47PF0023F0403↗

Johnson Controls Government Systems, LLC received this contract from PBS Energy Division, Public Buildings Service: $10.74M obligated so far for special studies/analysis- building technology. It runs to 2030-08-31.

Key facts · data as of Oct 26, 2026

Recipient
Johnson Controls Government Systems, LLC
Awarding agency
Public Buildings Service (General Services Administration)
Contracting office
PBS Energy Division (47PA10)
Obligated to date
$10.74M
Potential value
$11.50M
Ends
2030-08-31

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.

Cite this page: SpendQuery, Award 47PF0023F0403, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_47PF0023F0403_4740_DEEE0008032_8900

ENERGY SAVINGS PERFORMANCE CONTRACT, NATIONAL DEEP ENERGY RETROFIT PROGRAM ROUND 5, NORTHERN OHIO FOR IMPLEMENTATION OF ENERGY CONSERVATION MEASURES AT MULTIPLE LOCATIONS.

Delivery Order · Public Buildings Service · to Johnson Controls Government Systems, LLC (UEI RXNUR4G46NG3) · data as of 2026-10-26

Obligated to date$10.74M12 actions
Current value$10.74Mwith options exercised
Potential value$11.50Mif every option is used
Period2023-03-20 → 2030-08-31current end date
Passed on$11.95Mto 3 subcontractors

What it is

Product or service
Special Studies/Analysis- Building Technology (PSC B540)
Industry
Engineering Services (NAICS 541330)
Contracting office
PBS Energy Division (47PA10)
Competition
Full and open competition · 9 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under DEEE0008032
Where the work is
Cuyahoga, OH · district OH-11

Obligations by fiscal year

FY2023$9.73M
FY2024$429.0K
FY2025$296.8K
FY2026$278.6K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

6 subawards totaling $11.95M (111.3% of what was obligated), as Johnson Controls Government Systems, LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.

SubcontractorAmountSubawardsWhereFirstLast
Lighting Retrofit International, LLC$5.95M2MD2023-06-272023-06-27
Southern Co Services Inc$5.89M2NC2023-04-282023-04-28
Onix, Inc.$111.8K2PA2023-04-262023-04-26
The largest single subawards
DateToAmountFor
2023-06-27Lighting Retrofit International, LLC$3.11MLIGHTING RETROFITS AND LOCAL OCCUPANCY SENSORS
2023-04-28Powersecure, Inc.$2.95MMECHANICAL, HVAC, LIGHTING, BUILDING ENVELOPE, ELECTRICAL
2023-04-28Powersecure, Inc.$2.95MMECHANICAL, HVAC, LIGHTING, BUILDING ENVELOPE, ELECTRICAL
2023-06-27Lighting Retrofit International, LLC$2.84MLIGHTING RETROFITS AND LOCAL OCCUPANCY SENSORS
2023-04-26Onix, Inc.$55.9KCOMMISSIONING
2023-04-26Onix, Inc.$55.9KCOMMISSIONING

Every action

12 actions since 2023-03-20. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-08-12PA0011Funding only$278.6KNATIONAL DEEP ENERGY RETROFIT ENERGY SAVINGS PERFORMANCE CONTRACT - STOKES U.S. COURTHOUSE AND 3 OTHER LOCATIONS IN NORTHERN OHIO. MODIFICATION PA0011 TO OBLIGATE THE PERFORMANCE YEAR 3 PAYMENT.
2026-06-16PS0010Supplemental agreement (work within scope)$0NATIONAL DEEP ENERGY RETROFIT ENERGY SAVINGS PERFORMANCE CONTRACT - 4 LOCATIONS IN NORTHERN OHIO. MODIFICATION PS0010 TO ACCEPT THE PERFORMANCE YEAR 1 ANNUAL REPORT.
2025-08-19PO0009Administrative change$264.3KN.OHIO ENERGY SAVINGS PERFORMANCE CONTRACT STOKES U.S. COURTHOUSE, CLEVELAND OHIO AND TWO OTHER BUILDINGS IN CLEVELAND. MODIFICATION PO0009 TO OBLIGATE THE PERFORMANCE YEAR 2 PAYMENT.
2025-06-11PS0008Supplemental agreement (work within scope)$0ENERGY SAVINGS PERFORMANCE CONTRACT STOKES U.S. COURTHOUSE AND 3 OTHER LOCATIONS IN CLEVELAND AND AKRON, OH MOD PS0008 TO ACCEPT THE POST INSTALLATION REPORT FOR THE PROJECT.
2025-05-07PS0007Supplemental agreement (work within scope)$0ENERGY SAVINGS PERFORMANCE CONTRACT STOKES U.S. COURTHOUSE AND 3 OTHER LOCATIONS IN CLEVELAND AND AKRON, OH MOD PS0007 TO EXTEND THE CONSTRUCTION PERIOD OF PERFORMANCE FOR ECM 5.1 FROM 4/30/25 TO 7/31/25.
2024-12-11PO0006Funding only-$13.2KNORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT MODIFICATION PO0006 REVISES THE AMOUNT OF FUNDING FOR THE CONSTRUCTION PERIOD SAVINGS.
2024-11-12PS0005Supplemental agreement (work within scope)$45.7KNORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT MODIFICATION PS0005 ALLOCATES ALL CONTINGENCY FUNDING AND OBLIGATES ADDITIONAL FUNDING TO SUPPORT SCOPE CHANGES FOR COURTROOM LIGHTING AT THE STOKES US COURTHOUSE, CLEVELAND, OHIO.
2024-09-06PO0004Funding only$132.1KNORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT 4 LOCATIONS, OHIO STOKES COURTHOUSE, CLEVELAND METZENBAUM COURTHOUSE, CLEVELAND SEIBERLING COURTHOUSE, AKRON LAMBROS COURTHOUSE, YOUNGSTOWN MODIFICATION PO0004 TO OBLIGATE CONSTRUCTION PERIOD PAYMENT
2024-08-15PO0003Funding only$296.9KNORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT 4 LOCATIONS, OHIO STOKES COURTHOUSE, CLEVELAND METZENBAUM COURTHOUSE, CLEVELAND SEIBERLING COURTHOUSE, AKRON LAMBROS COURTHOUSE, YOUNGSTOWN MODIFICATION PO0003 TO OBLIGATE PERFORMANCE YEAR 1 PAYMENT
2023-08-14PO0002Option exercised$23.6KNORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT CLEVELAND, AKRON, AND YOUNGSTOWN, OHIO MODIFICATION PO0002 TO EXERCISE OPTION 1
2023-05-17PS0001Supplemental agreement (work within scope)$0NORTHERN OHIO ENERGY PERFORMANCE SAVINGS CONTRACT NATIONAL DEEP ENERGY RETROFIT 5 STOKES FEDERAL BUILDING, CLEVELAND, OHIO, AND OTHER BUILDINGS IN CLEVELAND, AKRON, AND YOUNGSTOWN, OHIO MODIFICATION PS0001 FOR ASSIGNMENT OF CLAIMS
2023-03-200$9.71MENERGY SAVINGS PERFORMANCE CONTRACT, NATIONAL DEEP ENERGY RETROFIT PROGRAM ROUND 5, NORTHERN OHIO FOR IMPLEMENTATION OF ENERGY CONSERVATION MEASURES AT MULTIPLE LOCATIONS.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗