGE'S CHAMBER, COURTROOM, AND JURY SUITE. |