Subcontractors: where the money went next
11 subawards totaling $14.08M (46.5% of what was obligated), as Ross Group Construction Corporation, LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
16 actions since 2023-09-22. Each is a modification or amendment with the money it added or took back.
Date
Modification
Kind
Amount
What the agency wrote
2026-06-02
PS0015
Supplemental agreement (work within scope)
$497.1K
THIS MODIFICATION SERVES TO INCORPORATE A REVISED SCOPE OF WORK DUE TO DESIGN DEFICIENCES AND OTHER REQUESTED CHANGES FOR THE CAPITAL SECURITY PROGRAM AND COURTS CONSTRUCTION PROJECT LOCATED AT 515 MURRAY STREET, ALEXANDRIA, LOUISIANA 71301.
2026-02-26
PS0014
Supplemental agreement (work within scope)
$164.8K
THIS MODIFICATION SERVES TO INCOPORATE A REVISED SCOPE OF WORK FOR ADDITIONAL WORK/CHANGES INTO THIS TASK ORDER FOR THE CAPITAL SECURITY PROGRAM AND COURTS CONSTRUCTION PROJECT LOCATED AT 515 MURRAY STREET, ALEXANDRIA, LOUISIANA 71301.
2025-11-03
PS0013
Supplemental agreement (work within scope)
$12.1K
THIS MODIFICATION SERVES TO INCORPORATE A REVISED SCOPE OF WORK FOR ADDITIONAL WORK/CHANGES INTO THIS TASK ORDER FOR THE CAPITAL SECURITY PROGRAM AND COURTS CONSTRUCTION PROJECT, LOCATED AT 515 MURRAY STREET, ALEXANDRIA, LOUISIANA 71301.
2025-09-17
PS0012
Supplemental agreement (work within scope)
$29.0K
THIS MODIFICATION SERVES TO INCORPORATE A REVISED SCOPE OF WORK INTO THIS TASK ORDER FOR ADDITIONAL WORK/CHANGES FOR THE CAPITAL SECURITY PROGRAM AND COURTS CONSTRUCTION PROJECT LOCATED AT 515 MURRAY STREET, ALEXANDRIA, LOUISIANA 71301.
2025-07-31
PS0011
Supplemental agreement (work within scope)
$12.7K
THIS MODIFICATION SERVES TO INCORPORATE A REVISED SCOPE OF WORK FOR ADDITIONAL WORK/CHANGES, INTO THIS TASK ORDER FOR THE CAPITAL SECURITY PROGRAM AND COURTS CONSTRUCTION PROJECT, LOCATED AT THE UNITED STATES COURTHOUSE IN ALEXANDRIA, LA.
2025-04-03
PS0010
Supplemental agreement (work within scope)
$23.1K
THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE A REVISED SCOPE OF WORK (DIFFERING SITE CONDITIONS) INTO THIS TASK ORDER FOR THE CAPITAL SECURITY PROGRAM AND COURTS CONSTRUCTION PROJECT, LOCATED AT THE UNITED STATES COURTHOUSE IN ALEXANDRIA, LA.
2025-02-25
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
2024-02-16
Masonry IV Inc
$2.37M
CMU
2023-10-18
Aca Mechanical/Industrial, L.L.C.
$2.03M
HVAC SYSTEM
2024-06-28
Firetrol Protection Systems, Inc
$1.48M
FIRE SUPPRESSION
2024-06-12
Johnson Drywall Solutions Inc
$881.3K
DRYWALL ASSEMBLIES
2024-05-16
Abg Caulking Contractors, Inc.
$861.5K
JOINT SEALANTS
2024-05-16
Abg Caulking Contractors, Inc.
$861.5K
JOINT SEALANTS
2024-04-19
El Dorado Glass & Mirror Co
$861.0K
ENTRANCES AND STOREFRONTS
2024-02-16
Orion Environmental, LLC
$444.6K
DEMOLITION
2024-02-16
Orion Environmental, LLC
$444.6K
DEMOLITION
2024-04-02
Darkhorse Industries, L.L.C
$32.3K
DEMOLITION
PS0009
Supplemental agreement (work within scope)
$10.8K
CAPITAL SECURITY PROGRAM AND COURTS CONSTRUCTION AT THE US COURTHOUSE IN ALEXANDRIA, LA. SUPPLIMENTAL MODIFICATION FOR ELECTRICAL, FLOORING, AND BLOCKING.
2024-11-06
PS0008
Supplemental agreement (work within scope)
$4.7K
LOBBY KIOSK CHANGES AT THE US COURTHOUSE IN ALEXANDRIA, LA.
2024-09-26
PS0007
Supplemental agreement (work within scope)
-$3.2K
FINALIZE PRICING TO RE-ROUTE GAS LINE AT THE US COURTHOUSE IN ALEXANDRIA, LA
2024-08-05
PC0006
Change order
$47.0K
RE-ROUTE EXISTING GAS LINE AT THE US COURTHOUSE IN ALEXANDRIA, LA
2024-07-24
PS0005
Supplemental agreement (work within scope)
$20.7K
ASBESTOS ABATEMENT AT THE US COURTHOUSE IN ALEXANDRIA, LA
2024-06-10
PS0004
Supplemental agreement (work within scope)
$9.7K
TEMPORARY RELOCATION OF GUARD BOOTH AT THE US COURTHOUSE IN ALEXANDRIA, LA.
2024-06-06
PS0003
Supplemental agreement (work within scope)
$788
PERIMETER FENCING REVISIONS AT THE US COURTHOUSE IN ALEXANDRIA, LA
2024-01-03
PS0002
Supplemental agreement (work within scope)
$0
ESTABLISH FULL NOTICE TO PROCEED AND NEW COMPLETION DATE FOR THE US COURTHOUSE IN ALEXANDRIA, LA
2023-12-20
PS0001
Supplemental agreement (work within scope)
$97.2K
CAST STONE VENEER AT THE US COURTHOUSE IN ALEXANDRIA, LA
2023-09-22
0
$29.39M
CAPITAL SECURITY PROGRAM AND COURTS CONSTRUCTION AT THE US COURTHOUSE IN ALEXANDRIA, LA