THIS REQUIREMENT IS FOR ADA RAMP REPAIRS AND A NEW ELEVATOR LOCATED AT THE COCHRAN CH, 501 EAST COURT STREET, JACKSON, MS.
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
11 actions since 2022-12-13. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-04-08 | PS0013 | Change order | $0 | MOD TO EXTEND POP THROUGH JUNE TO ALLOW PUNCHLIST TO BE COMPLETED. |
| 2025-10-23 | PS0012 | Supplemental agreement (work within scope) | $0 | THIS REQUIREMENT IS TO EXTEND THE PROJECT COMPLETION DATE BY 90 DAYS TO RESOLVE IT ISSUES REQUIRED FOR THE NEW ELEVATOR IN THE JACKSON FB MS0007ZZ. |
| 2025-09-12 | PS0011 | Supplemental agreement (work within scope) | -$25.6K | THIS MODIFICATION IS REQUIRED TO DECREASE THE FUNDING FOR UNNECESSARY WORK REQUIREMENTS, LOCATED AT THE JACKSON COURTHOUSE, JACKSON, MS. |
| 2025-03-20 | PS0010 | Supplemental agreement (work within scope) | $56.7K | THIS MODIFICATION IS REQUIRED TO EXTEND POP 60 DAYS CHANGE COR ADD CLIN 0005 AND FUNDING TO ADD REQUIRED MAD SYSTEM TO THE ELEVATOR AND MATCH STONE WORK FOR RAMP AT THE JACKSON CH MS0007ZZ. |
| 2025-02-25 | PS0009 | Supplemental agreement (work within scope) | $0 | THIS MODIFICATION IS TO EXTEND THE POP COMPLETION DATE 91 DAYS TO ALLOW TIME FOR EXTRA CONSTRUCTION FUNDING TO BE APPROVED AND APPLIED TO AWARD. PROJECT LOCATED IN JACKSON MS. |
| 2024-11-08 | PS0008 | Supplemental agreement (work within scope) | $35.7K | THIS AWARD MOD IS REQUIRED TO ADD FIRE ALARM SYSTEM CPU UPGRADE, REPLACE 10 LIGHT FIXTURES, AND EXTEND POP BY 126 DAYS FOR THE PROJECT LOCATED AT THE COCHRAN FB MS0007ZZ IN JACKSON, MS. |
| 2024-07-24 | PS0007 | Supplemental agreement (work within scope) | $5.3K | THIS MODIFICATION IS TO ADD CLIN 0003 AND FUNDING FOR THE ELEVATOR FIRE EGRESS FLOORING AND WAYFARING SIGNAGE FOR THE COCHRAN USCH IN JACKSON, MS. |
| 2024-05-08 | PS0006 | Supplemental agreement (work within scope) | $163.4K | THIS MODIFICATION IS REQUIRED TO INCREASE FUNDING FOR UNFORESEEN SITE CONDITIONS TO MEET CODE REQUIREMENTS AND EXTEND THE POP TO ALLOW FOR PROJECT COMPLETION. PROJECT LOCATION IS JACKSON, MS COCHRAN FB MS0007ZZ. |
| 2024-01-24 | PS0005 | Supplemental agreement (work within scope) | $0 | THIS REQUIREMENT IS TO EXTEND THE POP COMPLETION DATE BY 164 DAYS TO ALLOW FOR PROJECT COMPLETION DUE TO MULTIPLE DESIGN REVISIONS WERE REQUIRED. LOCATION JACKSON, MS. |
| 2023-06-21 | PS0004 | Supplemental agreement (work within scope) | $0 | THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE BY 210 DAYS FOR THE COCHRAN CH ADA RAMP REPAIR AND NEW ELEVATOR CONSTRUCTION LOCATED IN JACKSON, MS MS0007ZZ. |
| 2022-12-13 | PS0003 | Supplemental agreement (work within scope) | $0 | THIS REQUIREMENT IS TO CHANGE THE CO AND EXTEND THE PERIOD OF PERFORMANCE BY 84 DAYS TO ALLOW FOR PROJECT COMPLETION DUE TO UNFORESEEN CONDITIONS WHICH DELAYED THE START OF THE PROJECT. PROJECT LOCATION IS IN THE COCHRAN FB, JACKSON, MS. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗