47PE5526F0850↗

Jacobs Engineering Group Inc. received this contract from PBS Project Delivery Central - Branch E, Public Buildings Service: $412.2K obligated so far for architect and engineering- general: landscaping, interior layout, and designing. It runs to 2027-02-27.

Key facts · data as of Oct 26, 2026

Recipient
Jacobs Engineering Group Inc.
Awarding agency
Public Buildings Service (General Services Administration)
Contracting office
PBS Project Delivery Central - Branch E (47PE55)
Obligated to date
$412.2K
Potential value
$412.2K
Ends
2027-02-27

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.

Cite this page: SpendQuery, Award 47PE5526F0850, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_47PE5526F0850_4740_47PF0023D0006_4740

PROJECT TITLE - ATKINS - DYER UTILITIES SEPARATION STUDY LOCATION - DAVID W DYER FEDERAL BUILDING AND US COURTHOUSE AND C CLYDE ATKINS US COURTHOUSE

Delivery Order · Public Buildings Service · to Jacobs Engineering Group Inc. (UEI LKTBLK9RBZ53) · data as of 2026-10-26

Obligated to date$412.2K1 action
Current value$412.2Kwith options exercised
Period2026-10-30 → 2027-02-27current end date

Up for re-bid: ends 2027-02-27. Recompete brief →

What it is

Product or service
Architect and Engineering- General: Landscaping, Interior Layout, and Designing (PSC C211)
Industry
Architectural Services (NAICS 541310)
Contracting office
PBS Project Delivery Central - Branch E (47PE55)
Competition
Full and open competition · 1 offer received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under 47PF0023D0006
Solicitation
EQPMAE-26-0335
Where the work is
Miami-Dade, FL · district FL-27

Obligations by fiscal year

FY2026$412.2K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

1 action since 2026-09-30. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-300$412.2KPROJECT TITLE - ATKINS - DYER UTILITIES SEPARATION STUDY LOCATION - DAVID W DYER FEDERAL BUILDING AND US COURTHOUSE AND C CLYDE ATKINS US COURTHOUSE

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗