Date
Modification
Kind
Amount
What the agency wrote
2026-09-02
PS0017
Supplemental agreement (work within scope)
$365.9K
THIS MODIFICATION IS TO UPDATE THE DETENTION SUITE WALL MATERIAL AND TO DEFINITIZE PC0012 ASBESTOS CONTAINING MATERIAL AT THE LOADING DOCK BUILDING FOR THE GATEWAY LAND PORT OF ENTRY MODERNIZATION PROJECT IN BROWNSVILLE, TEXAS.
2026-08-27
PC0016
Change order
$100.0K
THIS UNILATERAL MODIFICATION IS TO ALLOW THE CONTRACTOR TO PROCEED WITH RESOLVING UNFORESEEN SOIL CONDITIONS DISCOVERED AT THE JOBSITE DURING EXCAVATION FOR THE GATEWAY LAND PORT OF ENTRY MODERNIZATION PROJECT IN BROWNSVILLE, TEXAS.
2026-08-12
PS0015
Supplemental agreement (work within scope)
$240.7K
THIS MODIFICATION IS FOR ACQUISITION OF A NEW INCINERATOR FOR THE BROWNSVILLE GATEWAY LAND PORT OF ENTRY MODERNIZATION PROJECT IN BROWNSVILLE, TX.
2026-06-30
PC0014
Change order
$50.0K
MODIFICATION PC0014 IS TO ALLOW THE CONTRACTOR TO PROCEED WITH RESOLVING UNFORESEEN CONDITIONS DISCOVERED AT THE JOBSITE DURING DEMOLITION/UNDERGROUND UTILITY DEMOLITION FOR THE GATEWAY LAND PORT OF ENTRY MODERNIZATION PROJECT IN BROWNSVILLE, TEXAS.
2026-06-16
PS0013
Supplemental agreement (work within scope)
$555.4K
THIS MODIFICATION IS FOR ADDITIONAL SCOPE FOR SUBMETERING, OPERATIONS AND MAINTENANCE SPACE BUILD OUT, AND AT&T TELEPHONE LINE FOR THE GATEWAY LAND PORT OF ENTRY MODERNIZATION PROJECT, BROWNSVILLE, TEXAS.
2026-06-08
PC0012
Change order
$100.0K
THIS PRICE DETERMINED LATER MODIFICATION IS TO ALLOW THE CONTRACTOR TO PROCEED WITH ASBESTOS CONTAINING MATERIAL (ACM) ABATEMENT AT THE LOADING DOCK FOR THE GATEWAY LAND PORT OF ENTRY MODERNIZATION, BROWNSVILLE, TEXAS.
2026-04-08
PS0011
Supplemental agreement (work within scope)
$149.4K
THIS MODIFICATION IS FOR ASBESTOS RECONCILIATION, HSDN ROOM UPDATES, AND PERSONNEL CHANGES FOR THE GATEWAY LAND PORT OF ENTRY MODERNIZATION PROJECT IN BROWNSVILLE, TEXAS.
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
2026-02-12
PS0010
Supplemental agreement (work within scope)
$153.9K
THIS MODIFICATION IS TO INCORPORATE MISCELLANEOUS DESIGN CHANGES TO INCLUDE ADDITIONAL BOLLARDS, HOSE BIBS AND VEHICLE ACCESS GATE FOR THE GATEWAY LAND PORT OF ENTRY MODERNIZATION IN BROWNSVILLE, TEXAS.
2026-02-06
PS0009
Supplemental agreement (work within scope)
$175.1K
THIS MODIFICATION IS TO ENHANCE THE SECURITY MEASURES PROVIDED AROUND THE TEMPORARY PARKING FACILITIES PROVIDED FOR THE PROJECT DURING CONSTRUCTION FOR THE GATEWAY LAND PORT OF ENTRY MODERNIZATION PROJECT, BROWNSVILLE, TEXAS
2025-10-30
PS0008
Supplemental agreement (work within scope)
-$782.3K
RESCISSION OF PBS P100 FACILITIES STANDARDS, AND ISSUANCE OF PBS INTERIM CORE BUILDING STANDARDS FOR THE GATEWAY LAND PORT OF ENTRY MODERNIZATION, BROWNSVILLE, TEXAS
2025-09-25
PS0007
Supplemental agreement (work within scope)
$0
THIS MODIFICATION IS TO INCORPORATE THE NO COST PROGRAM CHANGES FROM THE DESIGN PHASE ITEM CHANGE (DPIC) - 008 INTO THE GATEWAY LAND PORT OF ENTRY MODERNIZATION PROJECT, BROWNSVILLE, TEXAS.
2025-07-24
PS0006
Supplemental agreement (work within scope)
-$262.5K
THIS MODIFICATION IS TO PROVIDE THE GOVERNMENT WITH A CREDIT FOR Z-PORTAL DELETION AND REMOVAL OF OFFICE OF FEDERAL CONTRACT COMPLIANCE PROGRAMS (OFCCP) COORDINATION FROM THE GATEWAY LAND PORT OF ENTRY (LPOE) MODERNIZATION PROJECT IN BROWNSVILLE, TX.
2025-05-29
PS0005
Change order definitized
$1.8K
THIS MODIFICATION IS TO DEFINITIZE PC0002 AND PC0003 FOR DESIGN BUILDING CONSTRUCTION OF THE BROWNSVILLE GATEWAY MODERNIZATION PROJECT IN BROWNSVILLE, TX
2025-04-30
PS0004
Supplemental agreement (work within scope)
$0
THIS MODIFICATION IS TO INCORPORATE THE CBP NO COST IMPACT ITEMS INTO THE BROWNSVILLE GATEWAY TASK ORDER. THE TASK ORDER IS FOR DESIGN BUILD SERVICES FOR COMPLETE MODERNIZATION OF THE GATEWAY LAND PORT OF ENTRY IN BROWNSVILLE, TEXAS.
2025-03-19
PC0003
Change order
$1.4K
MODIFICATION IS FOR THE DESIGN BUILD CONTRACTOR TO EXTEND THE TIME FOR A LICENSED ARCHEOLOGIST TO PERFORM MONITORING DURING GEOTECHNICAL INVESTIGATIONS FOR THE GATEWAY BROWNSVILLE MODERNIZATION PROJECT IN BROWNSVILLE, TEXAS.
2025-03-11
PC0002
Change order
$10.5K
MODIFICATION IS FOR THE DESIGN BUILD CONTRACTOR TO HIRE A LICENSED ARCHEOLOGIST TO PERFORM MONITORING DURING GEOTECHNICAL INVESTIGATIONS FOR THE GATEWAY BROWNSVILLE MODERNIZATION PROJECT IN BROWNSVILLE, TEXAS.
2025-02-19
PS0001
Supplemental agreement (work within scope)
$0
MODIFICATION TO ISSUE NOTICE TO PROCEED FOR THE DESIGN BUILD CONSTRUCTION MODERNIZATION OF THE GATEWAY LAND PORT OF ENTRY, BROWNSVILLE, TEXAS.
2024-12-13
0
$263.91M
DESIGN BUILD CONSTRUCTION FOR GATEWAY LAND PORT OF ENTRY MODERNIZATION PROJECT, BROWNSVILLE, TX.