47PF0023F0403↗
Johnson Controls Government Systems, LLC received this contract from PBS Energy Division, Public Buildings Service: $10.74M obligated so far for special studies/analysis- building technology. It runs to 2030-08-31.
Key facts · data as of Oct 26, 2026
- Recipient
- Johnson Controls Government Systems, LLC
- Awarding agency
- Public Buildings Service (General Services Administration)
- Contracting office
- PBS Energy Division (47PA10)
- Obligated to date
- $10.74M
- Potential value
- $11.50M
- Ends
- 2030-08-31
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.
Cite this page: SpendQuery, Award 47PF0023F0403, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_47PF0023F0403_4740_DEEE0008032_8900
Johnson Controls Government Systems, LLC: all federal awards · General Services Administration: spending · PBS Energy Division: what it buys
ENERGY SAVINGS PERFORMANCE CONTRACT, NATIONAL DEEP ENERGY RETROFIT PROGRAM ROUND 5, NORTHERN OHIO FOR IMPLEMENTATION OF ENERGY CONSERVATION MEASURES AT MULTIPLE LOCATIONS.
What it is
- Product or service
- Special Studies/Analysis- Building Technology (PSC B540)
- Industry
- Engineering Services (NAICS 541330)
- Contracting office
- PBS Energy Division (47PA10)
- Competition
- Full and open competition · 9 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under DEEE0008032
- Where the work is
- Cuyahoga, OH · district OH-11
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
6 subawards totaling $11.95M (111.3% of what was obligated), as Johnson Controls Government Systems, LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Lighting Retrofit International, LLC | $5.95M | 2 | MD | 2023-06-27 | 2023-06-27 |
| Southern Co Services Inc | $5.89M | 2 | NC | 2023-04-28 | 2023-04-28 |
| Onix, Inc. | $111.8K | 2 | PA | 2023-04-26 | 2023-04-26 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2023-06-27 | Lighting Retrofit International, LLC | $3.11M | LIGHTING RETROFITS AND LOCAL OCCUPANCY SENSORS |
| 2023-04-28 | Powersecure, Inc. | $2.95M | MECHANICAL, HVAC, LIGHTING, BUILDING ENVELOPE, ELECTRICAL |
| 2023-04-28 | Powersecure, Inc. | $2.95M | MECHANICAL, HVAC, LIGHTING, BUILDING ENVELOPE, ELECTRICAL |
| 2023-06-27 | Lighting Retrofit International, LLC | $2.84M | LIGHTING RETROFITS AND LOCAL OCCUPANCY SENSORS |
| 2023-04-26 | Onix, Inc. | $55.9K | COMMISSIONING |
| 2023-04-26 | Onix, Inc. | $55.9K | COMMISSIONING |
Every action
12 actions since 2023-03-20. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-08-12 | PA0011 | Funding only | $278.6K | NATIONAL DEEP ENERGY RETROFIT ENERGY SAVINGS PERFORMANCE CONTRACT - STOKES U.S. COURTHOUSE AND 3 OTHER LOCATIONS IN NORTHERN OHIO. MODIFICATION PA0011 TO OBLIGATE THE PERFORMANCE YEAR 3 PAYMENT. |
| 2026-06-16 | PS0010 | Supplemental agreement (work within scope) | $0 | NATIONAL DEEP ENERGY RETROFIT ENERGY SAVINGS PERFORMANCE CONTRACT - 4 LOCATIONS IN NORTHERN OHIO. MODIFICATION PS0010 TO ACCEPT THE PERFORMANCE YEAR 1 ANNUAL REPORT. |
| 2025-08-19 | PO0009 | Administrative change | $264.3K | N.OHIO ENERGY SAVINGS PERFORMANCE CONTRACT STOKES U.S. COURTHOUSE, CLEVELAND OHIO AND TWO OTHER BUILDINGS IN CLEVELAND. MODIFICATION PO0009 TO OBLIGATE THE PERFORMANCE YEAR 2 PAYMENT. |
| 2025-06-11 | PS0008 | Supplemental agreement (work within scope) | $0 | ENERGY SAVINGS PERFORMANCE CONTRACT STOKES U.S. COURTHOUSE AND 3 OTHER LOCATIONS IN CLEVELAND AND AKRON, OH MOD PS0008 TO ACCEPT THE POST INSTALLATION REPORT FOR THE PROJECT. |
| 2025-05-07 | PS0007 | Supplemental agreement (work within scope) | $0 | ENERGY SAVINGS PERFORMANCE CONTRACT STOKES U.S. COURTHOUSE AND 3 OTHER LOCATIONS IN CLEVELAND AND AKRON, OH MOD PS0007 TO EXTEND THE CONSTRUCTION PERIOD OF PERFORMANCE FOR ECM 5.1 FROM 4/30/25 TO 7/31/25. |
| 2024-12-11 | PO0006 | Funding only | -$13.2K | NORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT MODIFICATION PO0006 REVISES THE AMOUNT OF FUNDING FOR THE CONSTRUCTION PERIOD SAVINGS. |
| 2024-11-12 | PS0005 | Supplemental agreement (work within scope) | $45.7K | NORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT MODIFICATION PS0005 ALLOCATES ALL CONTINGENCY FUNDING AND OBLIGATES ADDITIONAL FUNDING TO SUPPORT SCOPE CHANGES FOR COURTROOM LIGHTING AT THE STOKES US COURTHOUSE, CLEVELAND, OHIO. |
| 2024-09-06 | PO0004 | Funding only | $132.1K | NORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT 4 LOCATIONS, OHIO STOKES COURTHOUSE, CLEVELAND METZENBAUM COURTHOUSE, CLEVELAND SEIBERLING COURTHOUSE, AKRON LAMBROS COURTHOUSE, YOUNGSTOWN MODIFICATION PO0004 TO OBLIGATE CONSTRUCTION PERIOD PAYMENT |
| 2024-08-15 | PO0003 | Funding only | $296.9K | NORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT 4 LOCATIONS, OHIO STOKES COURTHOUSE, CLEVELAND METZENBAUM COURTHOUSE, CLEVELAND SEIBERLING COURTHOUSE, AKRON LAMBROS COURTHOUSE, YOUNGSTOWN MODIFICATION PO0003 TO OBLIGATE PERFORMANCE YEAR 1 PAYMENT |
| 2023-08-14 | PO0002 | Option exercised | $23.6K | NORTHERN OHIO ENERGY SAVINGS PERFORMANCE CONTRACT CLEVELAND, AKRON, AND YOUNGSTOWN, OHIO MODIFICATION PO0002 TO EXERCISE OPTION 1 |
| 2023-05-17 | PS0001 | Supplemental agreement (work within scope) | $0 | NORTHERN OHIO ENERGY PERFORMANCE SAVINGS CONTRACT NATIONAL DEEP ENERGY RETROFIT 5 STOKES FEDERAL BUILDING, CLEVELAND, OHIO, AND OTHER BUILDINGS IN CLEVELAND, AKRON, AND YOUNGSTOWN, OHIO MODIFICATION PS0001 FOR ASSIGNMENT OF CLAIMS |
| 2023-03-20 | 0 | $9.71M | ENERGY SAVINGS PERFORMANCE CONTRACT, NATIONAL DEEP ENERGY RETROFIT PROGRAM ROUND 5, NORTHERN OHIO FOR IMPLEMENTATION OF ENERGY CONSERVATION MEASURES AT MULTIPLE LOCATIONS. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗